ML20129B390

From kanterella
Jump to navigation Jump to search
Insp Rept 50-346/96-08 on 960624-0711 & 0814-15.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support
ML20129B390
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/12/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20129B388 List:
References
50-346-96-08, 50-346-96-8, NUDOCS 9609230023
Download: ML20129B390 (14)


See also: IR 05000346/1996008

Text

--- - --..

-a.

-

..n--,,,..+wn

.

..

.

!

!

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

,

,

Docket No:

50-346

f

License No:

NPF-3

,

,

Report No:

50-346/96008

,

Licensee:

Toledo Edison Company

Facility:

Davis-Besse Nuclear Power Station

'

.

'

Location:

5503 N. State Rte. 2

Oak Harbor, OH '43449

Dates:

June 24 - July 11 and August 14-15, 1996

Inspector:

D. Schrum, Reactor Engineer

Approved by:

R. N. Gardner, Chief, Engineering Branch 2

..y'

9609230023 960912

DR

ADOCK 050003 6

.

I

.

..

l

!

!

,

i

Report Details

.

!

IV. Plant Suonort

!

l

F1

Control of Fire Protection Activities

l

,

F1.1 Motor Operated Valve (M0VF Hot Shorti

a.

Insoection Scoce

The inspector reviewed the circumstances surrounding a potential-

!

condition outside of the facility's Appendix R design basis. The

condition involved plant fires which could cause a loss of remote

!

shutdown capability due to fire-induced spurious energization of MOVs to

a stalled condition, thus damaging the valves and preventing subsequent

. manual operation from outside the control room to achieve and maintain

j

safe shutdown. This issue was previously identified as Unresolved Item-

50-346/96002-05(DRP) in Inspection Report 50-346/96002.

,

b.

Findinas and Observations

[

In the mid-1980's, the licensee identified the potential for hot shorts

to adversely effect MOVs during postulated plant fires. The licensee

-had identified such MOVs in the safe shutdown procedures and Fire

.

!

Hazards Analysis Report (FHAR); however, the licensee had assumed that

manual actions could be taken to reposition valves during and following

the fire.

On February 28, 1992, the NRC issued Information Notice (IN) 92-18,

" Potential for loss of Remote Shutdown Capability During a Control Room

Fire." This IN identified a potential common mode failure mechanism of

MOVs in which a postulated fire could cause hot short damage to the

valve control circuit in such a way as to bypass the valve protective

features (i.e., valve limit switches and torque switches).

The

resulting fire-induced spurious operation of a valve could result in

physical damage to the valve operator or the valve itself.

)

'

The licensee's initial evaluation of IN 92-18 was performed in April

1994.

Davis-Besse followed Nuclear Energy Institute's (NEI) (formerly

NUMARC) recommendation not to take corrective actions for IN 92-18

i

because NEI considered a fire in the control room a low probability

,

event.

The licensee stated in its evaluation that certain safe shutdown

-

MOVs were susceptible to hot short damage; however, the licensee took no

action and cited NEI guidance as its basis.

]

l

In March 1996, after the NRC stated that the licensee's response to IN

{

92-18 was not adequate, the licensee initiated further evaluations of

-circuits associated with MOVs credited for safe shutdown in the event of

a fire. The licensee performed an evaluation of its MOVs using weak

link / valve actuator thrust data. The potential for body-to-bonnet bolt

failures was also evaluated. The evaluation indicated that no valve

2

,

.

. .

.

-

,

- .

._

.._ . ,,, ,_,_.

y

- . .,

..

.

,

body-to-bonnet bolt failures would occur, which would result in the loss

of the Reactor Coolant System (RCS) pressure boundary.

However, 41

valves were identified as susceptible to damage.

These valves could be

damaged such that they would fail open or closed, and they could not be

manually repositioned during a design base fire. Therefore, this valve

damage puts the plant outside of the Appendix R post-fire safe shutdown

design basis.

