ML20128D961
ML20128D961 | |
Person / Time | |
---|---|
Site: | LaSalle |
Issue date: | 05/20/1985 |
From: | Parker M ILLINOIS, STATE OF |
To: | Harold Denton Office of Nuclear Reactor Regulation |
References | |
DOE-85-071, DOE-85-71, NUDOCS 8505290255 | |
Download: ML20128D961 (1) | |
Similar Documents at LaSalle | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217H4661999-10-18018 October 1999
[Table view]Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl ML20217H6341999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for Kh Curran,Lm Gerlach,Rc Weber & Bt Rhodes Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC Form 396 Encl.Proprietary Info Withheld ML20217H6251999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for MR Kahn,Aj Mclaughlin,De Montgomery & Kr Murphy Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC from 396 Encl.Proprietary Info Withheld ML20217F4301999-10-14014 October 1999 Responds to 991012 Rai,Based on 991001 Telcon Re Suppl to Request for TS Change to Revise MCPR Safety Limit & Add Approved Siemens Topical Rept for LaSalle County Station, Unit 1 ML20217D3191999-10-12012 October 1999 Submits Request for Addl Info Re Licensee 990707 Proposed License Amend to Revise Min Critical Power Ratio.Listed Questions Were Discussed with Util in 991001 Telcon ML20217C1671999-10-0808 October 1999 Provides Suppl to RAI for Approval of Unreviewed Safety Question Re Assessment of Certain safety-related Concrete Block Walls at LaSalle County Station,Units 1 & 2 ML20217A7601999-10-0606 October 1999 Forwards Insp Repts 50-373/99-15 & 50-374/99-15 on 990729-0916.One Violation of NRC Requirements Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20212M0931999-10-0404 October 1999 Refers to 990922-23 Meeting Conducted by Region II at LaSalle Nuclear Power Station.Purpose of Visit,To Meet with Licensee Risk Mgt Staff to Discuss Util Initiatives in Risk Area & to Establish Dialog Between SRAs & Risk Mgt Staff 05000373/LER-1999-003, Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl1999-10-0404 October 1999 Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr ML20217A6201999-09-30030 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC Feedback on Any Planned Insps Which May Conflict with Plant Activities.Plant Issue Matrix & Insp Plan Encl ML20212E7171999-09-22022 September 1999 Forwards RAI Re Requesting Approval of License Amend to Use Different Methodology & Acceptance Criteria for Reassessment of Certain Masonry Walls Subjected to Transient HELB Pressurization Loads 05000374/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl1999-09-20020 September 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl ML20212C0591999-09-17017 September 1999 Informs That NRC Reviewed Licensee Justifications for Deviations from NEDO-31558 & Determined That Justifications acceptable.Post-accident Neutron Flux Monitoring Instrumentation Acceptable Alternative to Reg Guide 1.97 ML20212A3581999-09-13013 September 1999 Confirms That Fuel MCPR Data for LaSalle County Station,Unit 1,Cyle 9,sent by Ltr Meets Condition 2,as Stated in 970509 NRC Ltr ML20211Q9911999-09-10010 September 1999 Informs That License SOP-4048-4,for Wp Sly May Be Terminated Due to Individual Retiring ML20212A1141999-09-10010 September 1999 Forwards RAI Re Licensee 990519 Amend Request,Which Proposed to Relocate Chemistry TSs from TS to licensee-controlled Documents.Response Requested by 990930,so That Amend May Be Issued to Support Upcoming Unit 1 Refueling Outage ML20211P2211999-09-0808 September 1999 Forwards Insp Repts 50-373/99-14 & 50-374/99-14 on 990809- 13.No Violations Noted.Insp Concluded That Emergency Preparedness Program Maintained in Good State of Operational Readiness ML20212A8571999-09-0707 September 1999 Informs That Proprietary Document, Power Uprate SAR for LaSalle County Station,Units 1 & 2, Rev 2,Class III, NEDC-32701P,submitted in ,Marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) ML20211Q6861999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Plant License Applicants During Wks of 001113 & 20. Validation of Exam Will Occur at Station During Wk of 001023 05000374/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl1999-09-0303 September 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl ML20211M1151999-08-31031 August 1999 Requests That Following Eleven Individuals Take BWR Gfes of Written Operator Licensing Exam to Be Administered on 991006 ML20211G1831999-08-27027 August 1999 Provides Addl Clarification of Proposed Refueling Practices Under Proposed Core Alterations Definition Re 990813 Application for Amend to TS ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20211F8731999-08-25025 August 1999 Forwards Insp Repts 50-373/99-13 & 50-374/99-13 on 990804-06 & 09-11.No Violations Noted.Fire Protection Program Strengths Includes Low Number of Fire Protection Impairments & Excellent Control of Transient Combustibles ML20210U3201999-08-17017 August 1999 Forwards Insp Repts 50-373/99-12 & 50-374/99-12 on 990623-0728.No Violations Noted ML20210N5651999-08-0606 August 1999 Forwards Rev 8 to Nuclear Generating Stations Emergency Plan, for Plants.With Summary of Changes ML20210M9131999-08-0202 August 1999 Forwards Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for Fys 2000 & 2001 for Comed 05000373/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed1999-07-23023 July 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed ML20210E0501999-07-22022 July 1999 Submits Summary of 990630 Management Meeting Re Licensee Performance Activities Since Start Up of Unit 2.List of Attendees & Matl Used in Presentation Enclosed ML20210B7071999-07-16016 July 1999 Responds to Requesting Review & Approval of Three Proposed Changes to Ceco QA TR,CE-1A Per 10CFR50.54(a)(3) & 10CFR50.4(b)(7) ML20209H5171999-07-15015 July 1999 Discusses 990701 Telcon Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at LaSalle County Nuclear Generating Station for Weeks of 990913,1018 & 1129 ML20209G4031999-07-14014 July 1999 Forwards Insp Repts 50-373/99-11 & 50-374/99-11 on 990614-18.No Violations Noted ML20209E1211999-07-14014 July 1999 Submits mid-cycle Rev of COLR IAW LaSalle County Tech Spec 6.6.A.6.d.Rev to COLR Was Necessary Due to Implementation of TS Change Approved by Ltr Dtd 990212,which Changed Turbine Stop Valve & Turbine Control Valve Scram ML20209F6931999-07-13013 July 1999 Forwards Insp Repts 50-373/99-04 & 50-374/99-04 on 990513-0622.No Violations Noted.Determined That Multiple Challenges to Main Control Room Operators Occurred During Insp Period Due to Human Performance Weaknesses ML20210C1521999-07-0909 July 1999 Forwards Post-Outage (90 Day) Summary Rept for ISI Examinations & Repair/Replacement Activities Conducted from Beginning of First Insp Period of Second ten-yr Insp Interval Through L2R07 Refueling Outage ML20209G3901999-07-0909 July 1999 Informs NRC of Status of Commitments & Requests NRC Concurrence for Use of ASME Section III App F Acceptance Criteria to Permanently Qualify Units 1 & 2 Penetrations M-49 & M-50 ML20209E0341999-07-0909 July 1999 Provides NRC with Siemens Power Corp (SPC) Fuel & GE Fuel MCPR Data for LaSalle Unit 1 Cycle 9.LaSalle Unit 1 Is Currently Scheduled to Start Cycle 9 in 991101 ML20209E0361999-07-0808 July 1999 Forwards LaSalle County Station Unit 2 Cycle 8 Startup Test Rept Summary,Iaw TS NPF-18,Section 6.6.A.1.Startup Test Program Was Satisfactorily Completed on 990501 ML20196J9131999-07-0101 July 1999 Submits Status of Nuclear Property Insurance Currently Maintained for Braidwood,Byron,Dresden,Lasalle County,Quad Cities & Zion Nuclear Power Stations,Per 10CFR50.54(w)(3) ML20196J9061999-07-0101 July 1999 Provides Evidence That Util Maintains Guarantee of Payment of Deferred Premiums in Amount of $10 Million for Each of Thirteen Reactors,Per 10CFR140.21 ML20209B8241999-06-30030 June 1999 Forwards Five 3.5 Inch Computer Diskettes Containing Revised Annual Dose Repts for 1994 Through 1998 for Individuals Receiving Neutron Dose Not Previously Included in Reported Total Effective Dose Equivalent Values.Without Diskettes ML20196J4711999-06-30030 June 1999 Discusses Closure of GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity, Issued on 950519 to Plant,Units 1 & 2 ML20212J0311999-06-21021 June 1999 Informs of Actions Taken to Close Remaining Open Items in .Attachment Provides Detailed Justification for Closure of Open Items in Sections 5.2.2 & 5.2.8 ML20196B1951999-06-18018 June 1999 Informs NRC That Do Werts,License OP-30373-2,no Longer Requires Use of NRC License for LaSalle County Station. License May Be Terminated ML20195J7761999-06-15015 June 1999 Submits Request Relief CR-23,requesting Relief from Code Required Selection & Examinations of Noted Integral Attachments & Proposes to Utilize Alternative Selection & Examination Requirements Similar to Code Case N-509 ML20196G8021999-06-15015 June 1999 Requests Renewal of SRO License for Vv Masterson.Current License for Vv Masterson Will Expire Jul 1999.NRC Forms 398 & 396,encl.Without Encls ML20195G7101999-06-11011 June 1999 Informs That Effective 990514,GH Mccallum,License SOP-31412, No Longer Requires Use of NRC License for LaSalle Station. License Should Be Terminated ML20195D6351999-06-0404 June 1999 Notifies NRC of Actions That Has Been Taken in Accordance with 10CFR26, Fitness for Duty Programs ML20207D2821999-05-27027 May 1999 Requests That Implementation Date for Unit 1 Be Changed Prior to Startup for L1C10 to Allow Best Allocation of Resources to Implement Unit 1 Amend Prior to Startup for Either L1C9 or L1C10.Unit 2 Will Implement Mod IAW Request 1999-09-08 Category:INCOMING CORRESPONDENCE MONTHYEARML20217H4661999-10-18018 October 1999
[Table view]Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl ML20217H6251999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for MR Kahn,Aj Mclaughlin,De Montgomery & Kr Murphy Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC from 396 Encl.Proprietary Info Withheld ML20217H6341999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for Kh Curran,Lm Gerlach,Rc Weber & Bt Rhodes Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC Form 396 Encl.Proprietary Info Withheld ML20217F4301999-10-14014 October 1999 Responds to 991012 Rai,Based on 991001 Telcon Re Suppl to Request for TS Change to Revise MCPR Safety Limit & Add Approved Siemens Topical Rept for LaSalle County Station, Unit 1 ML20217C1671999-10-0808 October 1999 Provides Suppl to RAI for Approval of Unreviewed Safety Question Re Assessment of Certain safety-related Concrete Block Walls at LaSalle County Station,Units 1 & 2 05000373/LER-1999-003, Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl1999-10-0404 October 1999 Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr 05000374/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl1999-09-20020 September 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl ML20211Q9911999-09-10010 September 1999 Informs That License SOP-4048-4,for Wp Sly May Be Terminated Due to Individual Retiring 05000374/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl1999-09-0303 September 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl ML20211M1151999-08-31031 August 1999 Requests That Following Eleven Individuals Take BWR Gfes of Written Operator Licensing Exam to Be Administered on 991006 ML20211G1831999-08-27027 August 1999 Provides Addl Clarification of Proposed Refueling Practices Under Proposed Core Alterations Definition Re 990813 Application for Amend to TS ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20210N5651999-08-0606 August 1999 Forwards Rev 8 to Nuclear Generating Stations Emergency Plan, for Plants.With Summary of Changes ML20210M9131999-08-0202 August 1999 Forwards Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for Fys 2000 & 2001 for Comed 05000373/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed1999-07-23023 July 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed ML20209E1211999-07-14014 July 1999 Submits mid-cycle Rev of COLR IAW LaSalle County Tech Spec 6.6.A.6.d.Rev to COLR Was Necessary Due to Implementation of TS Change Approved by Ltr Dtd 990212,which Changed Turbine Stop Valve & Turbine Control Valve Scram ML20210C1521999-07-0909 July 1999 Forwards Post-Outage (90 Day) Summary Rept for ISI Examinations & Repair/Replacement Activities Conducted from Beginning of First Insp Period of Second ten-yr Insp Interval Through L2R07 Refueling Outage ML20209E0341999-07-0909 July 1999 Provides NRC with Siemens Power Corp (SPC) Fuel & GE Fuel MCPR Data for LaSalle Unit 1 Cycle 9.LaSalle Unit 1 Is Currently Scheduled to Start Cycle 9 in 991101 ML20209G3901999-07-0909 July 1999 Informs NRC of Status of Commitments & Requests NRC Concurrence for Use of ASME Section III App F Acceptance Criteria to Permanently Qualify Units 1 & 2 Penetrations M-49 & M-50 ML20209E0361999-07-0808 July 1999 Forwards LaSalle County Station Unit 2 Cycle 8 Startup Test Rept Summary,Iaw TS NPF-18,Section 6.6.A.1.Startup Test Program Was Satisfactorily Completed on 990501 ML20196J9131999-07-0101 July 1999 Submits Status of Nuclear Property Insurance Currently Maintained for Braidwood,Byron,Dresden,Lasalle County,Quad Cities & Zion Nuclear Power Stations,Per 10CFR50.54(w)(3) ML20196J9061999-07-0101 July 1999 Provides Evidence That Util Maintains Guarantee of Payment of Deferred Premiums in Amount of $10 Million for Each of Thirteen Reactors,Per 10CFR140.21 ML20209B8241999-06-30030 June 1999 Forwards Five 3.5 Inch Computer Diskettes Containing Revised Annual Dose Repts for 1994 Through 1998 for Individuals Receiving Neutron Dose Not Previously Included in Reported Total Effective Dose Equivalent Values.Without Diskettes ML20212J0311999-06-21021 June 1999 Informs of Actions Taken to Close Remaining Open Items in .Attachment Provides Detailed Justification for Closure of Open Items in Sections 5.2.2 & 5.2.8 ML20196B1951999-06-18018 June 1999 Informs NRC That Do Werts,License OP-30373-2,no Longer Requires Use of NRC License for LaSalle County Station. License May Be Terminated ML20196G8021999-06-15015 June 1999 Requests Renewal of SRO License for Vv Masterson.Current License for Vv Masterson Will Expire Jul 1999.NRC Forms 398 & 396,encl.Without Encls ML20195J7761999-06-15015 June 1999 Submits Request Relief CR-23,requesting Relief from Code Required Selection & Examinations of Noted Integral Attachments & Proposes to Utilize Alternative Selection & Examination Requirements Similar to Code Case N-509 ML20195G7101999-06-11011 June 1999 Informs That Effective 990514,GH Mccallum,License SOP-31412, No Longer Requires Use of NRC License for LaSalle Station. License Should Be Terminated ML20195D6351999-06-0404 June 1999 Notifies NRC of Actions That Has Been Taken in Accordance with 10CFR26, Fitness for Duty Programs ML20207D2821999-05-27027 May 1999 Requests That Implementation Date for Unit 1 Be Changed Prior to Startup for L1C10 to Allow Best Allocation of Resources to Implement Unit 1 Amend Prior to Startup for Either L1C9 or L1C10.Unit 2 Will Implement Mod IAW Request ML20195B2301999-05-19019 May 1999 Requests Approval of Proposed Changes to QA Topical Rept CE-1-A,rev 66a.Attachment a Describes Changes,Reason for Change & Basis for Concluding That Revised QAP Incorporating Proposed Changes Continues to Satisfy 10CFR50AppB ML20206R4561999-05-12012 May 1999 Provides Notification That Ws Jakielski,License SOP-30168-3, Is Being Reassigned & No Longer Requires Use of NRC License, IAW 10CFR50.74 05000373/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(ii).Attachment a Provides Commitments for Submittal1999-05-0707 May 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(ii).Attachment a Provides Commitments for Submittal ML20206K7081999-05-0707 May 1999 Forwards 10CFR50.46(a)(3) Rept Re Significant Change in Calculated Pct.Loca Analyses for Both GE Fuel & Siemens Power Corp Fuel Demonstrates Results within All of Acceptance Criteria Set Forth in 10CFR50.46 ML20206K1861999-04-30030 April 1999 Informs That in Comed Submitted Annual Exposure Rept for Personnel Receiving Greater than 0 Mrem/Yr Rather than 100 Mrem/Yr.Updated Rept Limiting Data to Personnel Receiving Greater than 100 Mrem/Yr,Attached ML20206R0751999-04-30030 April 1999 Forwards License Renewal Applications & Certification of Medical Examinations for LaSalle County Station Personnel Whose Licenses Expire in Nov.Personnel Listed.Without Encls ML20206F0931999-04-30030 April 1999 Forwards LaSalle County Nuclear Power Station,Units 1 & 2 Effluent & Waste Disposal Semi-Annual Rept for 1998. LaSalle County Station Tech Specs Recently Revised to Reduce Periodicity of 10CFR50.36a ML20206D5921999-04-28028 April 1999 Forwards Annual Environ Operating Rept for 1998 for Environ Protection Plan, for LaSalle County Station,Units 1 & 2. Rept Includes Info Required by Listed Subsections of App B to Licenses NPF-11 & NPF-18 ML20206B2471999-04-20020 April 1999 Informs That SE Kuczynski Has Been Transferred to Position No Longer Requiring SRO License.Cancel License SOP-31030-1, Effective 990412 ML20205L8161999-04-0808 April 1999 Advises NRC of Util Review & Approval of Cycle 8 Reload Under Provisions of 10CFR50.59 & Transmit COLR for Upcoming Cycle Consistent with GL 88-16.Reload Licensing Analyses Performed for Cycle 8 Utilize NRC-approved Methodologies ML20205J9451999-04-0505 April 1999 Submits Petition Per 10CFR2.206 Requesting That LaSalle County Nuclear Plant Be Immediately Shut Down & OL Suspended or Modified Until Such Time That Facility Design & Licensing Bases Are Properly Updated ML20205K5841999-03-31031 March 1999 Submits Rept on Status of Decommissioning Funding for Reactors Owned by Comm Ed.Attachment 1 Contains Amount of Decommissioning Funds Estimated to Be Required Pursuant to 10CFR50.75(b) & (C) ML20205B4241999-03-23023 March 1999 Provides Results of drive-in Drill Conducted on 990208,as Well as Augmentation Phone Drills Conducted Since 981015,as Committed to in Util ML20207J9841999-03-0505 March 1999 Informs That Effective 990212,KC Dorwick Has Resigned & No Longer Requires Use of NRC License for LaSalle County Station ML20207F9581999-03-0101 March 1999 Requests That Initial License Examination Currently Scheduled for Weeks of May 15 & 22,2000 Be Changed to Weeks of Nov 13 & 20,2000.Class Size Is Projected to Be Twelve RO & SRO Candidates ML20207C7251999-03-0101 March 1999 Forwards Annual Rept for LaSalle County Station, for Period of 980101-981231.App E to Rept Provides Info on All Personnel Receiving Exposures of More than 0 Mrem/Yr Rather than 100 Mrem/Yr Requirement of TS 6.6.A.2 ML20207D6831999-03-0101 March 1999 Forwards fitness-for-duty Program Performance Data for Each Comed Nuclear Power Station & Corporate Support Employees for Six Month Period Ending 981231,per 10CFR26.71(d) ML20207C8401999-02-25025 February 1999 Forwards Rev 60 of Comed LSCS Security Plan,Iaw 10CFR50.4(b) (4).Rev Eliminates Requirement for Annual change-out of Vital & PA Keys & Locks & re-configuration of PA Fence Around North Access Facility.Rev Withheld ML20207A9361999-02-24024 February 1999 Forwards Rev 4 to Restart Plan,To Reflect Review,Oversight & Approval Process Necessary to Restart Unit 2.Review & Affirmation Process Will Focus on Station Capability to Support Safe Dual Unit Operations 1999-09-30 Category:STATE/LOCAL GOVERNMENT TO NRC MONTHYEARML20204F1911986-07-29029 July 1986
[Table view]Requests Notification Prior to Issuance of Amends to OLs Per 10CFR50.91(b).NRC Adherence to State Notification Practice Generally Acceptable,W/Some Exceptions ML20204F2571986-07-29029 July 1986 Requests Notification Before Issuance of License Amends for State of Il Nuclear Power Plants,Per 10CFR50.91(b) ML20137P4161986-01-29029 January 1986 Advises That Review of Proposed Tech Spec Amend Involving Main Steam Line Low Pressure Instrument Response Time, Determined No Adverse Findings Exist ML20137M1511986-01-10010 January 1986 Advises That No Adverse Findings Identified Based on Review of Amends to Licenses NPF-11 & NPF-18,changing Tech Specs Re Mgt Organization ML20137A4231986-01-0707 January 1986 Advises of Review of Proposed Tech Spec Amend Re Administrative Control of High Radiation Areas.No Adverse Findings Determined ML20137A2971986-01-0606 January 1986 Notifies That Proposed Tech Spec Amend Re Addition of Excess Flow Check Valve Reviewed.No Adverse Findings Determined ML20136H2321986-01-0303 January 1986 Approves Util 851113 Request for Amends to Licenses NPF-11 & NPF-18,revising Tech Specs Re Low & Degraded Grid Voltage ML20138Q9461985-12-16016 December 1985 Notifies of Review & Approval of Proposed 851113 Tech Spec Amend Re CRD Charging Water Header Low Pressure Scram. Verbal Approval Conveyed to a Bournia of NRC by Swartz on 851212 ML20136A5621985-12-11011 December 1985 Lists New Address for Cd Jones,Director,State of Il Emergency Svcs & Disaster Agency ML20138N3401985-10-31031 October 1985 Advises That No Adverse Findings Identified,Based on Review of Util 851022 Proposed Tech Spec Amend to License NPF-11, Involving Reload Licensing Package for Cycle 2 ML20138H4971985-10-23023 October 1985 Notifies That No Adverse Findings Determined Based on Review of 851011 Proposed Tech Spec Amend Re Source Range Monitor Operability ML20138H9491985-10-22022 October 1985 Informs of Review of Application for Amend to License NPF-11 Re Proposed Changes to Tech Specs Concerning Vent & Purge