Rev 0 to Action Plan 1C, Auxiliary Feed Pump Turbine Manual/Auto-Essential Control ProblemML20129D574 |
Person / Time |
---|
Site: |
Davis Besse |
---|
Issue date: |
06/24/1985 |
---|
From: |
Jain S TOLEDO EDISON CO. |
---|
To: |
|
---|
References |
---|
NUDOCS 8507300094 |
Download: ML20129D574 (6) |
|
|
---|
Category:GENERAL EXTERNAL TECHNICAL REPORTS
MONTHYEARML20207E8011999-05-19019 May 1999 Non-proprietary Rev 2 to HI-981933, Design & Licensing Rept DBNPS Unit 1 Cask Pit Rack Installation Project ML20205K5781998-12-31031 December 1998 Waterhammer Phenomena in Containment Air Cooler Swss ML20217P8041998-04-0707 April 1998 11RFO OTSG ECT Insp Scope ML20196B8771996-12-16016 December 1996 First Amended & Restated Master Decommissioning Trust Agreement Dtd as of 961231 Between Toledo Edison Co & Mellon Bank ML20196B8951996-12-16016 December 1996 First Amended & Restated Master Decommissioning Trust Agreement Dtd as of 961216 Between Cleveland Electric Illuminating Co & Mellon Bank ML20134D7821996-05-0808 May 1996 Rev 1 to Instrument Drift Data Analysis Methodology & Assumptions ML20091S4311995-08-31031 August 1995 USI A-46 Seismic Evaluation Rept. W/61 Oversize Drawings ML20138J1411994-02-28028 February 1994 Rev 0 to IPEEE,A-46 & Design In-Structure Response Spectra for Selected Bldgs at Dbnps ML20067D3311993-08-31031 August 1993 Technical Evaluation Rept,Evaluation of B&Wog Pressurizer Surge Line Thermal Stratification Program to Address NRC Bulletin 88-11 ML20091P5721991-10-31031 October 1991 Reactor Containment Bldg Integrated Leak Rate Test Including,Type A,B & C Periodic Test Results ML20070Q1911991-03-25025 March 1991 NRC Form 474 Simulation Facility Certification ML20058L1891990-08-0101 August 1990 Dcrdr Human Engineering Discrepancy Repts 1988 Summary Addendum 1,Vol 1 ML20006E3671990-01-11011 January 1990 Toledo Edison Co Mark-BZ Fuel Assembly Seismic & LOCA Analysis. ML20094J0841989-12-0808 December 1989 Investigation of Acoustic Leak Monitoring for NRC Region Iii. Info Partially Deleted ML19324C1761989-10-30030 October 1989 Hpi/Makeup Nozzle Weld Overlay Repair Contingency Plan. ML19327B0161989-10-11011 October 1989 Cycle 7 LOCA Limits. ML20245K6751989-08-0202 August 1989 Rev 2 to Review 18 Month PM Items for Diesel Generator & Evaluate Extension to 30 Months ML20151Z1941988-08-11011 August 1988 Rept on Reactor Vessel Continuous Vent Line Performance, ML20234F2501988-01-0606 January 1988 Rev 3 to App R Compliance Assessmemt Rept ML20147C0851987-12-0101 December 1987 Fifth Refueling Outage Executive Summary. Related Documents Encl ML20237J9781987-08-24024 August 1987 Performance Indicators for Davis-Besse Nuclear Power Station,Salp 6,Weekly Rept 3 for Period Ending 870824 ML20214J1891987-05-0505 May 1987 Rev 2 to App R Compliance Assessment Rept ML20206J5001987-03-31031 March 1987 Dcrdr Special Study Plans for Davis-Besse ML20212G7461987-01-0707 January 1987 Rept of Emergency Evacuation Review Team on Emergency Response Plans for Perry & Davis-Besse Nuclear Power Plants ML20214E0761986-11-17017 November 1986 Auxiliary Feedwater Calculation Summary ML20211E0651986-09-26026 September 1986 Transient Assessment Program Rept,Davis-Besse Unit 1 Reactor Trip on High Flux,840302 ML20214T7501986-09-11011 September 1986 DB Small-Break LOCA Analysis Assumptions Evaluation ML20154Q6531986-02-28028 February 1986 Westinghouse Owners Group Position on Davis-Besse Event ML20141E6691985-11-30030 November 1985 B&W Owners Group Action Plan for Review of 850609 Davis-Besse Transient ML20138H4891985-11-25025 November 1985 Rev 17 to Seismic Category I Piping Sys Support & Hanger Discrepancies ML20136H0951985-11-15015 November 1985 Revised Davis-Besse Reactor Protection Sys Single Failure Analysis ML20137H3971985-11-12012 November 1985 Rev 16 to Seismic Category I Piping Sys Support & Hanger Discrepancies