Deficiency Rept Re Misoperation of GE SAM Relays.Site Delivery of Mod Parts Delayed.Corrective Actions Will Be Completed by 851001 Instead of 850731
ML20132F910
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 07/01/1985
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
(NMP2L-0437), (NMP2L-437), NUDOCS 8507190079
Download: ML20132F910 (1)


Text

NUMOHAWK Y NIAGARA NIAGARA MOHAWK POWER CORPORATION /300 ER;E BOULEVARD WEST SYRACUSE. N Y.13202/TELEPHcNE (315) 474-1511 July 1, 1985 (NMP2L 0437)

Mr. R. W. Starostecki, Director U.S. Nuclear Regulatory Commission Region I Division of Reactor Projects 631 Park Avenue King of Prussia, PA 19406 Re:

Nine Mile Point - Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

The corrective action to a

reported deficiency concerning the misoperation of General Electric " SAM" relays (Deficiency No. 84-27) was to be completed by July 31, 1985.

This date was based on site delivery of modification parts by early in 1985.

Due to difficulties in obtaining the required Quality Assurance Category I certifications, the projected site delivery date has changed to August 2, 1985.

Therefore, the corrective action is now scheduled for completion by October 1, 1985.

Very truly yours, C. V. Mangan Vice President Nuclear Engineering and Licensing CVM/GG/cla xc: