Text
,
7
' 1 k:
I s.
i f
RIVER BEND STATION APPREVAL SHEET STATION OPERATINC PROCEDURES go, ADM-0022 CONDUCT OF OPERATIONS TITLE YES ]
SAFETY RELATED NO NO]
TECHNICAL REVIEW REQUIRED YES X
REV.
PACES INDEP.
TECH.
NO.
ISSUED REVIEW REVIEW APPROVED BY EFFECT SIGNATURE /DATE SIGNATURE /DATE SIGNATURE /DATE DATE M
0 1 Thru 34 PFT 03/27/84 P.E. Freehill Philip D. Graham 03/29/84 03/27/84 03/27/84 1
1 Thru 34 Mc 4l g
- B
/ 25~
Y.W V- - -
D WM,,
y&
~
2 1 Thru 36 4/3#/ M W M NG I
0F/06/85 FRC MTc 85-17 bN~8
~
FOR INFORMATION ONLY s
B cRL g
......a,,-
J \\ f
')
ly ;
p'
,..~., nna r.,, w i
g.:, cemenu occum. g BEgg\\M E o a',3 N
g ()1 W cec I
8507170127 850709 PDR ADOCK 05000458 A
PDR SON-003 REY. 2
7; n
t.
r 1-l l
I I
l CONDUCT OF OPERATIONS
.l 7N I
l l
TABLE OF CONTENTS l
l 1
-l.
SECTION PAGE NO.
l l
1 l
1.0 PURPOSE 3
l l
l l
2.0 REFERENCES
3 l
l l
l 3.0 ORGANIZATION AND RESPONSIBILITY 4
l
.I A
l 4.0.
I OPERATIONS SHIFT COMPLEMENT, FUNCTIONS AND RESPONSIBLITIES l
l 4.1 Shift, Staffing 11 l
l 4.2 Operations Group Responsibilities 12 l
l 4.3 Notification of Absences 14 l
l 4.4 Personnel Recall 14 l
l 4.5,0ver, time 14 l
l 5
l l
5.0 SHIFT OPERATIONS l
r
.,,,,.f l 5.1 Shift Schedule 15 l
l 5.2 Shift Re!Lef 15 l
'l 5.3 Notificar.on 15 l
l 5.4 Training 16 l
l 5.5 Reactor Scram 16 l
/
5.6 Generator Load Changes 19 l
O, 5.7 Instrumentation and Control 19 l
l 5.8 Operation During Abnormal or Emergency Conditions 19 l
l 5.9 Control Room References 19 l
l 5.10 Housekeeping 20 l
l 5.11 Bypass of Safety Functions and Jumper Control 20 l
l 5.12 Safety Clearance and Tagging 20 l
l 5.13 Control Room Conduct 20 l
l 5.14 Shift / Evolution Briefings 21 l
l 5.15 Fire Brigade 22
'l l
5.16 Key Control 22 l
l 5.17 Component Labeling and Posted Signs 23 l
l 5.18 Radiological Controls 23 l
l~
5.19 Equipment Removal / Return to Service 23 l
l 5.20 Equipment Rotation 24 l
l l
l 6.0 PLANT OPERATING PROCEDURES l
l 6.1 Procedure Compliances 24 l
l 6.2 Procedure Implementation 25 l
~
l 6.3 Procedure Sign-Off List 25 l
l 6.4 System Check Lists 26 l
l 6.5 Periodic Review of Operating Procedures 26 l
l l
l I
l l
l l
ll l
l l
[
N/A
'i l
N/A ll ADM-0022 l
.REV - 2 l
PAGE 1 0F 36 l i
ll l
l l
6
3
-g
+
_l l
l-l l
CONDUCT OF OPERATIONS (Continued)
Ol
, [
I Y'
- l TABLE OF CONTENTS l
l.
I
'l SECTION PAGE NO.
l 1
1
[.
7.0 SHIFT RECORDS AND LOGS l
~l 7.1 Night Order Book 27 l
.l.
7.2 Standing Orders 27 l
"l:
.7.3 Limiting Conditions for Operation 28 l
1 l
l 8.0 SURVEILLANCE TESTING l
7> l 8.1 Operations Surveillance Tests 29 l
-l
.8.2 Conditional or Off-Normal Surveillance 29 l
1 I
l FIGURES l
l l
l Figure 1 - Operations Section Organization 30 l
- l Figure 2 - Control Room and At-The-Controls Area 31 l
l I
l ENCLOSURES l
.l l
l - Post-Trip Review Check List 32 l
l l - Scram Report 34
~
l.
l - LCO Status Sheet 36 1
g
- vl NOTE l
1 l
l This procedure is intended to provide guidance during normal l
l operation. During the constructio*n and pre-operational phase, l
l those sections that are based on the legal requirements of the l
l-Station Operating License need not be implemented until the l
l issuance of the Station Operating License.
l.
I I
I I
I I
I I
I l
l l
I I
l I
I I
I I
i 1
I I
I I
I I
I I
I I
I I
0d' I
il I
I I
l N/A l
N/A ll ADM-0022 l
REV,2 l
PAGE 2 0F 36 l I
I ll l
I I
1 l
l
[
l 1.0 PURPOSE I
I I
l, The purpose of this procedure is to provide instructions to ensure l'
l that the plant operations are conducted in an safe and effective, I
l consistent manner in accordance with the operating license, plant l
l procedures, and applicable regulatory requirements.
I l
l l
1.1 This procedure establishes the organiz.;tional and individual l
l responsibilities of the Operaticas Section and provides e
I l
.idministrative instructions necoscary for the daily conduct of l
I l
plant operations.
I I
I I
l 1.2 Prior to initial fuel load, the following sections of this I
l procedure will not be applicable and need not be strictly adhered I i
l to:
s
.? :
I
' 8'D' l
l 1
l 1.2.1 5.3, Notification
[
I I
l 1.2.2 5.5, Reactor Scram l
l l
l 1.2.3 5.6, Generator Load Changes l
I I
l 1.2.4 5.8, Operation During Abnormal or Emergency Conditions l
l
'I
" * ~
l 1.2.5 5.19. Equipment Return to Service
.I l
fI l
1.2.6 7.3 Limiting Conditions for Operation l
l I
-l 1.2.7 8.0, Surveillance Testing l
s (V) l I
l
2.0 REFERENCES
l I
I i
l 2.1 ADM-0007, Selection, Training,- Qualifica: Lon and Evaluation of l
j l
Plant Staff Personnel.
I l
l l
l 2.2 Gulf States Utilities Operations Quality Assurance Mtnaual l
1 l
(OQAM).
I l
l.
l 2.3 Reg. Guide 1.114 (Rev. 1, 11/76) Guidance on Being Operator At-l i.
l the-Controls of a Nuclear Power Plant.
l l
l l
2.4 NUREG-1000, Vol.1, April 1983.
I I
I l
2.5 RBS FSAR Chapter 13, Conduct of Operations.
l I
I l
2.6 ADM-0019, Condition Reporting.
l I
I l
2.7 10CRF55 Operator License.
I I
I l
2.8 10CFR50, Section 50.54, Conditions of License..
l i
I l
2.9 Gulf States Utilities Accident Control Manual.
l l
I l
2.10 G.E. BWR Standard Technical Specifications.
1 O
I I
C 1
I i
i ll l
1 l
l N/A l
N/A ll ADM-0022 l
REV - 2
'l PAGE 3 0F 36 l
1 1
11 1
I I
i l
l l
2.11 INPO Good Practice OP-204 Conduct of Operations.
l i
I i
l 2.12 OSP-0009, Author's Guide / Control and L'se of E=ergency Operating l g%7-s l
l Procedures.
1 I
l 2.13 RBS General Operatins Procedure GOP-0007, Scram Recovery.
l 1
I l
2.14 RBS Abnormal Operating Procedure A0P-0001, Reactor Scram.
l l
l l
2.15 AD.'!-0006, Control of Plant Records.
l 1
I l
'2.16 INPO SOER 82-04.
l l
l l
2.17 AD21-0031, Temporary Alterations.
l l
l l
2.18 AD?t-0027, Protective Tagging.
l l
l l
2.19 ADt!-0037, Equipment Identification and Labeling.
[
l I
l 2.20 ADt!-0028,?!aintenance Work Requests.
l l
1 l
2.21 AD?l-0003, Development, Control and Use of Procedures.
l l
I l
2.22 OSP-0002, Shift Relief and Turnover.
l 1
I l
2.23 OSP-0003, Logs and Records.
I l I
I
,l 2.24 IEIN 84-51, Independent Verification.
l($e.
l l
l 2.25 ADt!-0001, Station Staff Organization, Responsibilities and.
l
[
Authority.
l 1
I l
2.26 0CR-?!-85-009, Operation Respon'se to ANI/:!AELU Inspection.
l 1
l l
2.27 Generic Letter 82-12, Nuclear Power Plant Staff Working Hours.
l 1
l l
2.28 IEIN 83-27,~ Deliberate Acts Directed Against Plant Equipment.
l
'l I'
7,. _ -
l 2.29 ANSI N18.7-1976, Administrative Controls and Quality Assurance l
for the Operational Phase of Nuclear Power Plants.
l l
l l
3.0 ORGANIZATION AND RESPONSIBILITY l
I l
l 3.1 The Operat. ions Group is comprised of personnel in the following l
l classifications:
l 1
I l
General Operations Supervisor l
l 1
l Assistant Operations Supervisor l
1 l
l Shift Supervisor l
1 1
l Control Operating Foreman l
l l@
l l-l l
11 I
I l
N/A l
N/A ll AD?!-0022 l
REV - 2 1
PAGE 4 0F 36 l
s l
1 ll l
l l
r 3
n I
l Nuclear Control Oparstars I
l l
,3 g
Nuclear Equipment Operators 1
g IV) l l
l l
Shift Clerkt.
