TENNESSEE: VALLEY AUTHORITY CHATTANOOGA. TENNESSEE 37401 400 Chestnut Street Tower II i
April 25, 1985 BLRD-50438/83-39
'U.S.. Nuclear Regulatory Commission
- Region II-Attn
- - Dr. J. Nelson Grace, Regional Administrator
-101 Marietta Street, NN, kite 2900 Atlanta, Georgta 30323 Deer Dr. Grace:
BELLEFWTE NUCLEAR PLANf WIT 1 NATER Dams TO REACIOR BUILDING NORML' SIMP. ISG.ATIN VALVE ETOR TERTOR - BLRD-50-438/83 SUPPMENTAL FINAL REPORT-The subject deficiency was initially reported to NRC-0IE Inspector P. E. Fredrickson on Jme 9,1983 in accordance with 10 TR 50.55(e) as
~
Nm 2381. This was followed by our interim reports dated July 8 and-i 0ctober 20, 1983 and our_ final mport dated August 1,1984. Below is our supplemental final' report.
h.
As discussed with NRC-0IE Inspector A. Ignatonis on April 18, 1985, the date of April 19,1985 for completion of corrective actions indicated in our final report was not met. While the motor operator has been mpaired and returned to
~ the sLte, TVA has decided to keep the operator in storage and not install it until completion of the liquid radwaste disposal system. The corrective action on this matter 'util be completed by June 30, 1986.
r If you have any questions, p1 ease get in touch wLth R.
H.'
Shell at FTS 858-2688.
Very truly yours, TENNESSEE VALLEY AUIHORITY-g..L' W. Hufhan, Manager Licensing and Regulations oc:
Mr. James Taylor,' Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Canaission Was hington, ' D.C. 20555
~ Records Center
-Institute of Nuclear Power Operations 1100 Circle 75 Parkway,- mite 1500-
. At1anta,' Georgia 30339 8505240638 850425 ADOCK O 8-g 5
27 f
^
I An Equal Opportunity Emoh.,