y(ll w
%
'-;
.; .
a
,
,_
April 4, 1985
Florida Power and ' Light Company
ATTN: Mr. J. W. Williams, Jr.
Group Vice President
Nuclear Energy Department-
P. O. Box 14000-
Juno Beach, FL 33408
Gentlemen:
-SUBJECT: REPORT.NOS. 50-250/84-41 AND 50-251/84-42
Thank you for your response of March 18, 1985, to our Notice of Violation issued
on February 15, 1985, concerning activities conducted at your Turkey Point
We have evaluated
your response and found that it meets the requirements of 10 CFR 2.201. We will
examine the implementation of your corrective actions during future inspections.
We appreciate your cooperation in this matter.
Sincerely,
Original Signed by
Roger D. Walker
Roger D. Walker, Director
Division of Reactor Projects
-
.cc:
C. M. Wethy, Vice President
Turkey Point Nuclear Plant
C. J. Baker, Plant Manager
--
Turkey Point Nuclear Plant
K. N. Jones, Plant QA
Superintendent
[
bec: NRC Resident Inspector
Document Control Desk
>
State of Florida
'
8505200611 850404
gDR
ADOCK 05000250
I
RII
RII
RII
RII
- See previous concurrence
b
CSmith:cdg
.CUpright
AGibson
VBrownlee
03/ /85
03/ /85
03/ /85
99/3/85
H
I ffo/
_
C
'
..[
...
.
.
Florida Power and Light Company
ATTN: Mr. J. W. Williams, Jr.
Group Vice President
Nuclear Energy Department
P. O. Box 14000
Juno Beach, FL 33408
Gentlemen:
SUBJECT: REPORT NOS. 50-250/84-41 AND 50-251/84-42
Thank you for your response of March 18, 1985, to our Notice of Violation issued
on February 15, 1985, concerning activities conducted at your Turkey Point
facility under NRC Operating License Nos. DPR-31 and DPR-41.
We have evaluated
your response and found that it meets the requirements of 10 CFR 2.201. We will
examine-the implementation of your corrective actions during future inspections.
We appreciate your cooperation in this matter.
Sincerely,
Roger D. Walker, Director
Division of Reactor Projects
cc:
K. N. Harris, Vice President
Turkey Point Nuclear Plant
C. J. Baker, Plant Manager
Turkey Point Nuclear Plant
K. N. Jones, Plant QA
Superintendent
bec: NRC Resident Inspector
Document Control Desk
State of Florida
.
'
RII
RII
RII
RII
5d
- CSmith:cdg
4 Upright
AGi
n
VBrownlee
- See previous concurrence
03/ /85
03/ /85
% /85
03/ /85
.
L
- '
',
.
.
.
Florida Power and Light Company
ATTN: Mr. J. W. Williams, Jr.
Group Vice President
Nuclear Energy Department
P. O. Box 14000
Juno Beach, FL 33408
Gentlemen:
SUBJECT: REPORT NOS. 50-250/84-41 AND 50-251/84-42
Thank you for your response of March 18, 1985, to our Notice of Violation issued
. on February ~ 15, 1985, concerning activities conducted at your Turkey Point
-facility under NRC Operating License Nos. DPR-31 and DPR-41.
We have evaluated
your response and found that it meets the requirements of 10 CFR 2.201. We will
examine the implementation of your corrective actions during future inspections.
We appreciate your cooperation in this matter.
Sincerely,
Roger D. Walker, Director
Division of Reactor Projects
cc w/ encl:
K. N. Harris, Vice President
Turkey Point Nuclear Plant
C. J. Baker, Plant Manager
Turkey Point Nuclear Plant
K. N. Jones, Plant QA Superintendent