Isolation Valve Mods.No Adverse Findings Determined ML20138J0501985-10-22022 October 1985 Advises That Dept of Nuclear Safety Completed Review of Proposed Amend to Tech Specs Re Eccs/Rcic Testable Check Bypass Valves.No Adverse Findings Identified ML20138A9271985-10-0909 October 1985 Advises That No Adverse Findings Identified Based on Review of Proposed Amends to Licenses NPF-11 & NPF-18,changing Tech Specs Re Diesel Generator Lube Oil Mod ML20135E1441985-09-0909 September 1985 Submits Approval of Util 850827 Proposed Tech Spec Amends to Licenses NPF-11 & NPF-18 Re CRD Sys Scram Accumulator Alarms ML20135E3561985-09-0909 September 1985 Approves Util 850828 Proposed Tech Spec Amends for Licenses NPF-11 & NPF-18 Re APRM Calibr Gain Adjustment Factors,Per ML20134M7441985-08-28028 August 1985 Advises That Review of Proposed Tech Spec Amend Re Rev to Safety Relief Valve Setpoint & Setpoint Tolerances Revealed No Adverse Findings ML20137G0751985-08-20020 August 1985 Advises That No Adverse Findings Resulted from Review of 850715 Proposed Tech Spec Amend Involving Automatic Depressurization Sys Logic Mod ML20134G1261985-08-19019 August 1985 Advises That State of Il Dept of Nuclear Safety Review of Proposed Tech Spec Amend to License NPF-11 Waiving 18-month Surveillance Interval Completed.No Adverse Findings Resulted,As Previously Noted Verbally ML20134H2461985-08-13013 August 1985 Informs of No Adverse Findings in Review of Tech Spec Change Re Waiver of 18-month Surveillance Interval ML20129D6621985-07-0808 July 1985 Informs of Completion of Review Re Proposed Tech Spec Amend to Change Main Steam Line Low Pressure Instrument Response Time.Comments Verbally Communicated to B Rybak & a Bournia on 850619 & 24,respectively ML20127F5211985-06-20020 June 1985 Advises That Proposed Tech Spec Change to Eliminate Requirement of Reactor Water Cleanup Pump Room Ambient & Differential Temp Measurements Reviewed.No Adverse Findings Determined ML20127F4991985-06-20020 June 1985 Informs of Completion of Review of Proposed Tech Specs Amend Change to Main Steam Line Low Pressure Instrument Response Time.No Adverse Findings Determined as Result of Review ML20128N0801985-05-23023 May 1985 Advises That Proposed Tech Spec Amend Re Reactor Feedwater Inboard Check Valves Type C Test Will Cause No Adverse Effect ML20128E9571985-05-21021 May 1985 Advises of No Adverse Findings,Based on Review of Proposed Tech Spec Amend Re Revised Section of 10CFR50.72 & New Section 10CFR50.73 ML20128E8541985-05-21021 May 1985 Advises That No Adverse Findings Determined,Based on Review of Util 850417 Application for Amend Licenses NPF-11 & NPF-18,revising Tech Specs ML20128D9611985-05-20020 May 1985 Advises of Completion of Review of Amend to Tech Specs Re Addition of Suppression Pool Monitoring Instrumentation to Remote Shutdown Monitoring.No Adverse Findings Identified ML20112F6651985-03-20020 March 1985 Advises That Review of Proposed Amends to Tech Specs for Licenses NPF-11 & NPF-18 Re Reporting Requirements & Channel Check Requirements Completed.No Adverse Findings Determined as Result of Review ML20101T3581985-01-28028 January 1985 Comments on Proposed Tech Spec Amend Re Clarification of Standby Gas Treatment Heater.No Adverse Findings Noted ML20114D3121985-01-23023 January 1985 Requests That JW Mccaffrey Be Added to Distribution List for Facilities ML20065Q2191982-10-15015 October 1982 Advises of State of Il Intent to File Comments on Concrete Element Design Margin Summary.Comments Will Be Incorporated Into 10CFR2.206 Show Cause Request ML20023D2091982-09-0707 