Summary Rept ML20137S9031985-10-29029 October 1985 Toledo Edison Davis-Besse Nuclear Power Station Unit 1 Seismic Category I Piping Sys Support & Hanger Discrepancies,Summary Rept ML20209H5861985-10-28028 October 1985 Rev 3 to Course of Action ML20137S8241985-10-22022 October 1985 Rev 14 to Seismic Category I Piping Sys & Hanger Discrepancies,Summary Rept ML20209H6481985-10-15015 October 1985 Rev 3 to Auxiliary Feedwater Pump Turbine Overspeed Trip Throttle Valve Problem ML20138J4811985-10-15015 October 1985 Seismic Category I Piping Sys Support & Hanger Discrepancies ML20133M9911985-10-0808 October 1985 Rev 12 to Seismic Category I Piping Sys Support & Hanger Discrepancies,Summary Rept ML20133K9881985-10-0404 October 1985 Independent Mgt Assessment of Toledo Edison Davis-Besse QA Program ML20138A9411985-09-24024 September 1985 Rev 10 to Safety-Related Piping Sys Support & Hanger Discrepancies, Summary Rept ML20132E4471985-09-17017 September 1985 Rev 9 to Safety-Related Piping Sys Support & Hanger Discrepancies, Summary Rept ML20137C3021985-09-0909 September 1985 Toledo Edison Co Davis-Besse Nuclear Power Station Course of Action Rept ML20137M5431985-09-0909 September 1985 Vols 1 & 2 of Davis-Besse Course of Action ML20135D7421985-09-0303 September 1985 Rev 7 to Safety-Related Piping Sys Support & Hanger Discrepancies, Summary Rept ML20133K9941985-08-30030 August 1985 Rept of Assessment of Actions at Davis-Besse Resulting from 850609 Loss of Feedwater Event ML20134Q0161985-08-27027 August 1985 Rev 6 to Safety-Related Piping Sys Support & Hanger Discrepancies, Summary Rept ML20137U3061985-08-16016 August 1985 Rev 5 to Safety-Related Piping Sys Support & Hanger Discrepancies, Summary Rept ML20134B8371985-08-0909 August 1985 Rev 4 to Safety-Related Piping Sys Support & Hangar Discrepancies, Summary Rept ML20133M3261985-07-26026 July 1985 Rev 3 to Safety-Related Piping Sys Support & Hanger Discrepancies,Summary Rept ML20126L9021985-07-0505 July 1985 Rev 1 to Action Plans 5,6 & 7, Steam & Feedwater Rupture Control Sys Trip/Msiv Closure 1999-05-19
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217K1231999-10-14014 October 1999 Revised Positions for DBNPS & Pnpp QA Program ML20217D5441999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Davis-Besse Nuclear Power Station.With ML20211R0811999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20211B0271999-08-13013 August 1999 SER Accepting Second 10-year Interval Inservice Insp Requests for Relief RR-A16,RR-A17 & RR-B9 for Plant, Unit 1 ML20210Q8541999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20209E6231999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20195K2871999-06-16016 June 1999 Safety Evaluation Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20195F4871999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20207E8011999-05-19019 May 1999 Non-proprietary Rev 2 to HI-981933, Design & Licensing Rept DBNPS Unit 1 Cask Pit Rack Installation Project ML20207F4351999-05-0404 May 1999 Rev 1 to DBNPS Emergency Preparedness Evaluated Exercise Manual 990504 ML20206M6341999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Davis-Besse Nuclear Station,Unit 1.With ML20205M2931999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Davis-Besse Nuclear Power Station.With ML20207J1461999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20199H5931999-01-20020 January 1999 Safety Evaluation Accepting Thermo-Lag Re Ampacity Derating Issues for Plant ML20204J6751998-12-31031 December 1998 1998 Annual Rept for Dbnps,Unit 1,PNPP,Unit 1 & BVPS Units 1 & 2 ML20199E2501998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20206B0101998-12-31031 December 1998 1998 Annual Rept for Firstenergy Corp, for Perry Nuclear Power Plant & Davis-Besse Nuclear Power Station.Form 10-K Annual Rept to Us Securities & Exchange Commission for Fiscal Yr