The licensee's corrective actions included:

(1) modifications to ensure

,

that a hot short in the valve circuit does not cause valve damage or

affect its ability to be repositioned from emergency control stations;

(2) procedure changes to take credit for alternative valves to achieve

shutdown; (3) evaluations to show certain valves were not needed; and

(4) identification of those valves not needed early during the shutdown.

From the original population of 41 valves susceptible to damage, 25 were

eliminated from the list due to the effects of plant changes made since

original Appendix R evaluations were completed.

Listed below are the

most significant valves identified during the resolution of the hot

short issue and the potential consequences during a fire,

b.1 Plant Modifications

The following four valves required a circuit wiring modification to

ensure that they are available following a design base fire.

1

1.

M0V AF3870 - Auxiliary Feedwater (AFW) Pump 1 Discharge to Steam

Generator (SG) 1

This M0V could have been damaged during a control room fire. A valve

failure in the closed position would have resulted in a loss of

feedwater to SG 1.

This was the only SG assumed available in the event

I

of a control room fire.

The licensee stated that there was an altarnate

path that could be used to add water to the SG; however, the alternate

path was not identified in the licensee's Appendix R safe shutdown

analysis as being free of fire damage,

j

2.

M0V HP31 - High Pressure Injection (HPI) Pump 2 Recirculation Valve

This valve could have been damaged during a fire in fire area AB.

The

fire scenario assumes a Safety Feature Actuation Signal start of the HPI

pump and the loss of both Makeup (MU) pumps. A valve failure in the

closed direction would cause the HPI pump to overheat and fail in

i

approximately five minutes.

The plant would be in a forced cooldown to

allow reactor coolant water to be added using core flood tanks and Low

Pressure Safety Injection.

This could result in the plant's subcooling

margin being exceeded.

The licensee stated that the control room is

i

manned during this fire, so operators may have been able to identify

'

that the HPI pump was running and shut it off.

In addition, there may

have been sufficient time to establish an alternate recirculation path

or the HPI pump could have remained turned off until reactor coolant

pressure was below the pressure required to inject water.

A mitigating

circumstance for this event is the raised loop design which would give

3

.

-.

.

-.

-

_ - . - .

--

__

-

.

.

4

-

additional time (hours) to restore an alternate source of water before

core damage.

However, this alternative shutdown method has not been

analyzed and, therefore, its availability due to potential fire damage

,

has not been fully demonstrated.

3.

MOV MS106 - Auxiliary Feedwater Pump Turbine (AFPT) 1 Main Steam (MS)

Isolation Valve.

!

This MOV could have been damaged during a control room fire or a fire in

'

other areas. A valve failure in the closed direction would have

resulted in no steam being available to power the turbine driven AFW

pump.

In addition, damage was also assumed for MS106A, which is the

I

-

steam cross-tie from the second SG.

The potential existed for the

licensee to use alternate steam paths or use the motor driven feedpump;

'

,

however, these measures were not analyzed for potential fire damage and

!

their availability has not been fully demonstrated in the licensee's

safe shutdown analysis.

'

4.

MOV RC11 - Power Operated Relief Valve (PORV) Block Valve

4

This M0V could have been damaged during a control room fire.

In this

fire scenario, the PORV is assumed to fail open.

Consequently, a

failure of valve RCll in the open direction would result in a blowdown

of the reactor vessel (equivalent to a Loss of Coolant Accident).

Operator response involving feed / bleed activities would be assumed to

maintain core cooling; however, these actions were not included in the

licensee's safe shutdown analysis. The license stated that the

consequences of block valve damage were reduced by steps in the safe

shutdown procedure to shut the PORV block valve prior to abandoning the

control room during a fire and by guidance to depower the valve to

'

prevent valve damage soon after leaving the control room.

b.2 Procedure Chanaes

!

For the following four valves, procedure changes were required to

describe operator actions to accomplish the indicated function following

a design base fire.

1.

M0V AF 3869 - AFW Pump 1 Discharge to SG 2

i

This M0V could be damaged during a control room fire.

Damage to this

i

valve would result in an overfill of SG 2 and damage to AFW pump 1

turbine (steam is used from SG 2 to power the AFW pump).

