Part 21 & Interim Const Deficiency Rept Re Heat build-up in Emergency Diesel Generator Cabinets Reported by Louis Allis. Initially Reported on 850403.Bechtel Investigation Continuing.Next Rept Will Be Submitted 850803
ML20129F715
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/06/1985
From: Martin T
Public Service Enterprise Group
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
REF-PT21-85-274-000 PT21-85-274, PT21-85-274-000, NUDOCS 8506070024
Download: ML20129F715 (2)


Text

h-.

o r

Public Service Electric and Gas Company Thomas J. Martin 80 Park Plaza, Newark, NJ 07101 201-430-8316 Mailing Address: P.O. Box 570, Newark, NJ 07101 Vice President Engineering and Construction Dr. Thomas E. Murley, Administrator U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Dr. Murley:

POTENTIAL CONSTRUCTION DEFICIENCY HEAT BUILD-UP IN EDG CABINETS HOPE CREEK GENERATING STATION On April 3, 1985, a verbal report was made to Region I, Office of Inspection and Enforcement representative, Mr.

E.

Kelly.,

advising of a potentially significant construction deficiency concerning heat build-up due to three (3) transformers mounted inside the generator control cabinets.

The following interim report is provided in accordance with 10CFR50.55 (e).

Our verbal report to Region I was based on the Louis Allis 10CFR21 report on the subject concern.

To date, Bechtel; our Architect / Engineer and Constructor, has not received sufficient information from Colt Industries, Bassler Electric or Louis Allis to perform an analysis of safety implications.

We have been advised that a Bechtel representative was scheduled to discuss this issue at a meeting with the parties involved on May 2, 1985.

However, no resultant information is presently available for review and incorporation to this report.

R506070024 850506 PDR ADOCK 05000354 8

PDR f

g6 31

I

(

..,j.

Dr. T.

E.

Murley 2

5/6/85 aber of parties involved in the analysis and

.Given the resolution of the problem, we anticipate sending you a subsequent report on this issue by August 3, 1985.

Very truly yours,

[

h ie n C

Office of Inspection and Enforcement Division of Reactor Construction Inspection Washingcon, C. D.

20555 NRC Resident Inspector - Hope Creek P. O.

Bcx 241 Hancocks Bridge, NJ 08038 Records Center In:stitute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339

.