September 1982 Requests List of Results of Detailed Calculations on Rebar Damage for 647 Concrete Elements Affecting Unit 1 Operation & Approved CF Braun Proposal for Independent HVAC Review. Zack Co Chronology Encl ML20063F4611982-08-24024 August 1982 Comments on NRC Decisions to Authorize Facility to Operate Above 5% Power & Up to 50% Power & Require Independent Review of HVAC Sys.Comments Will Be Discussed at 820824 Meeting W/Region 3 ML20023D0551982-08-12012 August 1982 Requests That All Interested Parties Be Furnished Proposed Contract Between Util & CF Braun for Independent Investigation of Facilities & Be Allowed to Submit Written Comments Before Agreement Finalized ML20023D0461982-08-0909 August 1982 Informs of Atty General of State of Il Intention to Attend NRC 820811 Meeting W/Util & Govt Accountability Project to Discuss Selection of Third Party to Investigate HVAC Allegations ML20062K4151982-07-27027 July 1982 Comments on Results of Investigation Into Effect of Damage to Reinforcing Steel,Ie Investigation Repts 50-373/82-35 & 50-374/82-06.Results of Addl Analysis Requested.Full HVAC Investigation Should Be Conducted Prior to Full Operation ML20027A7961982-05-26026 May 1982 Comments on Com Ed 820507 Final Rept Re Procedures for Drilled & Cored Holes.Unit 2 Should Be Inspected for Rebar Damage.When Pending NRC Investigation Complete,State Will Attend Conference W/Nrc.Internal Util Memos Encl ML20027E1331982-04-21021 April 1982 Ack Receipt of IE Bulletin 82-01, Alteration of Radiographs of Welds in Piping Subassemblies. Status of Util Response to Bulletin Requested ML20027E1101982-04-14014 April 1982 Responds to Pp Steptoe 820412 Ltr Re Affidavit of D Bridenbaugh Concerning Drilling Practices at Facilities. Affidavit Encouraged NRC to Investigate Structural Review W/O Promoting OL Issuance ML20053D7391982-03-24024 March 1982 Forwards Request to Institute Show Cause Proceeding & for Other Relief ML20049J7701982-03-18018 March 1982 Expresses Concern Re Drilling of Holes Through Rebar to Install Electrical Equipment ML19305A8751980-03-11011 March 1980 Provides Certification That Plant Discharges to Il River Will Comply W/Limitations of Federal Water Pollution Control Act,Il Environ Protection Act & Implementing Federal Regulations ML19305A8301980-03-11011 March 1980 Provides Certification That Plant Discharge to Il River Will Comply W/Limitations of Federal Water Pollution Control Act, Il Environ Protection Act & Implementing Federal Regulations ML19256A8391979-01-0808 January 1979 No Comments Were Received from State Agencies on NUREG-0486 1986-07-29 |
Text
. ..
i I@'
N. " ;
N _ . -
I STATE OF ILLINOIS DEPARTMENT OF NUCLEAR SAFETY 1035 OUTER PARK DRIVE SPRINGFIELD 62704 (217) 546-8100 TERRY R. LASH DAN L. WILLIAMS DIRECTOR U[ ,
DEPUTY DIRECTOR Mr. Harold Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555
SUBJECT:
LaSalle Units I & 2 Proposed Technical Specification Amendment involving Addition of Suppression Pool Monitoring Instrumentation to Remote Shutdowon Monitoring Specification Docket Nos. 50-373 & 50-374
REFERENCE:
J.G. Marshall Letter to H . Denton Dated April 18,1985 In Reply Please Refer To: DOE-85-071
Dear Mr. Denton:
The Illinois Department of Nuclear Safety has reviewed the Proposed Technical Specification amendment referenced above. We have determined no adverse findings as a result of that review. -
Sincere y, W &ff Michael C. Parker, Chief Division of Engineering MCP:RRM:bkw cc: T. Lash G. Wright J. Keppler, NRC Region 111 R. Lickt 3, NRC Region 111 A. Bo',rnia, NRC Washington, D.C.