[
l l
The Operations Section is organized as shown in Figure 1.
l 1
l 3.2 Operations Section Position Responsibilities l
l l
1 3.2.1 General Operations Supervisor (GOS) l 1
I l
1.
Plan the overall activities and work of the operating l
l group in cooperation with the other section heads in j
g order to develop an integrated plant operations l
,p g
program; the primary objective being to generate unit j
safety, reliability, and availability.
j g
1 I
l 2.
Provide guidance and direction to supervisors to l
g ensure that the approved operating procedures and l
g practices are followed.
l l
Participate in development of training and retraining, I l
3.
l l
programs for all operating personnel in o:i:r to l
g provide a highly qualified and efficient aperating j
l force and to ensure that qualified replacement l
l personnel are available when vacancies occur.
l l
I p) g 4.
Develop performance standards for personnel under his
[*
i y
supervision as a means of evaluating individual l
l performance. Keep the Assistant Plant Manager j
l Operations informed on the qualifications and
[
g performance of empidyees, and make appropriate l
l recommendations concerning employees showing l
l outstanding or substandard performance.
[
l I
g S.
Promote safe working conditions for employees under l
g his supervision by proper instruction and,the l
g maintenance of tools, equipment, and work areas.
l g
Ensure that employees receive che requird l
l instructions concerning industrie! 34rety.
l 1
I l
6.
Promote good housekeeping.
l l
I l
7.
Ensure that personnel under hir supervision receive l
l training in appropriate radiokgical protection l
g practices, procedures and ALARA crinciples.
l 1
I l
8.
Develop and prepare operating orders, grocedures and l
g instructions to ensure safe and reliable operation of l
l equipment.
[
l I
I I
7 l
l l
l ll l
1 l
l N/A 'l N/A gl ADM-0022 l
REV - 2
-l PAGE 5 0F 36
[
l l
11 1
I l
4
a l
I l
9.
Establish and regularly review the required operating l
l logs and records. Supervise the praparation of l-
. l operating records to ensure that they are complete, l.'
l accurate and timely.
l
'p l
l l
- 10. Insist on-strict adherence to the company and plant l
j.
security provisions and procedures.
l I
I l
- 11. Coordinate development and implementation of progr..ms l
l and policies that ensure that plant operations ara l
l carried out in a safe and reliable manner.
l l
1 l
- 12. ?!aintain familiarity with the requirements of all l
l regulatory agencies with regard to plant operations.
l
_ l Prepare, supervise or assure the initiation and l
l preparation of the necessary reports and notifications l l
for these agencies as directed.
l l
l l
- 13. ?!aintain familiarity with the company-union agreements l' l
and keep current on interpretations. Ensure that they l l-are' administered properly.
l l
'l l
- 14. Ensure all required operational surveillance testing
,l l
is performed in a timely and proper manner.
l l
1 l
- 15. Perform such other duties as may be assigned by the.
l l
Plant !!anager.
l l
I
^l
- 16. Serve as an active member of the Facility Review l$
I l_
Committee (FRC) and Joint Tes: Group (JTG).
1 I
l
- 17. Implement plant goal.s and objectives. Establish l
l departmental goals and objecttves.
l 1-l l
- 18. Ensure the plant is operated in accordance with the l
l operating license requirements.
l l
l l
- 19. Authorize restart following post trip review.
l i
I r
l 3.2.2 Assistant Operations Supervisor (AOS) l 1
I l
1.
Administration of operations section surveillance l
l program.
l l
l l
2.
Initiate changes to operating procedures (per l
l Reference 2.21) which are required due to procedural l
l deficiencies or plant modifications.
l 1
I l
3.
Develop shift schedules to meet manpower and license l
l requirements of the Technical Specifications and I
j.
expected operational activities.
1 I
I i
1 l
lI@
l I
I 11 1
I I
l N/A l
N/A ll ADM-0022 REV - 2 l
PAGE 6 0F 36 1
1 1
11 l
I I
I I
4.
Review the operations section shift records l
g l
periodically, at least weekly for abnormalities and l
l completeness (Reference 2.26).
l l
k 5.
Assist with coordinatica of fuel handling activities g
with other plant sections.
l l
l 6.
Schedule, coordinate and document on-shift operations l l
g group training as specified in TPP-0007 " Training l
l Program Occutentation".
l I
I i
7.
Initista reports as directed by the 003.
l l
l I
g Initiata notification to operations group and licensed l 8.
l personnel of plant modifications, procedure changes, l
gj g.
and Techncial Specifications revisions that have l
l-operational or safety significance.
[
?
1 I
9.
Review of Operations Section Procedures.
l g
l I
g
- 10. Assume the responsibilities of the GOS in his absence. l l
l l
NOTE
- l While the responsibilities of the AOS are l
l delineated in some detail above, it should l l g
be clearly understood that the list is not l>
'g exhaustive nor does it preclude delegation l
g of functions.
l 1
I 3.2.3 Shift Supervisor (SS) l l
1 I
l 1.
In direct charge of unit operations during startup, l
g power operation and shutdown.
Normally~ acts as th.e
[
l Plant Management representative on site during
[
g backshifts, weekends, and holidays.
l l
1 l
2.
Supervise the Control Operating Foreman to ensure
['
g proper performance of his assigned duties.
l
.o.
l l
l 3.
Ensure shift operations are conducted in accordance j
g with plant procedures an'd operating licenses.
l 1
I g.
- 4.. Coordinate the activies of Operations, Chemistry, l
l Radiation Protection, Maintenance, Instrument and l
l Control (I&C), Radwaste, and Security groups to l
l accomplish the operating objectives for his shift.
l l
1 l
5.
Notify higher management authority as required by l
g plant reporting and notification requirements.
l l
l 1
I I
I O
l l
l 1
ll l
l l
_l N/A g
N/A ll ADM-0022 l
REV - 2
-l PAGE 7 0F 36 l
I i
11 1
I I
t
,-w
--y
,,c.
.e I
I l
6.
Supervise the on-site operations group functions
[
l required by the Emergency Plan, Radiation Protection l
l Plan, the Security Plan and their respective l
l implementing procedures.
l g..
I I
l 7.
Act as Emergency Director until relieved by higher l
l management authority.
l l
l l
8.
Authorize the removal of equipment and systems from l
l service for maintenance, testing, or cperational l
l activities.
l l
l l
9.
Authorize the return to service of equipment and l
l systems from service for maintenance, testing of l
l operational activities.
l-1 I
l
- 10. Act as custodian of plant keys assigned to the l
l operations group.
1 I
I l
- 11. Review shift records for accuracy an'd completeness.
l l
1 l
- 12. Ensure shift operating crews review changes to l
l operating procedures, plant modifications, and
.'l l
revisions to the Technical Specifications.
l l
1 l
- 13. Ensure that on-shif t training of personnel is
- l l
conducted as scheduled, including required reading.'
l
'l l
l
- 14. Ensure his shift is properly aanned. Request or
[ (@.
}
initiate callout of personnel as required.
l W;;
l I
l
- 15. Initiate reports of reactor trips and abnormal l
l activities and rep 6rtable events.
l l
l l
- 16. Supervise implementation of radioactive waste l
l management program with respect to shift operations.
l l
l l
- 17. Ensure completion of all surveillance / shift routines l'
l assigned to his shift.
l-equipment and l
1
[
- 18. Authorize safety tagging of plant l
systems.
l l
1
-l
- 19. Authorize temporary alteratic:u, jumpers, and lifted
[
l leads.
l l
l-l
- 20. ?!onitor qualification, mental and physical conditions l
l of operating shif t personnel.
I I
I l
- 21. Complete Post-Trip Review and Scram Report per
[,
l and 2 for any unplanned Reactor Scrams.
l l
l l
- 22. Authorizes access in accordance with Plant Security' l
l Procedures.
l 3
l l
l ll l
l l
l N/A l
N/A ll AD?!-0022 l
REV - 2
,l PAGE 8 0F 36 l
l l
ll l
l 1
l
l I
-l
- 23. Rssponsiblo for maintaining and complying with the l
requirements of the NRC Senior Reactor Operator l
l l
License.
l^
l I
V
[
- 24. Insuring a fully manned fire brigade' is present on l
l each shift.
[
l I
l
'3.2.4 Control Operating Foreman (C0F) l l
1 l
1.
Supervise activities assigned by the SS in accordance 1
l with the operating licenses and plant procedaros.
l l
I l
2.
Coordinate the operation of plant equipment and l
l systems.
l.
I I
l 3.
Coordinate safety tagging operations.
l l
l s
l-4.
Coordinate surveillance testing.
l l
I l-5.
Supervise the Nuclear Equipment Operators in the l
l performance of their duties.
l l
1 l
6.
Coordinate the activities of the Nuclear Control l
l Operators with other operations and plant personnel t
[
[
achieve safe reliable and efficient unit operation.
l l
l l
7.
Review of shift records for compliance with Reference l
l 2.23.
l i
I (mi l
8.