However, plant

operators would have greater than 21 minutes to take actions to prevent

j

SG overfill by taking control of AFW pump speed and/or taking steps to

isolate feed system valves.

2.

MOV MU6419 - MU Discharge Valve

'

This M0V could be damaged during a control room fire.

Damage to thi_s

,

valve could result in the loss of MU capability.

However, this event

would involve a slow inventory loss problem and operators would have

4

.

.

reactor coolant pump seal injection available as well as alternate

injection paths.

3.

MOV SW1399 - CW Heat Exchanger (HX) in Header Isolation Valve

This MOV could be damaged during a control room or fire area BF fire.

Damage to this valve could result in a diversion of service water (SW)

to the non-safety related equipment and inadequate cooling of the safety

related equipment.

Safety related safe shutdown equipment could be

damaged.

However, the staff could ideatify this problem during the

implementation of the shutdown procedure and close the manual isolation

valve, which is located in the same area as this valve.

4.

M0V MS107 AFPT 1 MS in Isolation Valve

This MOV could be damaged during a control room fire or a fire in other

areas. A valve failure in the closed direction would result in no steam

being available to power the turbine driven AFW pump.

A procedure

change provided instructions to use an available redundant steam path in

the same area.

b.3 Lono Term Actions

The following valves were determined not to be time-line critical in

that manual operations of these valves could be performed in the long

term during post fire shutdown.

M0V Decay Heat (DH) 2733 DH Pump 1 Boiling Water Storage Tank (BWST)

Suction Valve

MOV DH 2734 DH Pump 2 BWST Suction Valve

MOV SW1366 Containment Air Cooling (CAC) 1 in Isolation Valve

MOV SW1367 CAC 2 in Isolation Valve

.

MOV SW1368 CAC 3 in Isolation Valve

MOV SW1382 AFW Pump 1 Suction Valve from SW

b.4 Root Causes

The following root causes contributed to the licensee not identifying

and correcting the MOV hot short problem:

1.

The licensee's initial reviews of Appendix R hot short requirements were

not adequate in identifying the MOV problems discussed in this report.

2.

The licensee performed a minimal review of IN 92-18.

In aadition,

operability determinations were not made for the conditions described in

the IN. Also, ins were given a lcw priority for review, so ins were

reviewed one to two years after they were issued.

3.

NEI (formerly NUMARC) issued a memorandum which stated that corrective

actions for hot shorts that cause valve damage were not necessary

because it was such a low probability event.

5

_ _ _ _ _ _ _

_ ..

__

_

__

.

.

'

c.

Conclusions - Licensee Immediate and Lona Term Corrective Actions

After the NRC identified that the response to IN 92-18 was not

acceptable, the licensee initiated an evaluation to determine which MOVs

were susceptible to damage during a fire. Subsequently, the licensee

took corrective actions to ensure that the plant could safely shut down

following a design base fire.

The inspector reviewed the licensee's M0V

,

modifications, alternative actions for potentially damaged M0Vs, and the

licensee's analysis for the remaining valves that were not required for

safe shutdown during a fire. The inspector had no concerns with the

remaining six valves which were included on the licensee's long term

corrective action list.

The inspector reviewed the changes to the FHAR

and safe shutdown procedures to ensure that applicable changes had been

made to implement actions required for safe shutdown. Also, the

inspector concluded that adequate improvements had been made to the

licensee's IN review process to prevent these types of problems not

being identified in the future.

.

l

However, prior to April 16, 1996, the licensee did not have alternative

shutdown capability, because potential fire-induced hot shorts put the

plant outside of its Appendix R safe shutdown design basis necessary to

!

achieve and maintain hot shutdown conditions. This is an apparent

'

violation of 10 CFR 50, Appendix R, Section III.G.3, Fire Protection of

Safe Shutdown Capability.

The corrective actions to resolve these

Appendix R post-fire safe shutdown deficiencies will be reviewed during

subsequent NRC inspections.

F1

Control of Fire Protection Activities

i

F1.2

Inoperable Thermo-laa Radiant Enerav Shields

a.

