Interim Deficiency Rept 85-03 Re Instrumentation Installation Reverification Program.All Remaining Production Work W/Exception of Hanger Installation & Final QC Slope Verification Expected to Be Completed by 850831
ML20127G716
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 05/07/1985
From: Miosi A
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
0088K, 85-03, 85-3, 88K, NUDOCS 8505210125
Download: ML20127G716 (1)


Text

e -

Commonwealth Edison One First National Plaz', Chicago Illinois Address Reply to: Post Office Box 767 Chicago, Illinois 60690 May 7, 1985 Mr. James G. Keppler Regional Administrator U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Braidwood Station Units 1 and 2 10 CFR 50.55(e) No. 85-03 Interim Report Instrumentation Installation Reverification Program NRC Docket Nos. 50-456/457 Reference (a): D. H. Smith letter to J. G. Keppler dated February 27, 1985

Dear Mr. Keppler:

Reference (a) provided information concerning a deficiency reportable pursuant to 10 CFR 50.55(e) regarding deficiencies identified during the conduct of the Instrumentation Installation Reverification Program at our Braidwood Station. The purpose of this letter is to provide an updated status of the corrective actions taken to resolve this issue. This letter is considered to be an Interim Report.

Status of Corrective Action It was previously reported that Commonwealth Edison had anticipated completion of the Installation Reverification Program by March 31, 1985 with a final report to be submitted by May 1, 1985.

This reverification process has generated an unanticipated increased work load which has resulted in extending our expected completion date. Currently, out of a total of 513 isometric drawings,185 have been completed through Phase II of the IRV Program. All remaining production work with the exception of hanger installation and final QC slope verification, is expected to be complete by August 31, 1985. Final Hanger installation and QC verification is expected to be complete by December 31, 1985. A final report will be provided at that time.

Very truly yours, 8505210125 850507 n u/ '

  • PDR ADOCK 05000456 , Oy Z/ #W LC2' S PDR r Anthony D. Miosi Nuclear Licensing Administrator h pgl}

cc: NRC Resident Inspector - Braidwood Director of Inspection and Enforcement 1 U. S. Nuclear Regulatory Commission MAY 8 1985 (3 Washington, D.C. 20555 0088K