Responsible for maintaining and complying with the l
l requirements of the NRC Senior Reactor Operator l
l License.
I y
1 1
l 9.
Perform the duties of the SS in his absence.
l l
I l
3.2.5 Nuclear Control Operator (NCO) l 1
I l
1.
Responsible to the SS or C0F for operation of all 1-l equipment controlled from the !!ain Control Area.
l l
Operation is interpreted to mean:
l l
I l
a.
Acutal controls manipulation.
l 1
1
-l
,b.
?!onitoring equipment and system parameters.
l 1
I i
l c.
Documentation of evolutions and significant events l l
related to those systems and/or components l
l controlled from the ?!ain Control Room.
l l
1
-l d.
Initiation or performance of operation actions l
l required by normal operating procedures, Emergency l l
Operating Procedures, Abnormal Operating l
l Procedures, and Alarm Response Procedures l
l applicable to the ?!ain Control Board area.
l A
1 I
r 1
y /'
l l
l l
ll 1
1 I
l N/A l
N/A ll ADri-0022 l
REV - 2
-l PAGE 9 0F 36 l
I I
II l
I I
ma
o.
I I
1 l
2.
Recording of Control Room Log readings l
l l-l 3.
Initiate power reductions if plant parameters indic that such actions are required to sustain safe g
l l
+
l operation or prevent equipment damage.
l l
l l
4.
The NCO has the authority and responsibility to shut l
l the reactor down when he determines that reactor l
l safety is in jeopardy or when operating parameters l
l
'(scram settings) are exceeded and automatic. shutdown l
l does not occur (Reference 2.26).
l l
l l
5.
Initiate Emergency Safety System actuation if l
l indications exceed automatic actuation setpoints and l
l actuation has not occurred.
[
l I
l 6.
Initiate holds during plant evolutions that are l
g required to ensure that the evolution does not l
l threaten the stability of the plant, result in l
j equipment damage or violate administrative controls l
l such as System Operating Procedures, Technical l
l Specifications, etc.
[
[
l l
7.
Responsible for maintaining, and complying with the l
l requirements of NRC Reactor Operators License.
[
l
.' l l
8.
Initiate and Complete Page 1 of Scram Report l
l (Enclosure 2), for any unplanned Reactor Scram.
l
'l j (ih l'
l 9.
Act as Fire Brigade leader p
I I
l NOTE l
l l
l The At-The-Controls Operator shall not under l
g any circumstances leave the "at-the-controls l
l area" (Figure 2) for any reason without l
l obtaining a qualified relief operator.
Prior l
l to assuming responsibility, the Relief l'
l Operator will be informed of any evelutions l
l in progress that might affect the overall l
l status of the plant.
l 1
I l
3.2.6 Nuclear Equipment Operator (NEO) i l
l l
1.
Responsible for performance of assignments associated
[
l with shift operations and fuel handling as directed by l l
the SS.
l l
I l
2.
Duties are normally associated with operation of l
l auxiliary systems and equipment outside the main l
l control room and will include routine checks, data l
l acquisition, and local operation of equipment.
l l
1 l
l@
l 1
l l
11 I
.I I
l N/A l
N/A ll AD>l-0022 l
REV - 2
[
PAGE 10 0F 36 [
L I
II l
I I
l'.
l l
l 3.
?!aintain satisfactory progress toward qualification as l
2 Neo.
l l
l
.- (]-
l 3.2.7 Shift Clerk l
l
(_/
l l
g This individual will be required to t(ork.1 rotating shift l
j, schedule with duties as follows:
l l
1 l
1.
Trained to be the communicator for the Eaergency Plan l
l in the control rcom.
l l
I l
2.
Assist the SS in calling out personnal to maintain l
l shift staffing.
l l
l l
3.
!!aintain the Main and Auxiliary Control Room records, l
prints and station manuals.
l l'j' l
l
~"
l l
4.
Maintain overtime list, vacation and sick leave logs.
l
~
j i
g 5.
Transmit shift records to the PPF.
l l
I l
6.
Maintain inventory of chart paper, logs and control l
l roem supplies.
,l l
,I w.
.g 7.
Process and track Maintenance Work Requests.
l 1
1 l
8.
Process and track Technical Specification Surveillanc.e l
~
l Procedures.
l (X
l 1
)
d l-9.
Aid the SS in the maintenance and audit of the Safety l
l Tag Log and Jumper Log.
I l
l OPERATIONS SHIFT C0!!PLEMENT, FUNCTIGNS, AND r.SPONSIBILITIES I
4.0 l
l l
4.1 Shift Staffing l
1 l
l 1 Shift Supervisor (SRO) l l
l M-l 1 Control Operating Foreman (SRO) l
.u-l l
1 l
3 Nuclear Control Operators (RO) l l
l g
i.
l 4 Nuclear Equipment Operators I
l l
I l
4.1.1 A SS with a Senior Reactor Operator license, who is also a l l
member of the station supervisory staff, shall be on site l
l at all times when fuel is in the reactor.
l l
I l
4.1.2 A C0F with a Senior Reactor Operator license shall be in l
l the control room at all times, except when the unit is in l
l a cold shutdown condition. The SS may, from time to time, l l
act as relief for the COF assigned to the control room.
l l
1 l
I D
l Q
l I
l 1
l 11 I
I I
l N/A l
N/A ll ADM-0022 l
REV - 2
-l PAGE 11 0F 36 l l
l ll I
I I
.a-
~
ay s
..a a
,.s
- l 1
4.1. 3 A licenssd reactor operator shall bs in the at-the-
' g l
t g
controls area (Figure 2) of the control room at all times l when fuel is in the reactor.
l l
l 1.
Additional licensed operators, the Unit Operator, may l be used for data taking and other "back panel" work.
l 4.1.4 (Non-licensed) operators shall be properly qualified to 4
y support the the activities to which assigned.
l l
I 4.1.5 Periods of core alterations shall include a licensed SRO g
This licensed ll g
to directly supervise the core alterations.
g SRO operator shall have no other concurrent operational l
duties.
g l
,,,]
4.1.6 Deviations in shif t compliment may be approved by the GOS so long as the minimum manning and license requirements of l g
l Technical Specifications are met.
l l
l 4.1.7 g
Additional Operations Section personnel may be. required on l l
shift because of. unusual plant conditions or operational l
needs.
The SS shall obtain the additional personnel as g
Activities requiring additional personnel will l g
necessary.
g not be undertaken until the required personnel are
'll available.
g
,l l
-l i
4.1.8 Personnel who are relieving the shift should review all' l
g.
g.
pertinent operating data back to the time that they had
[
previously been on watch (Referenca 2.26).
1.
Narrative Log Books l
g l
l 2.
Standing Orders l
l l
3.
Tagging Order Log I
g l
l I
4.
Temporary Alteration Log
-l g
l 1-5.
Night Orders l
l l-I 4.2 Operations Group Responsibilities g
l
- l l
4.2.1 The following responsibilities are delineated for l
g l
Operations Section personnel:
.l l
I 1.
The responsibility of the SS shall be to maintain a l
g g
broad perspective of operational conditions affecting l
g the safety of the plant as a matter of highest l
l priority at all times.
l 1
I I
I
- l 1
- l I
I I
ll 1
l I
g N/A y
N/A gl ADM-0022 l
REV - 2
[
PAGE 12 0F 36 l l
l ll l
l l
4 e
-5.-
,--,y
-. wv, v-.-
--ww.
..,-r
s e
l 1
l 2.
The SS should not become involved in any single l
l operation that would prevent him from being' fully
(,
l aware of the overall plant status. This applies to l
m (V) l both normal and emergency conditions.
l g
l l
3.
During events that require implementation of Emergency l l
Plan Procedures, the SS is designated Emergency l
l Director until properly relieved.
l l
I l
4.
During accident situations, the COF is in charge of l
l the control room, and shall remain in the control room l l
unless properly relieved. His responsibilities are j
outlined in Reference 2.12.
l l
I l
S.
The SS, C0F, and Plant Operators on shift must be l-
,g l
aware of and responsibile for the plant status at all l
l times.
l 1
I l
6.
All Operations personnel must be alert and remain l
l within their immediate areas of responsibility until l
l properly relieved and be responsible for monitoring l
l the instrumentation and controls located within their l
l areas.
They are responsible for taking timely and l
l-proper actions to ensure safe operation of the l
~
l facility (i.e., actions or activities, including l
l
' failure to take action, related to the facility that. l l l
could have an adverse effect on the health and safety l
l of the public, plant workers, or other individuals).
l
,n l
I t].
l_
7.
Only Licensed Operators or trainees, under the direct l
y l
supervision of Licensed Operators, are permitted to l
l manipulate the controls that directly affect the l
l reactivity or power
- 1evel of the reactor.
l l
l l
8.
Personnel who have the classification of NCO or NEO l
l shall be considered as qualified personnel to perform l
l independent verification (see Reference 2.24).
l i.
l l*
l 9.