Insoection Scope

The inspectors reviewed the adequacy of radiant heat energy shields

installed in the containment and containment annulus areas.

This issue

was previously identified as Unresolved Item 50-346/96003-06(DRP) in

Inspection Report 50-346/96003,

b.

Findinas and Observations

In 1990, the licensee submitted an exemption request from Appendix R,

Section llI.G., regarding the use of radiant energy shields in the

,

annulus surrounding the containment. This request was based on the lar:k

of separation for safe shutdown cables. At that time, the licensee

believed that radiant energy shields constructed of Thermo-lag were

acceptable.

Approximately 170 linear feet of Thermo-lag energy shields

were installed in the containment and containment annulus.

Appendix R,Section III.G., precludes the use of combustibles to

(1) provide separation of redundant safe shutdown trains or (2) provide

radiant energy shield protection for shutdown components inside

containment. On December 15,1992, IN 92-82, "Results of Thermo-lag

6

i

_

.-

-.

.

.

330-1 Combustibility Testing," was issued to alert licensees that, based

on ASTM testing, Thermo-Lag fire barrier material was found to be

combustible. On May 31, 1995, IN 95-27, "NRC Review of Nuclear Energy

Institute, Thermo-Lag 330-1 Combustibility Evaluation Methodology Plant

Screening Guide," was issued.

This document stated that the NRC did not

accept the use of the NEI guide to justify the use of Thermo-lag

materials where noncombustible materials are specified by NRC fire

protection requirements or to assess the combustibility hazards

presented by Thermo-lag materials.

A fire in the containment and containment annulus could affect the

ability to safely achieve and maintain safe shutdown. The probability

of fire occurring in these areas is low due to the lack of an ignition

source and low combustible loading.

However, the safety consequences of

a fire in these areas could be high.

The radiant energy shields in containment are installed on electrical

circuits for CAC power and pressurizer level instrumentation.

The

radiant energy shields in the containment annulus protect electrical

circuits, including CAC power, pressurizer level instrumentation, high

point vent control, PORV power and PORV block valve power.

Appendix R

safe shutdown would be affected by the loss of these circuits; however,

the licensee has indicated that actions could be taken to reach cold

shutdown without the affected equipment.

b.2 Root Causes

The following root cause contributed to the failure to identify the

containment and annulus Thermo-lag radiant energy shields as

unacceptable and take compensatory measures for the impaired barriers.

The licensee performed a minimal review of ins. Also, ins were given a

low priority for review, so ins were reviewed one to two years after

they were issued.

c.

Conclusion - Anoarent Violation of Anoendix R

IN 92-82 and IN 95-27 gave the licensee prior opportunities to declare

the Thermo-lag radiant energy shields in the containment and in the

containment annulus areas inoperable and take adequate compensatory

measures until these barriers were replaced.

'

Based on the combustibility of Thermo-lag and the fire resistant ratings

being indeterminate, most licensees who had Thermo-lag inside

containment implemented the required compensatory measures for

inoperable rac'iant energy heat shields.

Davis-Besse did not implement

compensatory measures for the containment and the containment annulus

until after a conference call with the NRC on April 16, 1996.

10 CFR 50, Appendix R, Section III.G.2.f., requires radiant heat shields

to be constructed from noncombustible materials.

In addition, Generic Letter (GL) 86-10, Enclosure 2, Response to Question 3.7.1, provided

7

I

.

.

,

additional guidance pertaining to the design of radiant energy heat

shields inside containment.

GL 86-10 specifies that these shields

i

should be capable of directing convective energy for the fire away from

the protected division or train and the material used to construct these

shields should have a fire rating of 1/2 hour.

The failure to meet the this requirement is an apparent violation of

10 CFR 50, Appendix R, Section III.G.2.

V. Manaaement Meetinas

X1

Exit Meeting Summary

>

The inspectors met with licensee representatives after the inspection on

August 15, 1996, to discuss the scope and findings of the inspection.