Ending 981231,encl ML20205K5781998-12-31031 December 1998 Waterhammer Phenomena in Containment Air Cooler Swss ML20197J3441998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20195D0001998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20155B6781998-10-28028 October 1998 Safety Evaluation Accepting Proposed Reduction in Commitment Changes in QA Program Matl Receipt Insp Process ML20154H5801998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20151W1611998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Dbnps.With ML20237E3171998-08-21021 August 1998 ISI Summary Rept of Eleventh Refueling Outage Activities for Davis-Besse Nuclear Power Station ML20237B1681998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20236U5011998-07-23023 July 1998 Special Rept:On 980624,Unit 1 Site Damaged by Tornado & High Winds.Alert Declared by DBNPS Staff,Dbnps Emergency Response Facilities Activiated & Special Insp Team Deployed to Site by Nrc,As Result of Event ML20236R1441998-07-15015 July 1998 SER Related to Quality Assurance Program Description Changes for Davis-Besse Nuclear Power Station,Unit 1 ML20236N7451998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20236K3981998-06-30030 June 1998 SER Accepting in Part & Denying in Part Relief Requests from Some of ASME Section XI Requirements as Endorsed by 10CFR50.55a for Containment Insp for Davis-Besse Nuclear Power Station,Unit 1 ML20236K5131998-06-29029 June 1998 Safety Evaluation Accepting Proposed Alternate Emergency Operations Facility Location for Davis-Besse Nuclear Power Station,Unit 1 ML20248F7441998-05-31031 May 1998 Reactor Vessel Working Group,Response to RAI Regarding Reactor Pressure Vessel Integrity ML20249A4121998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20196B5221998-05-23023 May 1998 10CFR50.59 Summary Rept of Facility Changes,Tests & Experiments Dbnps,Unit 1 for 960602-980523 ML20236E7581998-05-19019 May 1998 Rev 0 to Davis-Besse Unit 1 Cycle 12 Colr ML20236N7501998-04-30030 April 1998 Rev 2 to Monthly Operating Rept for Apr 1998 for Davis-Besse Nuclear Power Station,Unit ML20247F6721998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Davis-Bess Nuclear Power Station,Unit 1 ML20249A4141998-04-30030 April 1998 Revised Monthly Operating Rept for Apr 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20217P8041998-04-0707 April 1998 11RFO OTSG ECT Insp Scope ML20216B4041998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20216C5131998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20202D3721998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Davis-Besse Nuclear Power Station,Unit 1 ML20199G6321998-01-26026 January 1998 Rev 1 to Davis-Besse Unit 1,Cycle 11,COLR ML20198R4771998-01-13013 January 1998 SER Approving Second 10-year Interval Inservice Inspection Program Plan Requests for Relief for Davis-Besse Nuclear Power Station,Unit 1 ML20198K7931997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Davis-Besse Nuclear Power Station,Unit 1 ML20217K6401997-12-31031 December 1997 1997 Annual Rept First Energy ML20203A3931997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Davis-Besse Nuclear Power Plant,Unit 1 ML20198S5371997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Davis-Besse Nuclear Power Station ML20217H7701997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Davis-Besse Nuclear Power Station,Unit 1 ML20216H3261997-08-31031 August 1997 Monthly Operating Rept for August 1997 for DBNPS ML20217K0241997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Davis Besse Nuclear Power Station,Unit 1 1999-09-30
[Table view] |
Text
.. . . . . - . _ - - . - . . . .- _ . - . _ . - . . _ - . - . _ . . ..-. .
p . ~* fg-1 s
4 e
i i
ACTION PLAN p IC !
- . /
TITLE: AFPT MANUAL / AUTO-ESSENTIAL CONTROL PROBLEM 1.
i i
l 2
I f
i APPR.
I CHAIRMAN FOR REV DATE REASON FOR REVISION BY TASK FORCE IMPL.
