ML20132E516
ML20132E516 | |
Person / Time | |
---|---|
Site: | Oconee, 05000000 |
Issue date: | 03/27/1985 |
From: | DUKE POWER CO., NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
To: | |
Shared Package | |
ML20132E501 | List: |
References | |
50-269-84-31, 50-270-84-31, 50-287-84-35, NUDOCS 8507170727 | |
Download: ML20132E516 (3) | |
Category:SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
MONTHYEARIR 05000269/19900241990-10-0202 October 1990
[Table view]SALP Repts 50-269/90-24,50-270/90-24,50-287/90-24 & 72-0004/90-24 for Feb 1989 - Jul 1990 IR 05000413/19880241988-10-13013 October 1988 SALP Repts 50-413/88-24 & 50-414/88-24 for Aug 1987 - Jul 1988 IR 05000369/19880211988-10-13013 October 1988 SALP Repts 50-369/88-21 & 50-370/88-21 for Aug 1987 - Jul 1988 IR 05000354/19860991988-03-0404 March 1988 SALP Rept 50-354/86-99 on 861201-880115 IR 05000272/19860991988-02-0505 February 1988 SALP Repts 50-272/86-99 & 50-311/86-99 for Oct 1986 - Dec 1987 IR 05000324/19870191987-09-23023 September 1987 SALP Repts 50-324/87-19 & 50-325/87-19 for Nov 1985 - June 1987 IR 05000250/19860271986-12-0101 December 1986 SALP Repts 50-250/86-27 & 50-251/86-27 for Nov 1984 - Apr 1986 IR 05000335/19860131986-12-0101 December 1986 SALP Repts 50-335/86-13 & 50-389/86-12 for Nov 1984 - Apr 1986 IR 05000352/19850991986-06-0606 June 1986 SALP Rept 50-352/85-99 for Dec 1984 - Jan 1986 IR 05000213/19850991985-08-13013 August 1985 Revised SALP Rept 50-213/85-99 for Sept 1983 - Feb 1985, Modifying Discussion Re Deviations from Normal QA Requirements & after-the-fact Determinations of Quality IR 05000424/19850271985-06-30030 June 1985 SALP Repts 50-424/85-27 & 50-425/85-26 for Nov 1983 - June 1985 ML20198A7001985-06-30030 June 1985 SALP Repts 50-321/85-21 & 50-366/85-21 for Nov 1983 - June 1985 IR 05000245/19850991985-05-0606 May 1985 SALP Repts 50-245/85-99 & 50-336/85-99 for Sept 1983 - Feb 1985 ML20128B2731985-04-23023 April 1985 SALP Rept 50-213/85-99 for Sept 1983 - Feb 1985 ML20132E5161985-03-27027 March 1985 App to SALP Repts 50-269/84-31,50-270/84-31 & 50-287/84-35 for May 1983 - Aug 1984 ML20132E5661985-03-27027 March 1985 App to SALP 50-369/84-36 & 50-370/84-34 for May 1983 - Aug 1984,consisting of Errata Sheet,Corrected Pages 7,8,9,15 & 26 & 850108 Meeting Summary IR 05000369/19840361984-12-31031 December 1984 SALP Repts 50-369/84-36 & 50-370/84-34 for May 1983 - Aug 1984 IR 05000269/19840311984-12-31031 December 1984 SALP Repts 50-269/84-31,50-270/84-31 & 50-287/84-35 for May 1983 - Aug 1984 ML20054M1141982-07-0202 July 1982 Forwards Systematic Assessment of Licensee Performance for Jul 1980-June 1981.Mgt Attention at Facilities Agressively Oriented Toward Nuclear Safety IR 05000546/19820071982-06-30030 June 1982 SALP Repts 50-546/82-07 & 50-547/82-07 for Jul 1980 - Sept 1981 ML20134A9821981-01-0808 January 1981 SALP Repts for Apr 1979 - Aug 1980 ML20210P1301980-10-0909 October 1980 SALP Repts for Periods May 1979 - Apr 1980 & Sept 1979 - Aug 1980 1990-10-02 Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS MONTHYEARPNO-II-97-065, on 971228,initiated Controlled Shutdown of Unit Due to Exceeding TS Leakage Limit of 150 Gpd.Licensee Continuing W/Plant Depressurization & Cooldown & Outage Planned of Several Days to Investigate & Repair SG1997-12-29029 December 1997