-

,

During the exit meeting, the inspectors discussed the documents and

processes reviewed by the inspectors during the conduct of this

inspection and the likely informational content of the inspection

report.

Licensee representatives did not identify any such documents or

processes as proprietary.

i

i

i

8

,

.

.

.-

--.

.

.-

!

.

a

PARTIAL LIST OF PERSONS CONTACTED

Centerior Enerav/ Toledo Edison

J. Stetz, Senior Vice President, Nuclear

J. Wood, Vice President, Nuclear

J. Lash, Plant Manager

T. Myers, Director, Nuclear Assurance

1

'

L. Dohrmann, Manager, Quality Services

D. Eshelman, Manager, Operations

J. Rogers, Manager, Plant Engineering

R. Zyduck, Manager, Design Basis Engineering

J. Michaelis, Manager, Maintenance

'

J. Freels, Manager, Regulatory Affairs

E. Bergner, Manager, Nuclear Training

D. Wuokko, Regulatory Affairs Supervisor

M. Leisure, Regulatory Affairs Senior Engineer

K. Byrd, Senior Design Engineer

P. Smith, Regulatory Affairs Supervisor

A. Migas, Senior Design Engineer

M. Murtha, Fire Protection Engineer

V. Patton, Fire Protection Advisor

E

R. Gardner, Engineering Branch Chief

S. Stasek, Senior Resident Inspector

D. Schrum, Reactor Inspector

K. Zellers, Resident Inspector

9

a

.

.

INSPECTION PROCEDURES USED

IP 64704

Fire Protection Program

!

IP 71707

Plant Operations

,

IP 37550

Engineering

IP 37551

Onsite Engineering

'

IP 40500

Effectiveness of Licensee Controls in Identifying, Resolving, and

i

Preventing Problems

IP 92902

Followup - Engineering

j

i

l

i

10

. _ _ _ _ . _ . .

. - _ . -

. _ ,

___

. _ _

_

_ _ . _ . .

_ _ _ . . _ . . . _ _ . _ _ _ _ . _ . _ . _ . _ . . _ _ _ _ _ . . _ _ _ . _ - _ . _ - . ,

-

.

,

.

.

c

i

!

DEFINITIONS

i

Unresolved Items

,

Unresolved Items are matters about which more information is required in order

i

to ascertain whether they are acceptable items, violations, or deviations.

l

Unresolved items are discussed-in Paragraphs F.1.1.a and F.1.2.a.

,

.

t

,

11

J

. ._ _ _ _

_

_

_

._

.

. . _ .

.

_

__

__

_ ._

1

.

.

LIST OF ACRONYMS USED

AFPT Auxiliary Feedwater Pump Turbine

AFW

Auxiliary Feedwater

BWST Boiling Water Storage Tank

CAC

Containment Air Cooling

DH

Decay Heat

FHAR Fire Hazards Analysis Report

GL

Generic Letter

HPI

High Pressure Injection

l

HX

Heat Exchanger

IN

Information Notice

!

150

Isolation

MOV

Motor Operated Valve

MS

Main Steam

MU'

Makeup

NEI

Nuclear Energy Institute

NRC

Nuclear Regulatory Commission

PORV Power Operated Relief Valve

RCS

Reactor Coolant System

SG

Steam Generator

i

SW

Service Water

j

l

l

12

.

.

_

_

-

_.

.

_

._

_

_

.

-

34386

Federd Register / Vol. 60, No.126 / Friday, Jun) 30, 1995 / Notices

factors in arriving at the appropriate

is not held, the licensee will normally

is a matter of public record, such as an

severity level will be dependant on the

be requested to provide a written

adjudicatory decision by the

circumstances of the violation.

response to an inspection report,if

Department of Labor. In addition, with

However,if a licensee refuses to correct issued, as to the licensee's views on the the approval of the Executive Director

a minor violation within a reasonable

apparent violations and their root

for Operations, conferences will not be

time such that it willfully continues, the causes and a description of planned or

open ta the public where good cause has

violation should be categorized at least

implemented corredive action.

been shown after balancing the benefit

at a Severity LevelIV,

During the predecisional enforcement of the public observation against the

D. Violotions of Reporting Requirements conference, the licensee, vendor, or

potentialimpact on the agency's

other persons will be given an

enforcement action in a particular case.