Operations personnel are responsible for the proper l
l exchange of important information and for manning l
l their stations until properly relieved. Shift l
l turnover shall be conducted in accordance with l
l Reference 2.22.
l l
l l
- 10. Operation of mechanisms and apparatus controls that l
l may directly or indirectly affect the power level or l
l reactivity of the reactor shall only be accomplished l
l with the knowledge and consent of a licensed operator l
l or SS.
l I
I I
I l
I I
I I
I A
l l
V l
l l
l 11 I
.I I
l N/A l
N/A l[
ADM-0022 l
REV - 2 1
PAGE 13 0F 36 l l
1
-11 1
I I
- 11. The use of valva parsuadars will be restricted to manually operated valves only. They shall not be used l to manually position motor operated valves (Reference l
2.16).
l
-l 1
4.3 Notification of Absences g
l 4.3.1 Personnel expecting to be late or unable to report for shift duty at the scheduled time shall, at the earliest l
possible time, inform the COF of the situation. The C0F
[
g shall make necessary arrangements for obtaining a replacement.
j l
l 1
4.4 Personnel Recall g
l 1
I 4.4.1 y
The SS has the authority to call out all required l
g personnel, regardless of discipline.
l 1
I 4.5 Overtime g
l l
1 4.5.1 g
Overtime shall not be routinely scheduled to meet the j
g shift crew staffing requirements stated in Section 4.1.
l In the event that overtime must be used, the following l
g g
overtime restrictions apply:
,((
1.
An individual should not be permitted to work more
{
g than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight (excluding shift turnover l
l time).
l 2.
There should be at least a S-hour break between all I
g work periods (shift turnover time is included in this.
g break).
l l
l I
3.
An individual should not be permitted to work more g
j than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in any 24-hour period, nor more than 24 g
hours in any 48-hour period, nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in ll g
l any seven day period (all excluding shift turnover l
g time).
l.
I I
4.
Except during extended shutdown periods, the use of g
l g
overt.ime should be considered on an individual basis l
g and not for the entire staff en a shift.
l l
I l
5.
When circumstances arise that require deviation from l
g[
the above, such deviations may be authorized by the
[
g Plant Manager or his designee. Authorized deviations l
g shall be recorded in the shift supervisor's log.
l 1
I 4.5.2 g
If a Reactor Operator or Senior Reactor Operator has been l
g working more than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> during periods of extended
.l l
shutdown (i.e., at duties away from the main control j
g board), he shall not be assigned licensed duties without l
least a 12-hour break preceding such an assignments.
at l
l L
ll@'
l l
l ll 1
l I
N/A g
g N/A ADM-0022 gg l
REV - 2
[
PAGE 14 0F 36 l 1
I 11 I
I I
i l
l 5.0 SHIFT OPERATIONS l
l l-l 5.1L. Shift Schedule l
l I
. d l.
5.1.1 The shift schedule shall be devised to provide twenty-four l l
hour coverage of operational activities. The schedule l
l must provide for vacation, sickness and training.
l 1
l l
5.2 Shift Relief l
l I
g 5.2.1 Shift cperating personnel on duty are to remain at their l
l assigned station with full responsibility for their l
l station, until properly relieved. Shift relief shall be a l l
formal evolution with documentation in accordance with l
l Reference 2.22.
l l
I l
5.2.2 As soon as practical after shift turnover the on coming SS l l-will.cour the plant and make contact with each watch l
2-l stander. During this contact, the SS will verify that all l l
watch standers appear to be physically and mentally able l
l to carry out their duties.
l l
I l
5.3 Notification
- l l
l
.l.
5.3.1 Some plant conditions and operating situations are of suc kl l
a nature that it is necessary or prudent to advise the GOB l L
l or designee of the circumstances. The SS must utilize ftis l Judgement and experience in assessing the need for such l
- ll notification. The following situations require verbal l'
1 l
notification:
l i.
l l
l 1.
Reactor Scram l
l I
l 2.
?!ajor equipment failure or malfunction l
l-l l
3.
Unexplained reactivity-changes l
I l
l 4.
Loss of off-site power l.
l I
l 5.
Any circumstances requiring unit outage or which l
l affect the ability to meet unit operations schedules.
l 1
'l 6.
Inadvertent Radioactive Liquid or Gaseous Release.
l l
l l
7.
?!ajor personnel injury or radiation overexposure.
l l
l 8.
Accidents occurring on plant property (except minor l
l injury).
l l
1 l
9.
All reportable events.
l l
l l
- 10. Events requiring immediate (red phone) NRC l
t l
notification.
l l
I O
i l
l 1
ll 1
1 I
l N/A l
N/A ll ADt!-0022 l
REV - 2
-l PAGE 15 0F 36 l 1
I II I
I I
s
,-ev---
,,----.,,-,,,--~ep.w--a,--m..,,,~-m---
m
-,wemw-,-w.-
,.v.,,r--..-n
.,--,-----r--,
,,-,--r-
I I
l
- 11. Violations of local, state, or federal pollution l
l (SPDES) regulations.
[
I h#
I l
- 12. Turbine trip.
l 1
I l
- 13. Load restrictions or inability to meet load l
l dispatchers requiremants.
l l
l l
5.3.2 The SS shall document in his log when he notifies the GOS, l l
or person on call.
If the GOS or his designee can not be l l
contacted, the on-call Emergency Director should be l
l notified. When cotification is required by Emergency Plan l l
Implementing Procedures, the above requirements are l
l superseded.
l 1
I l
5.4 Training l
1 I
l
?.4.1 It is important that operating personnel be informed in a l l
timely manner of plant modifications, procedure revisions, l license changes that have operational or safety l
l and l
significance. Training will normally be accomplished by l
l one of threc methods:
l l
I l
1.
On-shift formal instruction by Plant Instructors or l
l supervisory personnel.
l l
l l
2.
Covered as part of regularly scheduled license l
retraining.
l 3.
Placed in the required reading file.
l l
I l
5.5 Reactor Scram l
l I
l 5.5.1 When a reactor scram occurs, the SS or C0F will take the l
l following actions:
-l l
I l
1.
Ensure that the plant is placed in a safe condition by l -
l directing that the necessary operations are performed l
l in accordance with Reference 2.14.
I I
I l
5.5.2 Post Trip Review l
1 I
l The following information will be utilized to determine l
l thE direct and indirect causes for the trip:
l l
l 1.
Computer, printout of Sequence of Events (provide l
j details of log) (Process and ERIS).
I l
I l
2.
Computer princout of alarms (observe "first out").
l I
I l
3.
Other NSS Computer printout such as P-1, 00-3, and OD-l l
7.
l 4.' Status lights and annunciator windows.
l l
l l
11 1
I I
l N/A l
N/A ll ADM-0022 l
REV - 2 l
PAGE 16 0F 36 l 1
1 11 I
I l
~.
l
?
..f~
l The operators are directed not to reset any l
l a.
-l annunciators or status lights until they are l.
l noted.
[
l I
.l 5.
Recorder charts l
I I
The operators are directed to time and date each l
l a.
~
j' chart once per shift and as soon as practical l
l after a trip event.
l 1
l l-5.5.3 The SS is responsible for compiling all information and
[
l making the initial determination of the causa(s) for tha l
.l trip.
l l
1 l
1.
Determine if trip was spurious or.from an parameter l
2,tk
- ll.
deviation actual by comparing trip signals to other l
P.'
available instrumentation.
1 I
I l
a.
Complete Post-Trip Review Checklist (Enclosure 1). l 1
I l
2.
If trip was from actual parameter deviation, then l
l -~
determine the reason for the parameter deviation.
l l
l l
a.
Review FSAR Chapter 15 events.
l yv l
l b.
Review / complete applicable AOP's and ARP's.
l l
l l
c.
Consult with Reactor Engineering and maintenance l
l personnel.
l i
I s
l 3.
If_ trip was spurious, than determine what caused the l
l spurious trip and if the tripped channel has been l
l restored to a stabre state.
l l
I l
a.
Operator / Technician error l
l l
"2 l
b.
Power supply problems l
l 1*
' ' y,i.,2 l
c.
Radio interferrence l
9 l-l
[>
l d.
Relay / solid state device failure l
l
~
I
~'
-l 4.
Initiate repairs of the failed component (s) if l
l
.necessary.
l l
1 l
S.
Complete Scram Recovery prerequisites and Scram Report l j'
(Enclosure 2).
I I
I l.
6.
Report all the above to the GOS.
l 1
I l
5.5.4 The.GOS will review all compiled information (either over
(
-l-the phone or in person) and determine if restart is l
l authorized.
l
-l l
A l
l U
i l
i i
11 I
I I
l
-l N/A l
N/A ll ADM-0022 l
REV - 2
-l PAGE 17 0F 36 l~
- i i
I II I
I I
e
i
=
l l
l 1.
For straight forward causes such as operator error or [
g.
spurious trips he can make the authorization over the [
. phone with no other consultation and be recorded in l g l
the shift supervisors log.
l wp i
I l
2.
For more. complex situations such as actual FSAR
{
l Chapter 15 events the GOS should consult the
]
l following:
l 1
l l
a.
Reactor Engineering Supervisor 1
I I
l b.
Assistant Plant ?!anager-?!aintenance' l
1 I
Appropriate Technical Staff Supervisor l
l c.
l l
l and obtain concurrence from the Plant flanager and the i
g Assistant Plant Ifanager-Operations.
l 1
I l
3.
For complex situations, the GOS, or designee, should
[
g come to the plant to personally review the compiled
[
l information and interview personnel before authorizing l l
re-start.
l
[
.1 l
5.5.5 For any trip that the cause cannot be determined or l[
l corrected, the FRC shall convene to review the data befora l [
l recdemending restart.
1 l
I l
1.
Rostart shall be authorized by the Plant ?!anager, or
[
designee.
[
'l 2.
Plant !!anager should obtain eencurrence from the VP-l l
RBSG.