[Table view]PNO-II-97-065:on 971228,initiated Controlled Shutdown of Unit Due to Exceeding TS Leakage Limit of 150 Gpd.Licensee Continuing W/Plant Depressurization & Cooldown & Outage Planned of Several Days to Investigate & Repair SG ML20211K9431997-09-26026 September 1997 Notice of Violation from Insp on 970721-26.Violation Noted: Licensee Failed to Follow Procedures for Security Badges & Access Control of Facility ML20210S0391997-08-27027 August 1997 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $330,000.Violation Noted:Between 970501-02,w/ Fuel in Oconee Unit 3 Core & RCS Temp Greater than 350 F, Licensee Failed to Maintain HPI Sys Operable as Required PNO-II-97-034, on 970613,extended Shutdown to Meet CAL 2-97-03 Commitments to Shutdown Unit 1 No Later than 970614 & to Implement Actions Re HPI Sys.Nrc Resident Inspector Will Followup on Unit 1 Shutdown & Recovery Activities1997-06-13013 June 1997 PNO-II-97-034:on 970613,extended Shutdown to Meet CAL 2-97-03 Commitments to Shutdown Unit 1 No Later than 970614 & to Implement Actions Re HPI Sys.Nrc Resident Inspector Will Followup on Unit 1 Shutdown & Recovery Activities IR 05000269/19930321994-01-0606 January 1994 Insp Repts 50-269/93-32,50-270/93-32,50-287/93-32, 50-369/93-31,50-370/93-31,50-413/93-35 & 50-414,respectively on 931213-17.Violations Noted.Major Areas Inpected:Licensee Safeguards Info Program to folow-up on Licensee Repts PNO-II-93-039, on 930823,reactor Trip Occurred Due to Loss of Power to Vital Panelboard.Investigation Team Dispatched to Site to Review Root Cause & Plant Response.State & Local Authorities Notified1993-08-24024 August 1993 PNO-II-93-039:on 930823,reactor Trip Occurred Due to Loss of Power to Vital Panelboard.Investigation Team Dispatched to Site to Review Root Cause & Plant Response.State & Local Authorities Notified IR 05000269/19930061993-03-22022 March 1993 Partially Withheld Insp Repts 50-269/93-06,50-270/93-06 & 50-287/93-06 on 930222-25 (Ref 10CFR73.21).No Violations or Deviations Noted.Major Areas Inspected:Licensee Physical Security Program for Power Reactors IR 05000269/19930011993-02-0101 February 1993 Safeguards Insp Repts 50-269/93-01,50-270/93-01 & 50-287/93-01 on 930104-07.No Violations Noted.Major Areas Inspected:Physical Security Program.Details Withheld (Ref 10CFR73.21) IR 05000269/19920251992-12-0303 December 1992 Insp Repts 50-269/92-25,50-270/92-25 & 50-287/92-25 on 921102-06.No Violations or Deviations Noted.Major Areas Inspected:Physical Security Program for Power Reactors, Audits,Protected & Vital Area Barriers.Details Withheld PNO-II-92-070, on 921019,several Circuit Breakers Failed in 230KV Switchyard to Open Position for Unknown Reasons. Licensee Has Inititated Investigation to Review Event to Determine Cause & Determine Why Certain Equipment Failed1992-10-20020 October 1992 PNO-II-92-070:on 921019,several Circuit Breakers Failed in 230KV Switchyard to Open Position for Unknown Reasons. Licensee Has Inititated Investigation to Review Event to Determine Cause & Determine Why Certain Equipment