The NRC expects licensees to provide opportunity to provide information

As soon as it is determined that a

complete, accurate, and timely

consistent with the purpose of the

conference will be open to public

information and reports. Accordingly,

unless otherwise categorized in the

conference, including an explanation to observation, the NRC will notify the

the NRC of the immediate corrective

licensee that the conference will be

Supplements, the severity level of a

actions (if any) that were taken

open to public observation as part of the

violation involving the failure to make

following identification of the potential egency's trial program. Consistent with

a required report to the NRC will be

violation or nonconformance and the

the agency's policy on open meetings,

based upon the significance of and the

long-term comprehensive actions that

" Staff Meetings Open to Public,"

circumstances surrounding tne matter

were taken or will be taken to prevent

published September 20,1994 (59 FR

that should have been reponed,

recurrence. Licensees, vendors, or other 48340), the NRC intends to announce

llowever, the severity level of an

persons will be told when a meeting is

OPen conferences normally at least to

untimely report, in contrast to no report, a predecisional enforcement conferencu. working days in advance of conferences

may be reduced depending on the

A predecisional enforcement

throu8 (1) notices posted in the Public

h

circumstances surrounding the matter.

conference is a meeting between the

Document Room,(2) a toll free

A licensee will not normally be cited for NRC and the licensee. Conferences are

telephone recording at 800-952- 9674,

a failure to report a condition or event

normally held in the regional offices

and (3) a toll-free electronic bulletin

unless the licensee was actually aware

and are not normally open to public

board at 800-952-9676. In addition, the

of the condition or event that it failed

observation. However, a trial program is NRC will also issue a press release and

to report. A licensee will, on the other

hand, normally be cited for a failure to

being conducted to o(le conferences for notify appropriate State liaison officers

n approximately

25 percent of all elig

that a predecisional enforcement

r: port a condition or event if the

public observation, i.e., every fourth

conference has been scheduled and that

licensee knew of the infonnation to be

eligible conferenco involvin8 one of

it is open to public observation.

reported, but did not recognize that it

three categories of licensees (reactor,

The public attending open

was required to make a report.

hospital, and other materials licensees)

conferences under the trial program may

V, Predecisional Enforcement

will be open to the public. Conferences

bserve but not participate in the

Conferences

will not normally be open to the public

conferenco. It is noted that the purpose

Whenever the NRC has learned of the if the enforcement action being

of conducting open conferences under

lated.

the trial program is not to maximize

contegould l$e taken against an

public attendance, but rather to

sxistence of a potential violation for

(1)

which escalated enforcement action

appears to be warranted, or recurring

individual, or if the ac' ion, though not

determine whether providing the public

nonconformance on the part of a

taken against an individual, turns on

with opportunities to be informed of

whether an individual has committed

NRC activities is compatible with the

vendor, the NRC may provide an

doing.

NRC's ability to exercise its regulatory

wron$nvolves significant personnel

and safety responsibilities. Therefore,

opportunity for a predecisional

(2)

enforcement conference with the

licensee, vendor, or other person before failures where the NRC has requested

members of the public will be allowed

that the individual (s) involved be

access to the NRC regional offices to

ttking enforcement action. The purpose present at the conference;

attend open enforcement conferences in

of the conference is to obtain

information that will assist the NRC in

(3)is based on the findings of an NRC accordance with the " Standard

Office ofInvestigations report; or

Operating Procedures For Providing

determining the appropnata

(4) Involves safeguards information,

Security Support For NRC Hearings And

enforcement action, such as:(1) A

Privacy Act information, or information Meetings," published November 1,1991

common understanding of facts, root

which could be considered proprietary: (56 FR 56251). These procedures

causes and missed opportunities

In addition, conferences will not

provide that visitors may be subject to

associated with the apparent violations, normally be open to the public if:

personnel screening, that signs, banners,

(2) a common understanding of

(5) The conference involves medical

posters, etc., not larger than 18" be

corrective action taken or planned, and

misadministrations or overexposures

perrnitted, and that disruptive persons

(3) a common understanding of the

and the conference cannot be conducted may be removed.