{
l 1
l 5.5.6 For all events, the Scram Report (Enclosure 2) and Post-
{
l Trip Review Checklist (Enclosure 1) shall be completely
[
g filled out and copies all supporting documentation shall l
l be attached (Recorder Charts, computer printouts, logs).
l I
I,.
l 1.
The Scram Report shall be assigned a sequential number l l
(83-01, etc).
l l
l l
2.
A copy of the scram report shall be retained in the l
l Control Room for 1 year.
l l
l l
3.
The original pai:kage shall be retained as a permanent l
g plant record per reference 2.13 after routing to Tech l
l Staff.
l
.l l
l 4.' Restart is performed in accordance with Reference l
l 2.13.
[
l 1
I I
1 l
l l 43 l
1 QP l
I l
l 11 l
.I I
l N/A l
N/A ll ADef-0022 l
REV - 2 l
PAGE 18 0F 36 l l
l ll 1
I I
l
'l l
5.6 Generator Load Changes l
5.6.1 Generator load changes will normally be requested by the
(...
l System Load Dispatcher. When requested to change load the [
l NCO shall obtain concurrence from the SS and C0F and l
l comply with the Dispatcher's request.
The NCO shall l
l inform the JS when all load changes are complete. The l
l Load Dispatcher shall be notified by the NCO when tite
[
l l
requested load change is completed. Whenever plant l
l conditions dictate a load reduction, the Load Dispatcher l
l will be notified as soon as possible.
l l-I l
5.7 Instrumentation and Control l
1 i
l 5.7.1 Personnel shall not adjust or operate any set points, etc. l q,;.
l inside the control panels or on meter faces unless such l
l action is specifically called for in an approved l
q,'
l-procedure.
l l
l l
5.8 Operation During Abnormal or Emergency Conditions l
l l
l l
5.8.1 When operations are not a's expected, return to a known l
l safe condition.
If conditions warrant, reduce power level l l
as required until the cause of the condition haa been
' l l
determined and the status of the core is known to be in a ; i l
safe condition. Guidelines for equipment use during l
l emergencies is contained in Reference 2.12.
l I
I
_ (e.
l 5.9 Control Room References
[
l 1
l 5.9.1 To assist operations personnel in the conduct of their l
l duties, reference information reitted to plant operation.
l l
safety and administration is perniitted in the control l
l room.
Only controlled, approved documents are to be used l
l to conduct operations. The GOS is responsible for l
l ensuring that the controlled reference information is l
l maintained current. To meet these needs, the controlled l
l reference information listed below will be available in l*
.g l
the control room area.
l l
l l
1.
Plant Operating Procedures l
l
~C I
l 2.
Final Safety Analysis Report l
l I
l 3.
Technical Specifications l
1 l
l 4.
Selected Technical Manuals I
I l
S.
Selected Prints l
- l 1
l 6.
l I
l-7.
Setpoints Document l
l l
O i
~
i l
I il l
I I
l N/A l
N/A ll ADM-0022 l
REV - 2
'l PAGE 19 0F 36 l 1'
I ll I
I I
1 m,
-r
.4 y
l I
l 8.
Selected Tables and Curves l
l 1
,h l
9.
Radiation Protection Plan l
g j
l "i@
l 5.10 Housekeeping l
l I
l 5.10.1 The control room will be maintained in a clean and orderly l l
condition in the interest of safe and efficient l
l operations. The responsibility for keeping the control l
l room in this condition is that of all shif t operating l
l personnel. All dusting and cleaning of control consoles, l
l instrument panels, computer consoles, kitchen area, and l
l the orderly storage of books, drawings and records will be l l
performed by shift operating personnel.
It is sometimes l
l advisable not to clean or dust in some areas of the l
l control room during plant power operations because of the l
l hazard of bumping or otherwise moving critical controls.
l l
1-l 5.10.2 The NEOs are responsible for maintaining their watch l
l stations in a neat and orderly fashion.
l l
I l
5.11 Bypass of Safety Functions and Jumper Control l
l 1
[
5.11.1 All activitics involving lifted leads and jumpers will be [ [
' l conducted in accordance with Reference 2.17 with the
, l l
exception of jumpers, mechanical blocks or other comporar)l l
devices specified for us'e by the E0Ps or AOPs during l
l_
performance of these procedures shall be identified,
.l
'l maintained and controlled as follows:
l' 1
I l
1.
Premade and labeled for its incended function.
l I
I l
2.
Retained in locked storage in the control rcom when l
l not in use.
l 1
I l
3.
Controlled by S/S.
l l
l
}
4.
Not used except for its intended function.
l*
l l
l 5.12 Safety Clearance and Tagging i
i I
l 5.12.1 All safety clearance and tagging activities will be l
l conducted in accordance with Reference 2.18.
l I
I l
S.13 Control Room Conduct l
l I
l 5.13.1 Potentially distracting activities in the control room and l l
other watch stations are prohibited (for example: radios, l
l TV, alcohol or drug use, games, horseplay, hobbies and l
l reading that is not job related).
I i
i I
(
.l 5.13.2 Control room access must be limited to those persons on l
l the official access list.
l l
l@
l 1
1 1
11 1
-l I
l N/A l
N/A ll AD.'l-0022 j
REV - 2 l
PAGE 20 0F 36 l 1
I il 1
-l I
i
,vi
l l
l 5.13.3 All necessary plant-related technical / administrative l
l control room business must be conducted at a location and l.
l in such a manner that neither licensed control room l
l operator attentiveness nor the professional atmosphere l
l will be comprised.
l l
l l
5.13.4 No unauthorized, uncontrolled notes, pictures, graphs, l
l prints, etc. shall be used as operator aids for the l
l performance of Safety related activities.
l 1
I l
5.13.5 The "At-The-Controls area" will be identified for l
l restricted access, and casual access for non-work related l l
reasons will be prohibited (see Figure 2).
l l
l l
5.13.6 Permission to enter the "At-The-Controls area" for l
g l
personnel other than the shift complement must be obtained 1 l
from the At-The-Controls Operator,-Unit Operator, COF or l
4 l
the SS.
During periods of abnormal-or emergency l
l operations, permission shall be obtained from the SS.
l l
1 l
5.13.7 The SS and the C0F have the authority to restrict access l
l to or remove personnel from the control room during l
l routine and emergency operation.
,l l
1 l
5.13.8 The shift personnel must react / respond to instrument
,l l
Indications and annunciators in accordance with approved,
, l l
procedures unless they have been verified incorrect by l
l other instrumentation and data (Reference 2.26).
I j
5.14 Shift / Evolution Briefings l
l l
l 5.14.1 Briefings shall be conducted for individuals involved in l
l an evolution that is b4ing performed. The detail of the l
l briefing is dependent on the degree of complexity, l
l routineness, logistics, or number of people invcived.
l l
l l
5.14.2 The individual who is to perform the activity is l
l responsible to adequately review the procedure, to fully l'
l understand what he is doing, and to be cognizant of all l
l the limitations, precautions, and requirements.
l l
l l
5.14.3 Because some evolutions may be very complex, occur over an l l
estended period of time, or not be covered by approved l
l pro.cedures, the SS may supply written instructions or l
l checklists.
l l
1 l
l l
I l
l l
I I
I I
I I
I I
I C'
l l
EJ l-1 I
I It I
l I
l N/A l
N/A ll ADM-0022
[
REV - 2 l-PAGE 21 0F 36 l l
l ll l
1 I
e-
- .. s l
1 l'
3.14.4 Evolutions involving many individuals, especially from two l l
or more departments or disciplines, may require large l '
l formal briefings or preplanning sessions.
If the 1 56 l
evolution is complex and involves close coordination, the l l
briefing session should include:
I I
I l
1.
A review of the appropriate section of the procedure I
l by key parties.
l l
1 l
2.
Examination of each individual's specific involvement l l
and responsibility.
I I
I l
3.
Discussion of expected results or performance; review l l
of limitations, hold points, emergency action to be I
g l
taken if contingencies arise.
I I
I l
4.
Ensure that everyone understands the interface and l
l communications required.
I I
I l
5.15 Fire Brigade l
I I
l 5.13.1 A brigade of at least 5 members shall be maintained on l
l site at all times. The members of the fire brigade shalli l l
be designated each shift on the control room status board,I l
The fire brigade shall not include those personnel
! lI l
required in the control room nor those personnel required!
l for a safe sliutdown of the plan.
l 5.16 Key Control h
l I
l 5.16.1 A list identifying each key-contcolled item and area l
l should be maintained in the SS's affice. Keys shall be l
l maintained in a locked cabinet, under the control of the l
l SS.
Permission to obtain a controlled key shall only be l
l given by either the SS or COF.
l I
I l
5.16.2 Controlled keys are issued to certain "0N DUTY" operating ~ l l.
l classifications.
Possession of such keys will be l
necessary to perform normal and emergency duties within an l l
area of responsibility. The controlled keys remain on the l l
operator's person during assigned hours of duty and are l
l not permitted to be used by unauthorized individuals.
I I
I
[
5.16.3 A key control log shall be maintained.
Entries shall show l l
the purpose for which a controlled key was required, l
l personnel using it, their badge number,'and time it was l
l removed and returned to the key cabinet.
l I
I l
5.16.4 A physical inventory should be conducted at least semi-l l-annually for locks and keys used for operations (Reference l l
2.26).