Failed PNO-II-91-074B, on 911123,unit Remained in Cold Shutdown,Per Declaration of Alert at 0214 Due to Leak in Rcs.As of 911126,total of 7,800 Gallons of Treated Water Released from Plant to Lake Hartwell1991-11-26026 November 1991 PNO-II-91-074B:on 911123,unit Remained in Cold Shutdown,Per Declaration of Alert at 0214 Due to Leak in Rcs.As of 911126,total of 7,800 Gallons of Treated Water Released from Plant to Lake Hartwell ML20134D2581991-06-0404 June 1991 Notice of Violation from Insp on 910312-15.Violations Noted:Station Was Not Maintained According to Main Procedure MP/0/A/1800/105,Section 6.5,which Clearly Identified That Flange Was to Be Installed on Valve 3LP19 IR 05000269/19910081991-04-10010 April 1991 Insp Repts 50-269/91-08,50-270/91-08 & 50-287/91-08 on 910312-15.violations Noted.Major Areas Inspected:Maint, Control Room Operation,Planning & Scheduling Activities, Training & Procedures,Plant Physical Condition & Mgmt PNO-II-90-070, on 901108,unit Commenced Controlled Shutdown from 60% Power Due to Tube Leak in Steam Generator a1990-11-0808 November 1990 PNO-II-90-070:on 901108,unit Commenced Controlled Shutdown from 60% Power Due to Tube Leak in Steam Generator a IR 05000269/19900321990-11-0505 November 1990 Partially Withheld Insp Repts 50-269/90-32,50-270/90-32 & 50-287/90-32 on 901015-19.No Violations Noted.Major Areas Inspected:Physical Security Program Plans,Mgt Support, Security Program Plans & Protected & Vital Area Barriers IR 05000269/19900241990-10-0202 October 1990 SALP Repts 50-269/90-24,50-270/90-24,50-287/90-24 & 72-0004/90-24 for Feb 1989 - Jul 1990 IR 05000269/19900221990-07-24024 July 1990 Partially Withheld Safeguard Insp Repts 50-269/90-22, 5-270/90-22 & 50-287/90-22 on 900625-29.No Violations or Deviation Noted.Major Areas Inspected:Core Insp Program for Power Reactors & Safeguards Contingency Plan Implementation IR 05000269/19900181990-06-21021 June 1990 Partially Withheld Insp Repts 50-269/90-18,50-270/90-18 & 50-287/90-18 on 900604-08 (Ref 10CFR2.790 & 73.21).No Violations Noted.Major Areas Inspected:Security Program Audit,Detection & Assessment Aids & Key Control PNO-II-89-066, licensees Prepared for Adverse Weather Conditions Due to Hurricane.Briefings Held W/Key Managers on Responsibilities to Check All Trailers,Secure Crane Hooks & Increase Emergency Food Supplies1989-09-21021 September 1989 PNO-II-89-066:licensees Prepared for Adverse Weather Conditions Due to Hurricane.Briefings Held W/Key Managers on Responsibilities to Check All Trailers,Secure Crane Hooks & Increase Emergency Food Supplies PNO-II-89-066A, updates Status of Hurricane Hugo for Nuclear Facilities in Southeast.Manning of Incident Response Ctr by Region II Continuing1989-09-21021 September 1989 PNO-II-89-066A:updates Status of Hurricane Hugo for Nuclear Facilities in Southeast.Manning of Incident Response Ctr by Region II Continuing ML20247N0071989-09-11011 September 1989 PNS-I-89-015:revised Notification of Telephone Threat, Correcting Event Date from 890909 to 890911.Call, Originating from Limerick or Peach Bottom,Received at Corporate Ofc.On 890525,threat Received at Peach Bottom ML20246C4001989-08-15015 August 1989 Partially