Notice of Violation from Insp on 850325-28
ML20127G811
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/18/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20127G809 List:
References
50-302-85-16, NUDOCS 8505210152
Download: ML20127G811 (1)


Text

._ _ . . ._.

+

  • jo 4

ENCLOSURE 1 NOTICE OF VIOLATION Florida Power Corporation Docket No. 50-302 Crystal River 3 License No. DPR-72 y

~

The following violation was identified during .an inspection conducted 'on March 25-28, 1985. ~ The Severity Level was assigned in accordance with the NRC

. Enforcement Policy (10 CFR Part 2, Appendix-C).

10 CFR 50, Appendix B, Criterion V, and FSAR Section .1.7.1.5 require that

. activities affecting quality shall be prescribed by documented instructions, procedures or drawings...- and shall be accomplished in accordance with these

p. instructions, procedures or drawings. .The pipe support drawing and modifi-cation drawing provide installation dimensions for piece "H" of pipe support y- =MUH 556. The " Piping Hanger - Final Inspection" requirements provided on

' inspection plan . number. WR-60571 for pipe support . MUH 556 required - QC . .

E verification that "the overall configuration and sizing .of the completed hanger assembly or modification conform. to the applicable approved '

engineering; drawing."

M Contrary to the above, completed, installed, modified, inspected and QC 3 accepted pipe support MUH 556 piece "H" installation dimensions did not e " conform" with the applicable approved _ engineering drawings. . In addition, O unauthorized. loads (scaffolding) were being partially supported by the pipe 1 support. No procedure or -instructions were available authorizing or f prohibiting installation of scaffolding / staging on permanent -plant

. equipment. .

This is a Severity Level IV violation (Supplement II).

. Pursuant to 10 CFR 2.201, you are required to submit to this office within 30

' days of the date of this Notice, .a written statement or explanation in reply, 1

including: (1) admission or denial of the alleged violation; (2) the reasons for the violation if admitted; (3) the corrective steps which have been taken and the results . achieved; (4). corrective steps which will be taken' to avoid

further violations; and (5) the date when full compliance will be achieved.

, Security or' safeguards information should be submitted as 'an enclosure - to facilitate withholding it from public disclosure as required by 10 CFR 2.790(d)

'or 10 CFR 73.21.

p-n Q

Date: APR 181985

,g a c  ;

-9505210152 850418 PDR ADOCK 05000302

4 ,

7

s. , , . . . _ , - ,;,..- .-,,,.,_._.,.,,,.,-,_,,-+-,,.,_.--n.-_.- . , _ . - . , . , , , - , _ , . , - _ . .