. George Power Company

, 40 invemess Center Parkway Post OffK.e Box 1295 Birmingham, Alabama 35201 Telephone 205 992-7122 m

GeorgiaPOwer V P es ent, Nuclear Vogtle Project December 19, 1996 Docket Nos. 50-424 LCV-0606-E 50-425 TAC Nos. M84531

^ M84532 U. S. Nuclear Regulatory Commission 5- ATTN: Document Control Desk y- Washington, DC 20555 3j M

VOGTLE ELECTRIC GENERATING PLANT UPDATED INFORMATION FOR LICENSE AMENDMENTS APPLICATION f SOUTHERN NUCLEAR TO BECOME THE LICENSED OPER.ATOR Gentlemen:

, On September 18,1992, Georgia Power Company (GPC) submitted an application to amend Facility Operating License (FOL) Nos. NPF-68 and NPF-81 which would c authorize Southern Nuclear Operating Company, Inc. (Southern Nuclear) to become 1 the licensed operator and have exclusive responsibility and control over the physical

construction, operation, and raaintenance of Vogtle Electric Generating Plant, Unit 1 f- and Unit 2 (VEGP). By letters to the NRC dated October 7,1992, October 15,1992, September 11,1996 and Duember 12,1996, GPC supplemented or provided information related to this application.

In response to telephone conversations this week, GPC is informing the hTC that certain planned activities which were communicated in the application have been completed. Pursuant to the Nuclear Operating Agreement between GPC and Southern Nuclear, the companies have entered into a number of service plans which provide for g the performance of services by GPC after the license transfer occurs. Specifically, as Y' stated in the application "Following the reassignment ofoperating responsibilities to Southern Nuclear, a sign.ficant amount of off-site emergency planning support, including communication with the public, will be provided by Georgia Power Company." The service plans between Georgia Power Company and Southern Nuclear iM

\

to assure these services will be performed have been duly executed.

9612260066 961219 PDR ADOCK 05000424 P PDR

r .-

GeorgiaPower mL U. S. Nuclear Regulatory Commission Page Two Similarly, as stated in the application, " Pursuant to this requirement (GDC-17),

Southern Nuclear will enter into agreements with Georgia Power Company specifying:

(1) the arrangements for provision of a continued source of off-site power, (2) the arrangements for controlling operation, maintenance, repair, and other activities with respect to the transmission lines and the switchyard in the Exclusion Area, and (3) a requirement that Georgia Power Company obtain approval from Southern Nuclear prior to implementing any changes to the equipment located in the Exclusion Area."

The service plan between Georgia Power Company and Southern Nuclear to assure these services will be performed has been duly executed.

In accordance with 10 CFR 50.91, the designated State official will be sent a copy of this letter.

Sincerely, C. K. McCoy 1

CKM/JMG l

cc: Georeia Power Company ~

1 Mr. H. A. Franklin Mr. W. G. Hairston, III Mr. J. D. Woodard Mr. J. B. Beasley Mr. M. Sheibani NORMS l

U. S. Nuclear Rezidatory Commission Mr. S. D. Ebneter, Regional Administrator Mr. L. L. Wheeler, Licensing Project Manager, NRR Mr. C. R. Ogle, Senior Resident Inspector, Vogtle State of Georgia Mr. L. C. Barrett, Commissioner, Departmerd of Natural Resources l

LCV-0606-E