Deleted Insp Repts 50-272/89-19,50-311/89-17 & 50-354/89-15 on 890710-14 (Ref 10CFR73.21).Major Areas Inspected:Followup on Actions Taken in Response to Regulatory Effectiveness Review on 890410-14 ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods PNO-V-89-047, on 890808,earthquake & Aftershock of 5.1 & 4.2 Magnitudes,Respectively,Occurred Approx 15 Miles Southwest of San Jose,Ca.Reactors Shutdown During Earthquake.Tour of GE Reactor Disclosed No Damage1989-08-0808 August 1989 PNO-V-89-047:on 890808,earthquake & Aftershock of 5.1 & 4.2 Magnitudes,Respectively,Occurred Approx 15 Miles Southwest of San Jose,Ca.Reactors Shutdown During Earthquake.Tour of GE Reactor Disclosed No Damage IR 05000269/19890201989-07-25025 July 1989 Partially Withheld Insp Repts 50-269/89-20,50-270/89-20 & 50-287/89-20 on 890626-30 (Ref 10CFR2.790.(d) & 73.21). Violations Noted.Major Areas Inspected:Physical Security Program for Power Reactors & Security Audit PNO-IV-89-045, on 890703,earthquake Near Tremonton,Ut Occurred.Earthquake Safety Interlocks Did Not Trip & No Damage Occurred1989-07-0505 July 1989 PNO-IV-89-045:on 890703,earthquake Near Tremonton,Ut Occurred.Earthquake Safety Interlocks Did Not Trip & No Damage Occurred IR 05000269/19890101989-05-19019 May 1989 Partially Withheld Insp Repts 50-269/89-10,50-270/89-10 & 50-287/89-10 on 890410-14 (Ref 10CFR2.790 & 73.21). Violations Noted.Major Areas Inspected:Mgt Support,Security Program Plans & Audits & Protected & Vital Area Barriers IR 05000157/19890011989-05-11011 May 1989 Insp Rept 50-97/89-01 & 50-157/89-01 on 890425-26.No Violations Noted.Major Areas Inspected:Operation & Records of Triga & Zpr Reactors ML20247B6651989-05-0909 May 1989 Mgt Meeting Rept on 890307 & 0413.Major Areas Discussed: Status of Plant,Training & Safety Programs & Self Assessment Programs IR 05000269/19890091989-04-10010 April 1989 Insp Repts 50-269/89-09,50-270/89-09 & 50-287/89-09 on 890306-10.No Violations Noted.Weaknesses Noted Re Data Base Used to Prepare computer-generated Work Requests.Major Areas Inspected:Design Control,Mods & Open Items PNO-V-89-022, on 880403,earthquake of Magnitude of 4.5 on Richter Scale Occurred 10 Miles Northeast of San Jose,Ca. Automatic Seismic Protection Did Not Trigger Shutdown. Reactors Manually Shutdown.No Radioactive Release Occurred1989-04-0303 April 1989 PNO-V-89-022:on 880403,earthquake of Magnitude of 4.5 on Richter Scale Occurred 10 Miles Northeast of San Jose,Ca. Automatic Seismic Protection Did Not Trigger Shutdown. Reactors Manually Shutdown.No Radioactive Release Occurred PNO-IV-89-020, Region IV Notified of Recent Reactor Trip at Palo Verde Unit 3 That Was Complicated by Inability to Open Steam Generator Atmospheric Dump Valves Mfg by Control Components,Inc.No Sticking Problems Noted at Other Plants1989-03-23023 March 1989 PNO-IV-89-020:Region IV Notified of Recent Reactor Trip at Palo Verde Unit 3 That Was Complicated by Inability to Open Steam Generator Atmospheric Dump Valves Mfg by Control Components,Inc.No Sticking Problems Noted at Other Plants IR 05000269/19890071989-03-10010 March 1989 Insp Repts 50-269/89-07,50-270/89-07 & 50-287/89-07 on 890213-17.Deviation Noted.Major