Discusses Implementation of BWR Torus Temp TS Changes Re Listed Plants
ML20127H259
Person / Time
Site: Millstone, Hatch, Monticello, Dresden, Peach Bottom, Browns Ferry, Nine Mile Point, Oyster Creek, Cooper, Pilgrim, Brunswick, Vermont Yankee, Duane Arnold, Quad Cities, FitzPatrick
Issue date: 07/01/1975
From: Goller K
Office of Nuclear Reactor Regulation
To: Gallo J
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
Shared Package
ML20127H228 List:
References
NUDOCS 9211180463
Download: ML20127H259 (2)


Text

. _ - - -- . - . . . _ _ _ _ - . - - - ~ _ . ._.. ...- . . . - . -.

9~ .

a_ -.

4

  • UNITED STATES NUCLEAR REGULATORY COMMISSION =

j WASHINoToN. D. c. 20565-Jut a t 1P5 J. Gallo, Chief Ilearing Counsel, OELD BWR TORUS WATER TEMPERATURE LIMITS AND UNILATERAL TECHNICAL SPECIFICATION CHANGES We have implemented the "BWR Torus Temperature" Technical Specification changes for the " responsive" and " unresponsive" licensees in accordance with the guidelines provided following approval of the lead cases of Nine Mile Point (unresponsive licensee) and- Brunswick-2 (responsive licensee). T++c c2::: yet rc;.ain tc be ecmpleted; ':cnticclic s nd Ceeper; heu en r , Aw will Lc finnhed scer.

This action had been concurred in by TR, OR, E. Case and you. As you may recall, our June 10 meeting in E. Case's office (attended by J.

Carter, G. Lear, you and I) was the occasion-for your concurrence with the Icad cases, and simultaneously, concurrence with the new approach for " unilateral Tech Spec change" procedures Jerry Carter was given the task of reducing the latter procedures to a formal policy / procedural statement..

We now understand that you wish to see the individual letters being sent to BWR licensees for amendment of Technical Specifications as was done via Ictters dated June 13,.1975 for the two lead cases, NMP-1 and -

~' Brunswick-2. Therefore, the letters and their enclosures are forwarded herewith for your concurrence and return to OR for dispatch. Also enclosed, for your information, is a list of the responsive / unresponsive licensees to whom this licensing action applies.

JR Gd4 Karl R. Goller, Assistant Director for Operating Reactors Division of Reactor Licensing

Enclosures:

1. List of Responsive / Unresponsive

-Licensees

2. Letters to Licensees cc: ' Attached to each action package -

,dU 4, y _m u,j n i

9211180463 700715 PDR ADOCK 05000263

.P PDR

_ _ _ . ~ ~ _ . . . . . .

ENCLOSURE j,gg, a 1 Eg

  • Licensing Action Technical Specifications Chance BWR Torus Water Temperature Limits PLANT DOCEET RESPONSIVE LICENSEES Dresden 2/3 50-237/249 Coramonwe tith Edison Co.

Quad Cities 1/2 50-254/265 Commonwealth Edison Co. 50-260/296 Tennessee Valley Authori.ty** Browns Ferry 1/2 Monticello 50-263 Northern States Power Co. 50-271 Vermont Yankee Nuclear Power Corp. Vermont Yankee Philadelphia Electric Company Peach Botton 2/3 50-277/27S Boston Edison Company Pilgrin 50-293 Duane Arnold 50-331 lowa Electric Licht 6 Power Co. 50-521 Georgia Power Ccapany Edwin 1. llatch 1 Carolina Power G Li;;ht Co.* Brunswich-2 50-325 P l. ANT DOCEET UNRESPON31VE I ICC: SEES Jersey Central Power 6 1.icht Oyst er Creek 50-219 Niagara Mohawk Power Corp.* Nine "ile l'oint-1 50-220' Millstone Unit 1 50-245 Northeast Nuclear Fncrev Co. 50-295 Nebraska l'ublic Po.eer l'is tri c t Cooper Power Authority State ot' N.Y. Fit. Patrick 50-333 Lead cases - letters sent 6/13/75

    • This change will be implemented in Tech Specs for Browns Ferry 1/2 when they return to operation later this year. .