I I
I I
I l
I I
I i
11 1
l l
l N/A l
N/A ll ADM-0022 l
REV - 2 I
PAGE 22 0F 36 l l
l ll l
I I
er w
y 7-
-v
l
-(
l l
5.17 Comoonent Labeling, and Posted Signs l
l 1-fm l
5.17.1 Labeling of components or systems and posting of signs l
(v) l will be performed in accordance with Reference 2.19.
l g
l 5.18 Radiological Controls l
l l
l 5.18.1 All personnel must be continuously alert to the l
l radiological aspects of the work / evolution they are l
l involved in and take appropriate actions to minimize man-l l
rem exposure and to control the generation and spread of l
l radioactive contamination.
l 1
I l
5.18.2 Very high radiation areas shall be locked and prior to l
l entry into these areas Radiation Protection personnel l
P l
shall be contacted. This shall apply except in an l
g, emergency condition.
l 1
I l
5.19 Eguipment Removal / Return to Service l
l l
l 5.19.1 Prior to remcval of equipment from service, the Operations l l
Section will verify the equipment may be removed.
Before~ [
l authorizing the removal for maintenance, testing, or
,l l
operational activities the following will be performed:
l 1
. Verify the equipment or system can be removed from I
l 1.
.l service.
l
[
.l 1
2.
Determine how long it may be removed from service.
l 3.
In the case of a component or system that is required l
l by Technical Speci(ications, attention shall be given l
l to the potentially degraded degree of protection when l
l one subsystem of a redundant safety system has been.
l l
removed from service.
l I
I l
4.
Documencing the removal from service per Reference
[,
l 2.20.
[
l I
l 5.19.2 Following maintenance on or modification to a l
l system / component, the Operations Section is responsible l
l for verifying the operable condition of the l
l system / component to comply with Tech Spec's.
Verification l l
may be accomplished by either special testing or by l
l adherence to surveillance testing.
In the case of the l
l component / system that is not covered by Technical l
l Specifications, a special return to service inspection l
l shall be performed.
Requirements on tests performed shall l l
be logged on the Maintenance Work Reques't per Reference l
l 2.20.
l l
l l
1.
Mechanical coupling
'l l
I l
2.
Blinding flanges installed / removed l
l l
l l
ll l
.I l
l N/A l
N/A ll ADM-0022 l
REV - 2
-l PAGE 23 0F 36 l l
l ll l
l 1
s i
I j
3.
Electrically connected l
.l 1-g 4.
Area cleanliness
[
g l
- W g
5.
Valve alignment l
1 I
l 6.
Proper lubrication l
1 I
g 7.
System integrity l
1 I
l 8.
Hand torquing of remotely operated valves
[
l l
l 9.
System filled and vented
{
l I
l 5.19.3 Components of the Reactor Trip System and other safety l
l related components must (as a minimum) be demonstrated
[
g operable by performance of the applicable Surveillance
[
g
, Test Procedure (s).
l 1
I l
5.20 Equipment Rotation l
1 I
g 5.20.1 The SS or C0F should ensure major plant equipment is l
l rotated monthly when continued plant operation is not
,[
g jeopardized to maintain equipment run times near equal.
l l l
Equipment run times are maintained in the Equipment Run
- ll g
Time Log as described in Reference 2.23.
l l
6.0 PLANT OPERATING PROCEDURES
'g lh l
I l
6.1 Procedure Compliance l
1 I
l 6.1.1 Plant equipment shall b,e operated in accordance with l
g written approved procedures.
l 1
I l
6.1.2 If the individual actually performing the activity cannot
[
g or believes he should not follow the procedure governing
[
g that activity as written, he shall place the l
g system / component into a stable and safe condition and l,
l inform the responsible supervisor. The supervisor shall
[
g resolve the discrepancy in the procedure by either:
l I
I g
1.
Determining the methods by which the activity can be.
l l
performed using the procedure as. written and conveying l l
. this to be the individual performing the activity, or I
I I
l 2.
Submitting a procedure change, either temporary or l
l permanent depending on the actual situation.
(No
(
g Further procedural steps shall be accomplished until l
1 l
the procedure change is approved in accordance with l
l Reference 2.21.
(
I I
I I
I I
l l@
l I
I I
11 1
I I
l N/A l
N/A ll ADM-0022 l
REV - 2 l
PAGE 24 0F 36 l l
l 11 I
I I
1 I
~*
l 6.1.3 In the event of an emergency not covered by an approved l
l procedure, operators shall take action so as to minimize l
(q l
personnel injury, damage to the facility, and to protect l
'y l
the health and safety of the public.
l l
l l
6.1.4 It is the policy of the Operations Group that no interlock l l
will be bypassed or defeated from performing its function l
[
unicss it is accomplished in accordance with an approved l
l procedura or work request.
l I
I l
6.2 Procedure Imolementation l
l 1
l 6.2.1 Procedures that control operations where reliance on l
l memory cannot be trusted and where operations must be l
l performed in a specified sequence shall be followed step-l i;$c l
by-step with the procedure in hand. Many procedures will l
l also require signoffs, while others may need to be l
l referred to only occasionally. Routine procedural actions [
l that are frequently performed may not necessitate the use l
l of a procedure.
If there is any doubt as to the l
l procedural action by the individual performing the job, l
l the procedure must be in hand. Entry conditions of
[
l cmergency procedures shall be committed to memory by
, l l
licensed personnel.
l l
l 6.2.2 If an evolution is suspe,nded for an extended period of l.
l l
l time, reverification of the initial, conditions is required [
as determined by the SS.
l
}l l-V l
6.2.3 Controlled copies of appropricte system operating l
l procedures and temporary proceduras shall be available to l
l all Operations Section, personnel for in-plant use at l
l important local / manual stations.
l l
l l
6.3 Procedure Sign-Off List l
l 1
l 6.3.1 Procedure sign-off lists are used as an aid in confirming l,
l the completion of steps in proper sequence as,, required.
l l
In addition, it provides formal documentation of the
[
l completion of critical steps in the procedure and thus l
l aids in any subsequent determination of equipment or l
l system status.
Sign-off lists are executed when specified l l
by the associated procedure or when included as an l
l Intogral part of the procedure. After the completion of l
l each item on the sign-off list, the operator completing l
l the sten initials the item. The operator completing the l
l final item of the sign-off list signs the list to signify l
l its completion'. The sign-off list is then reviewed by the l l
, SS and placed in the control room status file. The l
l previous n-off list is removed from the file and l
l forwarde( o the GOS for distribution per reference 2.15.
l l
1 1
I I
I
("'i l
l O
l l
l l
ll l
..I l
l N/A l
N/A ll ADM-0022 l
REV - 2 t
PAGE 25 0F 36 l 1
l ll l
l l
s l
l l
6.4 System Check Lists l
l 1
l 6.4.1 System check lists are used for establishing and l.g, l
confirming the status of equipment and systems. Systems l %1 l
check lists are performed as a prerequisites for system l
l operation and periodically for equipment status l
l verification.
l 1
l l
6.4.2 The _ operator will be instructed to note the position of l
l all components with any discrepancies to be resolved at a l
l later time, OR he will be instructed to reposition l
l components that are found not to be positioned in l
l accordance with the check list.
l l
1 l
6.4.3 When checking a manual valve's position, it must always be l l
operated in the close direction. NEVER CHECK A VALVE BY l
l MOVING IT IN THE OPEN DIRECTION.
l 1
I l
6.4.4 When all check list items are completed, the operator who l
l ccmpletes the final item signs and dates the check list l
l signifying completion. For safety-related and other l
l important systems an independent position verification l
l will then be performed by a second qualified individual.
l l
Each completed check list l
completion and to determine exceptions or unusualis reviewed by the
[ {l l
conditions. The completed check list is inserted in the l l l
control room system status file. The superseded check -
l
'll list is forwarded to the GOS for distribution per l
.h references 2.15.
I l
1 l
6.4.5 Selected valves will be sealed in position to prevent l
l undetected tampering (I,EIN 83-27).
l 1
I l
6.4.6 Independent verification is intended to mean a second l
l check of the position or status of a component or system.
l l
The independent verification will be performed separately l
l without visual or audible contact with the first performer l,
l (Reference 2.24).
{
l l
l 6.5 Periodic Review of Operating Procedures l
l I
l 6.5.1 The following procedure categories are defined as l
l operating procedures:
l l
l l
1.
General Operating Procedures l
1 I
l 2.
System Operating Procedures l
1 I
l 3.
Alarm Response Procedures l
l 1
l 4.
Emergency Operating Procedures l
l 1
l S.
Fuel Handling Procedures l
l l
1 h"-
l l
I l
l ll 1
1 I
l N/A l
N/A ll ADM-0022 l
REV - 2
'l PAGE 26 0F 36 l 1
I ll l
1 I
c--
m w
s-.
es.-4
~.
- '8 l.
1 4
[
6.
Surveillance Test Procedures (Operations Group) l l
I'
- {}
l 7.
Abnor:nal Operating Procedures l
v l
l l
6.5.2 The GOS is responsible for conducting a periodic review of I l
operating procedures per Reference 2.21 with the exception l l
of AOPs and E0Ps, which will be reviewed annually.
l l
Appropriate documentation of this review will be made.
I l
Applicable procedures will be reviewed folicwing an l
l unusual incident such as an accident, an unexpected l
l transient, significant operator error, or major equipment l
l valfunction where inadequate procedural controls l
l ccstributed to the incident. Applicable procedures will l
l be reviewed following modification to a plant syste.