Areas Inspected:Conformance to Reg Guide 1.97 Re Instrumentation for light-water-cooled Plants to Assess Conditions During & Following Accident IR 05000321/19880371989-03-0909 March 1989 Partially Withheld Insp Repts 50-321/88-37,50-366/88-37 & 50-424/88-53 on 881102-890106 (Ref 10CFR2.790(d) & 73.21). Violations Noted.Major Areas Inspected:Physical Security Operational Activities & Safeguards Matl Handling IR 05000213/19880211988-11-15015 November 1988 Physical Security Insp Repts 50-213/88-21,50-245/88-22, 50-336/88-25 & 50-423/88-21 on 881017-21.No Noncompliance Noted.Major Areas Inspected:Safeguards Info Program - Corporate Ofcs PNO-I-88-116, on 881108,voters Voted Down state-wide Referendum to Shutdown Plants in State of Ma If Nuclear Waste Produced in Process1988-11-0909 November 1988 PNO-I-88-116:on 881108,voters Voted Down state-wide Referendum to Shutdown Plants in State of Ma If Nuclear Waste Produced in Process IR 05000280/19880401988-10-26026 October 1988 Insp Repts 50-280/88-40,50-281/88-40,50-338/88-28 & 50-339/88-28 on 880926-30.No Violations or Deviations Noted. Major Areas Inspected:Control Room Habitability & Insp Followup Items IR 05000369/19880211988-10-13013 October 1988 SALP Repts 50-369/88-21 & 50-370/88-21 for Aug 1987 - Jul 1988 IR 05000413/19880241988-10-13013 October 1988 SALP Repts 50-413/88-24 & 50-414/88-24 for Aug 1987 - Jul 1988 ML20151U7701988-08-10010 August 1988 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $1,250,000.Violations Noted:Control Room Operators Observed Sleeping While on Duty,Reading Matls Not Directly Job Related & Failure to Rept Items to NRC PNO-V-88-044, on 880627,earthquake Occurred 5 Miles East of Santa Cruz,Ca.Seismic Instrumentation Not Triggered at Vallecitos,Aerotest Operations or at Univ of California at Berkeley1988-06-27027 June 1988 PNO-V-88-044:on 880627,earthquake Occurred 5 Miles East of Santa Cruz,Ca.Seismic Instrumentation Not Triggered at Vallecitos,Aerotest Operations or at Univ of California at Berkeley PNO-V-88-038, on 880612,earthquake Occurred on Calaveras Fault within 50 Miles of Identified Facilities.All Reactors Shutdown at Time of Earthquake.No Seismic Trips Observed. Insp Revealed No Signs of Damage at Facilities1988-06-13013 June 1988 PNO-V-88-038:on 880612,earthquake Occurred on Calaveras Fault within 50 Miles of Identified Facilities.All Reactors Shutdown at Time of Earthquake.No Seismic Trips Observed. Insp Revealed No Signs of Damage at Facilities IR 05000454/19880081988-05-27027 May 1988 Insp Repts 50-454/88-08,50-455/88-08 & 50-456/88-16 on 880509-19.No Violations or Deviations Noted.Major Areas Inspected:Review of Action on Previous Insp Items & Followup on SER Items PNO-IV-88-040, on 880509,System Energy Resources,Inc to Manage & Operate All Middle South Nuclear Plants.Arkansas Power & Light & Louisiana Power & Light Will Apply for Appropriate License Amends1988-05-0909 May 1988 PNO-IV-88-040:on 880509,System Energy Resources,Inc to Manage & Operate All Middle South Nuclear Plants.Arkansas Power & Light & Louisiana Power & Light Will Apply for Appropriate License Amends IR 05000269/19880051988-03-21021 March 1988 Insp Repts 50-269/88-05,50-270/88-05 & 50-287/88-05 on 880217-0316.No Violations Noted.Major Areas Inspected:Maint, Operations,Surveillance,Physical Security & Design Changes IR 05000272/19880061988-03-18018 March 1988 Partially Withheld Physical Security Insp Repts 50-272/88-06,50-311/88-06 & 50-354/88-04 on 880201-05 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected: Procedures,Security Organization & Mgt Effectiveness ML20151U8781988-03-0404 March 1988 Partially Withheld Insp Repts 50-259/88-01,50-260/88-01, 50-296/88-01,50-327/88-01 & 50-328/88-01 on 880106,07 & 13. (Ref 10CFR2.790(d) & 73.21).Major Areas Inspected:Corrective Measures in Response to Unresolved Item IR 05000354/19860991988-03-0404 March 1988 SALP Rept 50-354/86-99 on 861201-880115 PNO-I-88-020, on 880216,CA Mcneill Named Executive Director - Nuclear W/Responsibility of Directing Nuclear Operations, Including Nuclear Dept Reorganization & Restart Efforts of Peach Bottom1988-02-16016 February 1988 PNO-I-88-020:on 880216,CA Mcneill Named Executive Director - Nuclear W/Responsibility of Directing Nuclear Operations, Including Nuclear Dept Reorganization & Restart Efforts of Peach Bottom PNO-II-88-013, on 880211,two Workers Slightly Contaminated W/ Radioactive Water.Caused by Approx 1,000 Gallon Leak of Radioactive Water Occurring During Maint on Valve.Workers Showered to Remove Contamination1988-02-12012 February 1988 PNO-II-88-013:on 880211,two Workers Slightly Contaminated W/ Radioactive Water.Caused by Approx 1,000 Gallon Leak of Radioactive Water Occurring During Maint on Valve.Workers Showered to Remove Contamination 1997-09-26 |
Text
r%)
' r e
NAR 2 71985
- ENCLOSURE 1 APPENDIX TO DUKE POWER COMPANY OCONEE NUCLEAR STATION UNITS 1, 2 AND 3 SALP BOARD REPORT (Dated December 31,1984)
~
l 8507170727 850327 PDR ADOCK 05000269 e pm l
L
Enclosure 1 I. MEETING
SUMMARY
- a. A meeting was held at 10:00 a.m. on January 8,1985, at Duke Power Company's Charlotte, North Carolina corporate offices to discuss the SALP Board Report for the Oconee facility.
- b. Licensee Attendees:
D. W. Booth, President and Chief, Executive Officer W. H. Dwen, Executive Vice President', Engineering Construction and Production R. B. Priory, Vice President, Design Engineering H. Tucker, Vice President, Nuclear Production R. Dick, Vice President, Construction M. D. McIntosh, Manager, McGuire M. S. Tuckman, Manager, Oconee
- c. NRC Attendees:
J. N. Grace, Regional Administrator, Region II (RII)
J. A. Olshinski, Deputy Regional Administrator, RII J. P. O'Reilly, Former Regional Administrator, RII V. L. Brownlee, Chief, Projects Branch 2, Division of Reactor Projec.s (DRP), RII J. C. Bryant, Senior Resident Inspector, Oconee, DRP, RII L. King, Resident Inspector, Oconee, DRP, RII K. Sasser, Resident Inspector, Oconee, DRP, RII W. T. Orders, Senior Resident Inspector, McGuire, DRP, RII R. Pierson, Resident Inspector, McGuire, DRP, RII D. Hood, Project Manager, Licensing Branch 4, Divison of Licensing (DL), Office of Nuclear Reactor Regulation (NRR)
H. Nicolaras, Project Manager, Operating Reactors Branch 4, DL, NRR
k4 ,
Enclosure 1 II. LICENSEE CON 4ENTS Licensee's coments submitted in response to the SALP Board Report follow.