ML20129F792

From kanterella
Jump to navigation Jump to search
Answer to Util Motion for Summary Disposition of Intervenor Contention 1 That Util Never Planned to Build 765-kV Line for Power Transmission.Amend to Environ Rept Should Not Be Controlling Issue.Certificate of Svc Encl
Date released: 05/22/2020 Download: ML20129F792


Affidavit of Cw Bohlen Re Negotiations of 345-kV Line & Wider Easement for Const of 765-kV Line.No Indication That Bldg of 765-kV Line Dependent Upon Const Other than Const in Progress at Plant
ML20129F914
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 07/09/1985
From: Bohlen C
BOHLEN, C.W.
To:
References
Download: ML20129F914 (2)
Affidavit of Jj Tryner Re Negotiation for Easement Rights for 765-kV Transmission Line Through Property of J Moran & M Moran.Util Objective to Obtain Easements for 345-kV & 765-kV Lines at Same Time in 1980
ML20129F886
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 07/10/1985
From: Tryner J
TRYNER, J.J.
To:
References
Download: ML20129F886 (1)
Affidavit of L Creek Re Negotiations W/Util for Easement Across Property for 765-kV Transmission Line.Power Grid Fed from Several Sources.Defining Which Power Comes from Which Source Impossible
ML20129F846
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 06/10/1985
From: Creek L
NEINER, B. (BOB NEINER FARMS, INC.)
To:
References
Download: ML20129F846 (2)
Answer to Util Motion for Summary Disposition of Intervenor Contention 1 That Util Never Planned to Build 765-kV Line for Power Transmission.Amend to Environ Rept Should Not Be Controlling Issue.Certificate of Svc Encl
ML20129F786
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 07/15/1985
From: Bock C
BOCK, C.A., NEINER, B. (BOB NEINER FARMS, INC.)
To:
Atomic Safety and Licensing Board Panel
References
CON-#385-814
Download: ML20129F786 (7)