I g
l When procedures are determined to be inadequate through l
W*
l reviev or during use, the procedure will be revised.
l l-I l
6.5.3 Review of Night Orders, Standing Orders and Special Orders l l
shall be done by the GOS or designee on a periodic basis l
l not be exceed 90 days (Reference 2.26).
I I
I l
7.0 -SHIFT RECORDS AND LOGS I
^
l
' I l
Shift records and logs will be maintained and reviewed in accordance i l l
with Reference 2.23.
l l l
l 7.1 Night Order Book
. t I l
s
-1~
I
[\\
~
- l SS will be responsible for impl eenting these orders. The l
_ l 7.1.1 The GOS will from time to time iu.:e night orders, and the I i
l Night Orders Book will ncrmally ba kept in the SS's l
l o f fic.e. All night orders vill be signed and dated by the l
l individual issuing them. Orerators on shift will read and l l
initial night orders c. the shifts following their being l
l written.
l I
I l
7.2 Standing Orders l.
I I
l 7.2.1 A Standing Order will be used as a vehicle for-l l.
disseminating information or non-procedural information, l-l relative to the conduct of operations,. of an intermediate l
l to long-term nature. These memorandums will be serialized l l
for a period of one year (i.e., 83-01, 63-02, etc.).
l l
Ackhowledgement of receipt and understanding will be l
l accomplished via a signature sheet for each Standing l
[
Order.
l l
'l I
l I
I I
l l
l l
1 l
l
,o I'"
i I
l l
ll l
I I
l N/A l-N/A ll ADM-0022 l
REV - 2
. 1 PAGE 27 CF 36 l t
i I
II I
I I
,------.,--ywe,-
g--
c
---.m-,w-,
.r.v..--
v.,
, ---m%-,
--,.,y._,
.w.v-
,7
..t 1 e-
.l.
1 l
7.3 Limiting Conditions for Operation l
-7.3.1 The COF will initiate a LCO Status Sheet (Enclosure 3) for 1 x
l any LCO which becomes-effective during his shift. This l
l will be. accomplished by filling out Section I of the LCO l
l Status-Sheet with the following information:
I I
I l
1.
Date and time LCO became effective l
1 I
l 2.
Condition initiating LCO l
l 1
l 3.
Reference to applicable section of Technical l
l Specifications for the particular LCO.
l I
I l
4.
Required time for completion of restoration (maximum I
l time allowed by Technical Specifications to continue l
l operatioris in present mode with LCO in effect).
l I
I l
5.
Required action if time exceeded (action required by I
l Technical Specifications if restoration is not made by l
.l time specified in "4" above).
I l-l l
6.
Testing or other actions required by Technical l
l Specifications while LCO in effect (any limitations or I
l plant operation or special surveillance testing).
I I
I l
7.
C0F's signature.
l 7.3.2 Section I of the status sheet will then be reviewed and l
l signed by the SS and filed in the LCO Status Binder under l
l the applicable Operational Condition. The pink copy will l
l be forwarded to the designated individual of the Technical l l
Staff for reporting purposes at the time the LCO is l
l initiated.
Subsequently, for as 'long as the LCO-is in l
l effect, the C0F will insure that the required time for l
l completion of restoration will not be exceeded during his l
l shift. The COF will initial Section II indicating that I-
~
l any testing or actions (specified in Section I) required l
l by Technical Specifications have been completed as l
l applicable to his shift.
l I
I l
7.3.3 When the LCO is no longer in effect, the C0F will complete l l
Section III of the status sheet and forward it to the,SS l
l.,
GOS.
If cummulative inoperative restrictions apply to the l for review. The SS will forward :he status sheet to the l
l l
LCO, the COF will have a copy made for the control room l
l files prior tio forwarding the status sheet to the GOS.
l I
I I
I I
I I
I l
'l l
I i
l@
l l
I I
ll l
1 l
l N/A l
N/A ll ADM-0022 l
REV - 2
- l PAGE 28 0F 35 l
I I
II I
I I
q *;- p l
l 8.0 S!!RVEILLANCE TESTING g
l l
l-The GOS is responsible for overall performance contro.1 and e
(
coordination of the operations surveillance testing program.
l l
-l l
~8.1 Operations Surveillance Tests l
l
-1 The Operations Section is responsible for the performance,.l1 8.1.1 g
g documentation and initial review of operations j
surveillance tests.
l l
I 8.1.2 The SS/C0F approval will be obtained prior to the l
g l
commencement of any surveillance testing. The performer l
g of the test will record the information required by the l
g
- est procedure in the appropriate space and initial each j
ze g
step as it is completed. The performer will sign and date l l
the procedure upon completion of the test.
All items will j be written in ink.
If a step is not completed for any l
l reason, the reason must be recorded on the procedure.
l g
When a test is performed and does not meet the specified l
g acceptance _ criteria, the SS will be notified and
[
g corrective action initiated.
l l
l 8.1.3 The SS/C0F will review all surveillance tests performed o l
.l g
his shif t.for completeness and accuracy and shall so l
g indicate by signing and dating the procedure (s) in the I
l appropriate space.
In addition, he will ensure that an,
l l
'g entry is made on the control room surveillance test l
(Q
=
schedule to document the completion of operations section l
/
g test.
l l
l 8.2 Conditional or Off-Normal Surveillance Requirements g
l l
l 8.2.1 The SS/C0F is responsible for establishing the schedule.of l g
g surveillance testing to comply with Technical
[
_g Specification requirements in ccnditional or off-normal l
l situations.
l, I
I
..g33.,
j l
l l
l I
1 l
I l-I l
I 1
I I
I I
I 1
I
-l l
l 1
l l
- O l
l 1
l l
ll l
- 1. l
.I g
N/A l
N/A ll ADM-0022 l
REV - 2
-1 PAGE 29 0F 36 - l j
i i
ll l
l 1
~.
.. _ _,. -,. _ _ _ _, _,, _ - - - -. - - - - ~ _
e
.o l
i I'l l
I I
l FIGURE - 1 l
OPERATIONS GROUP ORGANIZATION 1
I 4
l ef I
l l
l I
GENERAL I
OPERATIONS I
l-SUPERVISOR l
AsstsTANT g
g OPERATIONS l
St'PERVISOR I
i l
SECRETARY I
l CLERx l
I l
l l
l l
l sutri l
[
SUPERVISOR l
[
l 1
I I
I 1
SaIrT l
CLERK i
1 l
CONTROL l
OPERATING l
r0 Rests l
.I I
I I
I I
I l
1 l
l l
I NUCLEAR l
- l CONTROL l
OPERATORS I
I I
I I
I I
I I
I I
I I
NectEAR I
l EQUIPMENT l
OPERATORS I
I I
I I
I l
l 11 I
I l
' FIGURE - 1 I
PAGE 1 0F 1 ll ADM-0022 l
REV - 2 l
PAGE 30 0F 36 l l
l Il I
I I
l l
l
[
l I
l l
FIGURE - 2 l
CONTROL R00t! AND AT-THE-CONTROLS AREA (IIII) l CAD,1 I
I 91
. y ;w w.,,.
I
- g%.s.c... s l
I
_;s es
,s s s
l c
- i--l:i L il l
I li Ml ht ll "115!Ril;ilgIi8 E s's h.
l f
i ht :siliui ih 88 l
g i
-ti s
l
.L.q l
l-]l l it i og jii:11:1leiIE's:!:ticil O(:f l
o
[
l l
l{
i
-j 1,3
,,,iir ;7ud jj
EEE y
I l
l ss, ;
l
- gl l
l
}-l tir ! t its ironi {i j.1 ri:li tsi is $ 18 I je3 l
l l
l s
[
2 2;f i
l f..f l il lil liflif fII Ifi fil IfIlii4I II l
[a l
.i k jLaiti!nI
{i ji I it I it i si I f.h..l l
I I
I h
I 4.l I!
[
is in ill 4 1 !'dd I
il a
l l
1
~ ' ANSSNS%'RsN FNNNs NW"'
s
- _;j I
_. E.j I
i;i l
-L 1
g;.
l l
11P.!
l
[
'NN'
' ' N'\\(cj '
'dl IQ l
N t
stj - h;;
l,iz.'.9 l
i l
-t
- ts t:
.. dI3N.
x i c-l gh.4Ys.
N $$
k-rN i
I d
x I
i I
i M-ndd
,3, ili 1
i nid I !!5! /
I I
sj
- i+ r l
l 7x--.
. sssWww eNNw svasv.1
's l
- b l
k I~"
l it sa-ge..