significance ofissues and the need for

without disclosing the exposed

Members of the public attending open

lasting comprehensive corrective action. Individual's name: or

conferences will be reminded that (1)

If the NRC concludes that it has

(6) The conference will be conducted the apparent violations discussed at

sufficient information to make an

by telephone or the conference will be

predecisional enforcement conferences

informed enforcement decision, a

conducted at a relatively small

are subject to further review and may be

conference will not normally be held

licensee's facility.

subject to change prior to any resulting

unless the licensee requests it. However,

Notwithstandmg meeting any of these enforcement action and (2) the

y

an opportunity for a conference will

criteria, a conference may still be open

statements of views or expressions of

p

normally be provided before issuing an

if the conference involves issues related opinion made by NRC employees at

j

order based on a violation of the rule on to an ongoing adjudicatory proceeding

predecisional enforcement conferences.

Deliberate Misconduct or a civil penalty with one or more intervonors or where

or the lack thereof, are not intended to

is an unlicensed person,if a conference the evidentiary basis for the confemnce represent final determinations or beliefs.

NUREG-1600

8

i

._.

_ . . . _ . . _ . . . - . . _ _ - . .

~ - -

-.

O

.

Federal Register / Vol. 60, No.126 / Friday, June 30, 1995 / Notices

34387

Persons attending open conferences will to be under oath. Normally, responses

management involvement in licensed

be provided an opportunity to submit

under oath will be required only in

activities and a decrease in protection of

written comments concerning the trial

connection with Severity Level I, II, or

the public health and safety.

program anonymously to the regional

III violations or orders.

office.These comments will be

The NRC uses the Notice of Violation

1. Base Civil Penalty

subsequently forwarded to the Director

as the usual method for formalizing the

'fhe NRC imposes different levels of

of the Office of Enforcement for review

existence of a violation,lasuance of a

penalties for different severity level

and consideration.

Notice of Violation is normally the only violations and different classes of

When needed to protect the public

enforcement action taken, exmpt in

licensees, vendors, and other persons.

health and safety or common defense

cases where the criteriefor issuance of

Tables 1A and 1B show the base civil

and security, escalated enforcement

civil penalties and orders, as set forth in penalties for various reactor, fuel cycle,

action, such as the issuance of an

Sections VI.B and VI.C. respectively, em materials, and vendor programs. (Civil

immediately effective order, will be

met. However, special circumstances

penalties issued to individuals are

taken before the conference. In these

regarding the violation findings may

determined on a case-by-case basis.) The

cases, a conference may be held after the warrant discretion being exercised such structure of these tables generally takes

t

j

escalated enformment action is taken,

that the NRC refrains from issuing a

into account the gravity of the violation

y tice of Vi lation. (See Section VII.B.,.)

as a primary consideration and the

VI. Enforcement Actions

Mitigation of Enforcement Sanctions.

ability to pay as a secondary

j

This section describes the

In addition, licensees are not ordinarily consideration. Generally, operations

enforcement sanctions available to the

cited for violations resuking from

i"" 1'i"8 8 *

i*

' rial

4

l

NRC and specifies the conditions under matters not within their control, such as

d

l1

l

which each may be used.The basic

equipment failures that were not

n

ces to

b a dlicensee

enforcement sanctions am Notices of

avoidable by reasonable licensee quality

1

i high

i il

'"P { Reg rding the secondary

i

Violation, civil penalties, and orders of assurance measures or management

(nal

various types. As discussed further in

controls. Generally, however, licensees

<

ab

1

f

l

Section VI.D. related administrative

are held responsible for the acts of their lic

to y the civi pena

it is

actions such as Notices of

employees. Accordingly,this policy

not the NRC intention that the

s

Jonconformance, Notices of Deviation, should not be construed to excuse

4

economic impact of a civil penalty be so

Con nna

Ac n

i'e

letters of

personnel errors,

,

,

ds

severe that it puts a licensee out of

!'