1 t 0 6/24/85 Initial Issue S.C. Jain i -
i i
8507300094 850624 ,
PDR ADOCM 05000346 p PDit I i .
l l
l r
TITLE: AFPT MANUAL / AUTO-ESSENTIAL CONTROL PROBLEM PREPARED BY: Sushil C. Jain PLAN NO. 1C DATE PREPARED: June 24, 1985 PAGE 1 of 4
- 1. INTRODUCTION This report provides an evaluation of the June 9, 1985, trip in relation to the apparent inability to take manual and auto-essential control of the auxiliary feed pump turbines (AFPT) from the Control Room. This inability was experienced following the full SFRCS trip actuation of both Auxiliary Feedwater System (AFWS) trains and subsequent trip of both AFPT's on overspeed. This report has been prepared in accordance with the " Guidelines to Follow When Trouble-shooting or Performing Investigative Actions into the Root Causes Surrounding the June 9, 1985 Reactor Trip, Revision 4."
SL'MMARY OF DATA A. Known information and operational data for cor litions prior to, during, and after the transient.
PRIOR TO THE TRANSIENT:
Both AFWS trains were in their normal standby condition with the associated AFPT controllers (in the Control Room) in the " auto essential" position and the trip throttle valve aligned open.
This is established by the absence of alarms from computer points Z012 and Z013 (AFP1 and 2 Auto-Essen Level Control Transfer Switch Alarm) prior to the transient. Also the trip throttle valve must be open for AFPT's to start. Su rveillance testing and maintenance history prior to the transient is in-cluded in Section B.
DURING THE TRANSIENT:
The following chronology is listed to facilitate cross-referencing with the alarm printout and to identify the development of events relating to SFRCS actuation. AFP/AFPT initiation, and subsequent operation and control of AFWS.
COMPUTER TIME POINT ID DESCRIPTION 1:41:04 Q963 A full trip of SFRCS occurred on steam generator low level.
1:41:08 P680/P681 SFRCS main steam line low pressure trip on Channels 1 and 2 (manual trip).
COMPUTER TIME POINT ID DESCRIPTION
- 1:41:31 S007/Z001 AFPT-1 tripped on overspeed and its stop valve started to close.
1:41:44 S017/Z002 AFPT-2 tripped on overspeed and its stop valve started to close.
1:42:00 P680/P681 SFRCS main steam line low pressure trip on Channels 1 and 2 manually reset.
1:45:50 S017 AFPT-2 overspeed trip reset.
1:46:12 Z013 AFPT-2 control switch in Control Room placed in manual, indicating manual control of AFPT-2 from Control Room.
- 1:46:50 Z012 AFPT-1 control switch in Control Room placed in manual, indicating (attempted) manual control of AFPT-1.
- 1:47:02 ZO12 AFPT-1 control switch placed in auto.
- 1:47:26 2012 Manual control of AFPT-1 re-attempted.
- 1:50:47 2012 AFPT-1 control switch placed in auto.
- 1:50:51 2012 Manual control of AFPT-1 (re-attempted).
1:52:53 ZOO 2 AFPT-2 stop valve fully open.
1:53:51 Z002 AFPT-2 stop valve not fully open.
1:56:08 Z001 AFPT-1 stop valve fully open.
1:56:56 S008 AFPT-1 speed high.
1:57:22 L885 SG-1 start up range level normal.
1:57:37 L895 SG-2 start up range level normal.
1:58:39 Z001 AFFT-1 stop valve started to close.
1:58:55 S008 AFPT-1 speed normal.
1:58:57 S007 AFPT-1 overspeed trip reset.
From a review of the above, it is evident that soon after the STRCS actuation, both AFPT's tripped on overspeed (also see Action Plans 1A and 1B). The turbine overspeed trip device is connected to the overspeed trip linkage and ultimately to the
, trip throttle valve as indicated in Figure 1. The trip throttle valve serves to provide the only steam path to the AFPT's. Note that with an overspeed trip, the trip throttle valve will be closed.
AFTER THE TRANSIENT:
At approximately 2 p.m. on June 9, 1985, ST 5071.02 AFWS Refueling Test was conducted which demonstrated successful control of AFPT's in manual mode from the Control Room.
B. MAINTENANCE AND SURVEILLANCE / TESTING HISTORY A review of maintenance history for the AFPT level control mechanism revealed no pertinent maintenance bcing performed on either the Control Room switches or the speed control mechanisms.
The surveillance test of significance to this action plan is ST 5071.04 AFWS monthly functional test. This test ensures Control Room capability and operation of level control mechanism in both the manual as well as auto essential control modes. The test is conducted monthly on a staggered test basis on each AFPT. This test was last conducted on June 7, 1985, for AFPT-1 and on May 21, 1985, for AFPT-2 with all acceptance criteria being met.