I 191 u
i ts i i-- l 1 if I
E.'-:,.3jes I
-c=
1 i
+i 1
h,4. ! lj55 I
2:!
l 1ll
$ it n.
sj. I ti i 11 l
if i
j l
l g
gs-ilth gi'y
- -7sE 'i!Ui I
j'jji ti i
I l
. i.
l l
i-i-l 5:i a
- t; la"
' 4Y.!$'
I I
g ggq N'dfi '
i i
I h%MNh1N '%R ' !
ab.
l
[
l II I
l l
l FIGURE - 2 l
PAGE 1 0F 1 ll ADBI-0022 l-REV - 2 l
PAGE 31 0F 36 l l
l 11 I
l l
o e -o l-1 I-1 I
I l
ENCLOSURE - 1 l
POST TRIP REVIEW CHECKLIST J
l l
(dQ l
V l tit!E/DATE/# OF SCRA!!
l l
I l _ Review Computer Trip Logs and Sequence-of-Events Logs to determine " Initial Scram l
l Signal".
l l
(Initial Scram Signal) l l
1 l _ Review computer alarm printout and annunciator " hits" to confirm " Initial Scram l
l Signal" l
.l l
.l Review Computer Trip Logs, P-1, OD-3, and OD-7 printouts to determine that all l'
l required automatic Safety-Related actions occurred.
l I
I l
Review Control Room Logbook and Shift Supervisors Logbook to determine if any work l
l was going on that could have generated the condition that generated the scram.
l l
l l _ Review the following recorders.to determine what additional conditions have contri-l l
buted to the scram and if Safety-Related Automatic Action occurred as required.
l l
Reactor Water Level (wide range) (P680) l Reactor Recirc Loop A/B Flw (P680) l APRtf/IRt! (P680) l l
Rx Level / Press A/B (P601) l Standby Service Water Flow (P870) l, l'
l Drywell Pressure (P808)
[
l l
.Contmt Atmos Temp I/II (P808) l Drywell Atmos Temp I/II (P808) h l
Suppression Pool Temp I/II (P808) l Contmt/Drywell Analyzer I/II (P808) l l
ADS SRV Temp ?!onitoring (P614) l l
Off-Gas System After Filter Disch Flow (P845) l l
1 l
l l
Interview Shift Operations personnel before the end of the affected shift, 7.0 l
l determine the cause of the scram, what automatic actions occurred, and what manual l
l actions were taken.
.l 1
l l
Review recorders, control room logs, computer sequence-of-events printout, and
,l l
computer alarm printout for the following parameters to determine if any safety l
]~
systems function was supposed to actuate. Check any that exceeded a trip / actuation l
l setpoint:
l l
RPV Water Level t!ain Condenser Vacuum l
l RPV Pressure Drywell Pressure l
l
!!ain Steam Line Pressure t!ain Steam Line Flow l
l Flain Steam Line Radiation CRD Disch Vol Water Level l
l Steam Pipe Tunnel Temp 1R!i Power Level l
l' APRt! Power Level SRt! Flux l
l Flode Switch Position
?!SIV Position l
l Turbine Control Valve Position.
Turbine Stop Valve Position l
l Reactor Protection Sys Trip Logic 4.16KV Bus Voltage l
l Suppression Pool Level Drywell Sump Flow Rates l
1 I
I I
il I
l l
ENCLOSURE - 1 l
PAGE 1 0F 2 ll AD!i-0022 l
REV - 2 l
PAGE 32 0F 36 1 I
I ll l
l l
m i.
O e
l_
l i
I I
. I I
' I ENCLOSURE - 1 l
POST TRIP REVIEW CHECKLIST (Continued)
'l
[
l 1
. N. A l
I Log any safety systems functions that were. supposed to actuate, but did not I
1 I
I i
I I
I I
I I
I I
I I
I I
I Shift Supervisor I
'.n
'1, - l l~
-?;ti 1 I
'f I I
e.
g l
Mi 1
1 i
i
.t I
I I
I 1
1
- *')
l l
I I
9 I
I
,il I
u l.
I I
1 l
- i. I I
I I
l 1.
1 I
. :1
.I
'1} l' l l
dl I
%I I
ga 1
-l
- 3. '. l l
1 I
I l
l l
l 1
1 I
I I
I I
I I
I I
I I
I I-I I
II i
1 1
ENCLOSURE - 1 I
PAGE 2 0F 2 ll ADM-0022 I
REV - 2 I
PAGE 33 0F 36 l' l-1 II I
I l
h 1=
p
.r--,-
gw e,,m+
n- - - -
,e--s.
w--e e
-9
,-'t
c <
o, i
I I
I' I
I
.I l
ENCLOSURE - 2 l
SCRAM REPORT I
I e
I l Date:
Time:
_ Number:
l l
l MODE SWITCH l
REACTOR l
FLOW CONTROL I
l CAUSE l
POSITION l
STATUS l
STATUS l
l l
l l
l l _ Operator Error l
Run l
Critical l
Loop ?!anual j
i l
i I
I l
Testing Error l
Startup l
MWT l Flux Manual l
l l
1 1
I l
Equipment Failure l Refuel l
Subcritical l
Master ?!anual l
l i
I I
I l
Other l
l l
Master Auto l
l l
l 1
l l
l SCRAM TIMES l
l l
STATION STATUS l
(For Monitored CRDS's) l STATION CONDITIONS l
1 I
I I
l Starting-Up l
None Available l Core Flow Lb/Hr l l
l l
l l
Shutting Down l Average Seconds l Reactor Pressure Psig l l
l 1
I l
Changing Power l Fastest Rod l Steam Flow Lb/Hr l l
1 1
I l
Steady State l Time Seconds l Vessel Level I5ches l l
l 1
I l
Surveillance l Slowest Rod l Feedwater Flow Lb/Hgg l
Testing l
l
'y l
Other l Time Seconds l Radwaste Building Vent l
l l
Activity Mr/Hr l l
1 I
I l
l l Plant Exhaust Stack l
l l
l Activity Mr/Hr I I
I i
1 l
l l Fuel Building Vent l
l l
l Activity Mr/Hr'l l
l 1
I l
l l_ Generator Output MWE "__Of f l l
l l Brief Description of Scram:
l l
l l
l l
l l Contributing Conditions:
I l
l l
I l
l l Suspected Cause of Scram:
[
l l
I I
I I
i 1
l Operator At-The-Controls [.
l ENCLOSURE - 2 l
PAGE'l 0F 2 ll ADM-0022 l
REV - 2 1
PAGE 34 0F 36 I I
I II I
I
. g a r,
+
> g, l
l e-r l-I
.I
(,.J.s l ENCLOSURE - 2 l
SCRAM REPORT (Continued) l 1
1 I
Vl l
l 1.' Requirements of A0P-0001 " Reactor Scram" have been completed:
l l
I I
I I
I l 2. Determination of the cause of the scram / bases *:
l l
1 I
I
- c 1 1
I I
I.
I
..r JS;" l 1.
7, l
Shift Supervisor l
Wl I
"[ l 3. Determination that the cause of the scram has been corrected / bases *:
l l
l
.I
-l 1.
'l I
..I l
1 I
,[
Shift Supervisor l
l l
l 4. Classification of scram:
Spurous Actual Para:ceter Deviation l
ml l
I i
1
'l Shift Supervisor l
l
.I
-l S. Personnel Contacted:
l 1
I I
I l
General Operations Supervisor l l
l
,~
j
.l I
I gi: _l 6' FRC Review required:
Yes No l
-l I
I I
l 7. Authorization to Restart / Concurrence:
l l
I 1
l l~ General Operations FRC Chairman Plant Manager VP-RBNG l
l Supervisor l
I l
l
- Attach supporting documentation (copies of records, charts, logs, etc.), use additional l l pages as necessary.
I l
l l
l l
I I
I I
>m I
(J l
11 I
I i
l ENCLOSURE - 2 l
E..JE 2 0F 2 ll ADM-0022 l
REV - 2 l
PAGE 35 0F 36 l l-l_
ll l
l l
l 3
o.3 t
I
-1 I
I I
I I
l-ENCLOSURE - 3 l
LCO STATUS SHEET
-1 I
)
l SECTION I l
LCO EFFECTIVE ll RESTORATION REQUIRED ll TECH SPEC REF ll MODES l
l DATE l
TIME ll DATE l
TIME ll ll l
l l
11 l
ll 11 I
I l
l CONDITION INITIATING LCO:
l 1
1 1
I I
I l
i I
I
.l REQUIRED ACTION IF RESTORATION TIME IS EXCEEDED:
l l
1 1
I I
I I
I I
I l REQUIRED ACTION WHILE LCO IN EFFECT:
l 1
l l
I I
I
~
i l C0F:
SHIFT SUPERVISOR:
I l
l SECTION II l FOREMAN'S INITIALS INDICATE THAT ANY TESTING OR ACTIONS REQUIRED HAVE BEEN COMPLETED.
1 I
I l
MONTH l-l l
l l
l l
l l
l l
l l
l l
DATE l
l l
l l
l l
l l
l l
l l
l l
NIGHT l
l l
l l
l l
l l
l l
l l
l l
DAY l
l l
l l
l l
l l
l l
l l
l l
EVENING l l
l l
l l
l l
l l
l l
l l
1
-l I
i l
MONTH l
l l
l l
l l
l l
l l
l l
l l
DATE l
l l
l l
l l
l l
l l
l l
l l
NIGHT l
l l
l l
l l
l l
l l
l l
l I
DAY l
l l
l l
l l
l l
l l
l l
l l
EVENING l l
l
~ l l
l l
l l
l l
l l
l l
SECTION III l
l LCO NO LONGER IN EFFECT: DATE TIME l
l TIME LCO IN EFFECT: DAYS HOURS l
l CORRECTIVE ACTION REQUIRED:
l l
l l
I I
I I
i l
I I
I l
CONTROL OPERATING FOREMAN SHIFT SUPERVISOR GENERAL OPERATIONS
. C,s4 l
SUPERVISOR REVIEW 47/
I I
ll l
l l
l ENCLOSURE - 3 l
PAGE 10F 1 ll ADM-0022 l
REV - 2 l
PAGE 36 0F 36 l l
l ll 1
1 I
/
.