rmation am used to supplement the

B. Civi/ Penolty

business (orders, rather than civil

enforcement program. In selecting the

A civil penalty is a monetary penalty

Penalties, are used when the intent is to

suspend or terminate licensed,s ability

activities)

enforcement sanctions or administrative that may be imposed for violation of (1)

!

actions, the NRC will consider

certain specified licensing provisions of

or adversely affects a licensee

enforcement actions taken by other

the Atomic Energy Act or

to safely conduct licensed activities.

'

I

Federal or State regulatory bodies

supplementary NRC rules.or orders; (2)

The deterrent effect of civil penalties is

best served when the amounts of the

1

having concurrent jurisdiction, such as

any requirement for which a license

!

in transportation matters, Usually,

may be revoked; or (3) reporting

Penalties take into account a licensee's

whenever a viobtion of NRC

requirements under section 206 of the

ability to pay. In determining the

4

requirements of more than a minor

EnergyReorganization Actl Civil

amount of civil penalties for h,censees

,

for whom the tables do not reflect the

j

con::em is identified, enforcement

penalties are designed to deter future

i

action is taken. The nature and extent of violations both by the involved licensee ability to pay or the gravity of the

the enforcement action is intended to

as well as by other licensees conducting violation, the NRC will consider as

j

reflect the seriousness of the violation

similar activities and to emphasize the

necessary an increase or decrease on a

-

involved. For the vast majority of

need for licensees to identify violations case-by-case basis. Normally, if a

licensee can demonstrate financial

!

violations, a Notice of Violation or a

and take pro npt comprehensive

Notice of Nonconformance is the normal corrective action.

hardship, the NRC will consider

4

action.

Civil penalties are considered for

Payments over time, including interest,

.

Severity Level 111 violations. In addition, rather than reducing the amount of the

i

j

A. Notice of Violotion

civil penalties will normally be assessed

civil enalty, flowever, where a licensee

P

!

A Notice of Violation is a written

for Severity Levell and 11 violations and claims financial hardship, the limnsee

i

notice setting forth one or more

knowing and conscious violations of the will normally be requhed to address

l

violations of a legally binding

reporting requiremants of section 206 of why it has sufficient resources to safely

!

requirement. The Notice of Violation

the Energy Reorganization Act.

conduct licensed activities and pay

i

normally requires the recipient to

Civil penalties are used to encourage

license and inspection fees.

provide a written statement describing

prompt identification and prompt and

2. Civil Penalty Assessment

,

(t) the reasons for the violatior. or, if

comprehensive correction of violations,

2

contested, the basis for disputing the

to emphasize compliance in a manner

In an effort to (1) emphasize the

,

j

violation; (2) corrective steps that have

that deters future violations, and to

importance of adherence to

been taken and the results achieved; (3) serva to focus licensees * attention on

requirements and (2) reinforce prompt

'

corrective steps that will be taken to

violations of sigulficant regulatory

self-identification of problems and root

prevent recurrence; and (4) the dets

conoam.

causes and prompt and comprehensive

when full compliance will be achieve 1.

Although management involvement,

carrection of violations, the NRC

'

The NRC may waive all or portions of

direct or indirect, in a violation may

reviews each proposed civil penalty on

a written response to the extent relevant lead to an increase in the civil penalty,

its own merits and, after considering all

information has already been provided

the lack of managem6nt involvement

relevant circumstances, may adjust the

to the NRC in writing or documented in may not be used to mitigate a civil

base civil penalties shown in Table 1A

en NRC inspection report.The NRC may penalty. Allowing mitigation in the

and 1B for Severity IAvelI, H, and III

{

require responses to Notices of Violation latter case could encourage the lack of

violations as described below.

}

9

NUREG-1600

,

t

j-

I

--

,

-

_.

~-

- - - - - - - -

-

.

.

.

- . , - - - .

m ,

- - -

-w,

-

_

w

.

,.