Proposed Tech Specs,Modifying Section 4.6.6.2.b.4 Re Hydrogen Recombiner by Changing Heater Resistance to Ground Testing Requirement
ML20133F228
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 08/02/1985
From:
GEORGIA POWER CO.
To:
Shared Package
ML20133F202 List:
References
TAC-59335, NUDOCS 8508080193
Download: ML20133F228 (5)


Text

(

ATTACHMENT 4 NRC DOCKET 50-366 OPERATING LICENSE NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNIT 2 REQUEST TO REVISE TECHNICAL SPECIFICATIONS:

REVISE HYDROGEN RECOMBINER HEATER INTEGRITY TEST SPECIFICATION The proposed changes to Technical Specifications (Appendix A to Operating License NPF-5) would be incorporated as follows:

Remove Page Insert Page 3/4 6-43 3/4 6-43 w.

e 8500000193 850002 PDR ADOCK 05000366 P

PDR

~

, i. 3.-

00NTADNEth* SYSTEMS 9

PRIMARY-00Nrf.INMENT HYDROGEN REQNBINER SYSTEMS LIMITING CONDITION FOR OPERATION 3.6.6.2 Two indepe M ent primary containment hydrogen recombiner systems shall be OPERABLE.

APPLICABILITY: CONDITIONS 1 and 2.

ACTION With one hydrogen recombiner system inoperable, restore the inoper-a.

j able system to OPERABLE status within 30 days or be in at least HOT SHlfrDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The provisions of Specification 3.0.4 are not applicable.

b.

With both hydrogen recombiner systems inoperable, be in at least H0ff SHTIDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

^

SURVEILLANCE REQllIREMENTS-4.6.6.2 Each hydrogen recombiner system shall be demonstrated OPERABLE:

At least once per 6 months by verifying during a recombiner a.

system functional test 'that the ministmi heater sheath temperature increases to > 6000F within 60 minutes and is maintained for at least 2 hoiirs.

b.

At least once per 18 months by:

1.

Performing a OIANNEL CALIBRATION of all recombiner instru-mentation and control circuits.

2.

Verifying through a visual examination that there is no evidence of abnonnal conditions within the recombiners 4

+-

(i.e., loose wiring or structural connections, deposits

'l of foreign materials, etc.)

t 3.

Veritying during a recombiner system functional test that the heater sheath temperature increases to > 1200'F within 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> and is maintained between T1500F and 13000F for at least 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

4 Verifying the integrity of all heater electrical circuits by perfonning a continuity and resistance to ground test i

following the above required functional test. The resis 6 tance to ground for any heater element shall be > 1.0 x 10 l

j ohms.

i i