Control of AFPTs in manual mode from the Control Room is also demonstrated on a monthly basis by ST 5071.01, AFWS monthly test. This test was last conducted on May 23, 1985, for AFP 1-1 and on June 6, 1985, for AFP 1-2. Although no specific accept-ance criteria are associated in this procedure regarding manual control, demonstration of this capability is integral with successful completion of the surveillance test.
III. CHANGE ANALYSIS A review of the modification and maintenance history from 1983 to date does not reveal any Facility Change Request and/or Maintenance Work Order (preventive or corrective) directly related to Control Room operation of the AFPT's in manual or auto essential mode.
IV. HYPOTHESIS Following a detailed review of the digital data obtained from the data acquisition and display system and the alarm log, as correlated with cperator interviews, it became clear that the perceived inability to take control from the Control Room was directly attributable to the inability to re-latch the trip throttle valve linkage and the difficulty and delay in opening the trip throttle valve following the AFPT trip on overspeed. Following evidence and evaluation is offered to support this hypothesis:
, A. The equipment operators that were dispatched to investigate and restore the AFPT's after overspeed trip, identified their difficulty in re-latching the trip linkage to the trip throttle valve in the normal fashion. The operators. reported that even though they followed the procedural steps for engaging the trip hcok with the latch-up lever, they were unable to open the trip throttle valve for "several" minutes.
B. The problem of interest to this action plan appears to have occurred for approximately 4 minutes (f rom 1:46:50 - 1:50:51) for AFPT-1 as shown by events highlighted with an asterisk on page 2. This corresponds very well with the overspeed trip, operator dispatch to AFP rooms, attempted opening (with delay) of the trip throttle valve, and inability to completely open this valve.
C. Since the trip throttle valve provides the only path of steam to the AFPT, AFPT motion and speed control cannot be completely established until this valve is latched and fully open. The placement of Control Room switch in manual and speed control switch in raise or lower will only have controlled the governor valve.
D. The Control Room operator believing that the equipment operator in AFP-1 room had fully opened and latched the trip throttle valve realized that turbine was still not up to full speed. In order to improvise, several transfers to manual and auto-essential control were attempted with no appreciable benefits gained in AFPT performance because the trip throttle valve was indeed not fully open.
E. Lack of unavailability of enough steam for AFPT-1 for the above timeframe is substantiated by the digital data on AFPT-1 speed.
It is emphasized that later in the transient, because of initial difficulty in re-latching and fully opening the trip throttle valve as mentioned above, both AFPT's were controlled locally by controlling the trip throttle valve. Auto essential control was never attempted.
This is substantiated by absence of associated computer points Z012 and Z013 in the alarm log for the time period of interest.
V. ACTION PLAN From the above evaluation, it is evident that the root cause of the subject inability to assume control of AFPT-1 from Control Room is the difficulty and delay in opening the trip throttle valve. Since the latter is an integral part of Action Plan ID an independent action plan is not necessary and, therefore, is not developed.
Further, since the resolution of trip throttle valve issue is being controlled and tracked by that action plan, it is recommended that the AFPT-1 control inability issue be hereby closed, de a/6
..i .
ACTION PLAN Ms NUMHE H PAGE .
1 a' 1
'3**** .
IC TITLE ___.___m.DATE PREPARED PHEPARED BY
~ AFPT MANUAL / AUTO ESSENTIAL CONTROL PROBLEM (Rev. 0) ~
June 25, 1985 Sushil Jain_
SPE"CIFIC oBJE CTIVE To Verify Operability of Manual and Auto-Essential Control of Both AFPT's from the Control Room STEP PRIME ASSIGNED START TARGET DATE ACTION STEPS NUMBER RFSPONSIBILITY TO DATE DATE COMPLETED
- 1. As part of Action Plan _1A/B, perform visual inspection of the K.A. Yarger/
governor control _ system for each AFPT to identify _ any_ S,C,_Jain_ .
mechanical or electrical problem that may_have caused loss of remote control.
- 2. Prior to testing to be conducted per Action Plan 1A/B, perform K.A._Yarger __
ST 5071.04 to verify AFPT operation in both the manual and auto-essential modes from the Control Roon including the following:
Manual Mode: Verify control in both increase and decrease directions Auto-Essential Mode: Verify control de low and high setpoints
- 3. Exercise and monitor above controls (as specified in 2) while K.A. Yarger performing testing per Action Plan 1A/B in Mode 3.