d Y NIAGARA UMOHAWK NIAGARA MOHAWK POWER CORPORATION /300 ERIE BOULEVARD WEST. SYRACUSE. N Y.13202/ TELEPHONE (315) 474-1511 August 23, 1985 (NMP2L 0475)
Mr. R. W. Stamstecki, Director U.S. Nuclear Regulatory Comission Region I Division of Reactor Pmjects 631 Part Avenue King of Pmssia, PA 19 406 Re: Nine Mile Point - Unit 2 Docket No. 50-410
Dear Mr. Stamstecki:
Enclosed is an interim report in accordance with 10CFR50.55(e) for the pmblem concerning acceptance of soldering installations that are rejectable.
This pmblem was reported via tel-con to R. A. Gram of your staff on July 24, 1985 Very tmly yours, 3
M C. V. Mangan Senior Vice President CVM/GG/cla (1206H)
Enclosum xc: Director of Inspection and Enforcement U.S. Nuclear Regulatory Comission Washington, DC 20555 R. A. Gram, NRC Senior Resident Inspector Project File 8509260007 050823 DR ADOCK 050 4}O V
i i p
. 7
[~
NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT - UNIT 2 DOCKET N0. 50-410 Interim Report for a Problem Concerning Acceptance of Soldering Installations That are Rejectable.
(55(e)85-24)
Description of the Problen A reinspection of the soldered connections on 32 switches installed in the reactor water cleanup and recirtulation control boa rd, Panel 2 CEC *PNL602, identified several nonconfonning soldered connections that were found to be doctnented as satisfactory when initially inspected.
The subject connections were found to be unsatisfactory based on the acceptance criteria established in the Quality Assurance Inspection Plan for Specification No. E062A.
This matter is still under investigation, and a final report will be submitted by September 30, 1985.