4 Commonwealth litiwn Company liraidwood Generating Station Route 01,11ox Hi a
litaces ille, II. 60 407 Axil 9 Tel H15-45R2801 December 5,1996 BW/96-0095 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
Monthly Operating Report for November,1996 Braidwood Nuclear Power Station, Units I and 2 Facility Operating Licenses NPF-72 and NPF-77 NRC Docket Nos. 50-456 and 50-457 Ladies and Gentlemen:
In accordance with Technical Specification 6.9.1.8, enclosed you will find the Monthly Operating Report for Commonwealth Edison Company's (Comed's) Braidwood Nuclear Power Station, Units I and 2, covering the penod November 1,1996 through November 30, 1996.
Please address any comments or questions regarding this matter to Chris Pershey at (815) 458-2801, extension 2173.
Very truly yours, T
'ulon tion Manager
\\
l Braidwood Nuclear Station h&
TJT/CP/bl O:\\CORREsPZCSTECif BW96 0095 Enclosures cc:
A. B. Beach, Regional Administrator - RIII R. R. Assa, Braidwood Project Manager - NRR C. J. Phillips, Senior Resident inspector - Braidwood T. J. Esper, IDNS Resident Inspector - Braidwood Office of Nuclear Facility Safety - IDNS 9612180030 961130 PDR ADOCK 05000456 R
PDR H70038 A l'nicom Compan)
BRAIDWOOD NUCLEAR POWER STATION UNIT I AND UNIT 2 MONTHLY PERFORMANCE REPORT Comed NRC DOCKET NO. 050-456, LICENSE NO. NPF-72 NRC DOCKET NO. 050-457, LICENSE NO. NPF-77 i
i
~
I i
A. OPERATING DATA REPORT Docket No: 50 - 456 Unit: Braidwood 1 Date: 12/05/1996 Completed by: Chris Pershey Telephone: 815-458-2801 4
OPERATING STATUS
- 1) Reporting Period: November 1996 Gross Hours:
720
- 2) Currently Authorized Power Level (MWt):
3411 Design Electrical Rating (MWe-gross):
1175 Design Electrical Rating (MWe-net):
1120 Max Dependable Capacity (MWe-gross):
1175 Max Dependable Capacity (MWe-net):
1120
- 3) Power level to which restricted (if Any):
None i
- 4) Reasons for restrictions (If Any):
None This Mo.
Yr to Date Cumulative
- 5) Report Period Hours:
720 8040 73113
- 6) Hours Reactor Critical:
0.0 6,356.1 57,334.0
- 7) RX Reserve Shutdown Hours:
0.0 0.0 0.0
)
- 8) Hours Generator on Line:
0.0 6,339.1 56,519.8
- 9) Unit Reserve Shutdown Hours:
0.0 0.0 0.0 10 Gross Thermal Energy (MWHt):
0 20,923,111 179,407,927 11 Gross Elect. Energy (MWH):
0 7,219,784 60,610,104 12 Net Elect. Energy (MWH):
10,010 6,934,041 58,061,401 13 Reactor Service Factor:
0.0 79.1 78.4 14 Reactor Availability Factor 0.0 79.1 78.4 15 Unit Service Factor:
0.0 78.8 77.3 16 Unit Availability Factor:
0.0 78.8 77.3 17 Unit Capacity Factor (MDC NET):
-1.2 77.0 70.9 18 Unit Capacity Factor (DER NET):
-1.2 77.0 70.9 19 Unit Forced Outage Rate:
0.0 7.3 7.7 20 Unit Forced Outage Hours:
0.0 499.9 4,714.4 21 Shutdown Schedule Over Next 6 Months:
22 If Shutdown at End of Reporting Period, Estimated Date of Startup:
12/2/96
+
B. AVERAGE DAILY UNIT NET POWER LEVEL LOG Docket No: 50 - 456 Unit: Braidwood 1 Date: 12/05/1996 Completed by: Chris Pershey Telephone: 815-458-2801 MONTH: November 1996 p_ay MWe-net Qay MWe-net a
1)
-13 16)
-14 2)
-13 17)
-14 3)
-13 18)
-14 4)
-13 19)
-14 5)
-13 20)
-14 6)
-13 21)
-14 7)
-13 22)
-14 8)
-13 23)
-14 9)
-13 24)
-14 10)
-13 25)
-14 11)
-14 26)
-14 12)
-14 27)
-14 13)
-13 28)
-14 j
14)
-14 29)
-14 15)
-13 30)
-15
- Due to condenser efficiency
C.
UNIT SHUTDOWNS / REDUCTIONS Docket No.:
50- 456 Unit:
Braidwood 1 Date: 12/05/96 Completed by:
Chris Pershey Telephone:
815-458-2801 REPORT PERIOD:
November 1996 LER Cause & Corrective Action h
Date Type Hours Reason Method Number System Component to Prevent Recurrence 6
961101 S
720.0 8
4 N/A RC TBG Continuation of scheduled maintenance outage to allow inspection of steam generator tubing.
SUMMARY
Unit 1 entered the month of November in a scheduled maintenance outage to inspect the steam generator tubing. The unit remained shutdown through the end of the month.
TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure Maint or Test 1 - Manual S - Scheduled B - Maint or Test 2 - Manual Scram Exhibit F & Instructions for C - Refueling 3 - Auto Scram Preparation of Data Entry Sheet D - Regulatory Restriction 4 - Continued Licensee Event Report (LER) File E - Operator Training & Licensee Examination 5 - Reduced Load (NUREG-0161).
F - Administration G - Operator Error H - Other
D.
SAFETY / RELIEF VALVE OPERATIONS Docket No.:
50 - 456 Unit:
Braidwood 1 Date: 12/05/96 Completed by:
Ted Eliakis Telephone:
815-458-2801 Valves No. & Type Plant Date Actuated Actuation Condition Description of Event None
j.*
A. OPERATING DATA REPORT Docket No: 50- 457 Unit: Braidwood 2 Date: 12/05/1996 Completed by: Chris Pershey Telephone: 815-458-2801 OPERATING STATUS
- 1) Reporting Period: November 1996 Gross Hours:
720
- 2) Currently Authorized Power Level (MWt):
3411 Design Electrical Rating (MWe-gross):
1175
)
Design Electrical Rating (MWe-net):
1120 l
Max Dependable Capacity (MWe-gross):
1175 Max Dependable Capacity (MWe-net):
1120
- 3) Power level to which restricted (If Any):
None
- 4) Reasons for restrictions (if Any):
None This Mo.
Yr to Date Cumulative l
- 5) Report Period Hours:
720 8040 71195 i
- 6) Hours Reactor Critical:
720.0 6,623.7 60,045.1
)
- 7) RX Reserve Shutdown Hours:
0.0 0.0 0.0
- 8) Hours Generator on Lins:
720.0 6,606.0 59,632.1
- 9) Unit Reserve Shutdown Hours:
0.0 0.0 0.0 10 Gross Thermal Energy (MWHt):
2,441,614 21,865,063 192,648,518 11 Gross Elect. Energy (MWH):
838,346 7,458,788 63,364,575 q
12 Net Elect. Energy (MWH):
811,755 7,168,353 60,804,121 13 Reactor Service Factor 100.0 82.4 84.3 14 Reactor Availability Factor:
100.0 82.4 84.3 15 Unit Service Factor:
100.0 82.2 83.8 16 Unit Availability Factor:
100.0 82.2 83.8 17 Unit Capacity Factor (MDC NET):
100.7 79.6 76.3 18 Unit Capacity Factor (DER NET):
100.7 79.6 76.3 19 Unit Forced Outage Rate:
0.0 0.0 4.7 20 Unit Forced Outage Hours:
0.0 0.0 2,947.6 21 Shutdown Schedule Over Next 6 Months:
22 If Shutdown at end of Reporting Period, Estimated Date of Startup:
B. AVERAGE DAILY UNIT NET POWER LEVEL LOG Docket No: 50 - 457 Unit: Braidwood 2 Date: 12/05/1996 Completed by: Chris Pershey Telephone: 815-458-2801 MONTH: November 1996 Ray MWe-net Day plWe-net 1
1) 1130
- 16) 1132
- 2) 1134
- 17) 1129
- 3) 1135
- 18) 1129
- 4) 1136
- 19) 1129
- 5) 1136
- 20) 1129
- 6) 1135
- 21) 1131
- 7) 1135
- 22) 1131
- 8) 1135
- 23) 1131
- 9) 1135
- 24) 1066 10) 1135
- 25) 1119 1
11) 1134
- 26) 1117 12) 1135
- 27) 1119 13) 1133
- 28) 1117 14) 1133
- 29) 1107 15) 1135
- 30) 1105 l
l l
~.
t C.
UNIT SHUTDOWNS / REDUCTIONS Docket No.:
50 - 457 Unit:
Braidwood 2 Date: 12/05/96 Completed by:
Chris Pershey Telephone:
815-458-2801 REPORT PERIOD:
November 1996 LER Cause & Corrective Action h
Date Type Hours Reason Method Number System Component to Prevent Recurrence l
None i
t s
- S U MMARY***
Unit 2 entered the month of October 1996 at 100% capability and operated routinely the entire month.
TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure Maint or Test 1 - Manual i
S - Scheduled B - Maint or Test 2 - Manual Scram Exhibit F & Instructions for j
C - Refueling 3 - Auto Scram Preparation of Data Entry Sheet D - Regulatory Restriction 4 - Continued Licensee Event Report (LER) File l
E - Operator Training & Licensee Examination 5 - Reduced Load (NUREG-0161).
i F - Administration G - Operator Error l
H - Other i
D.
SAFETY / RELIEF VALVE OPERATIONS Docket No.:
50- 457 Unit:
Braidwood 2 Date: 12/05/96 Completed by:
Ted Eliakis Telephone:
815-458-2801 Valves No. & Type Plant Date Actuated Actuation Condition Description of Event None i
.