Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-250/84-41 & 50-251/84-42
ML20127F857
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 04/04/1985
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Williams J
FLORIDA POWER & LIGHT CO.
Shared Package
ML20127F861 List:
References
NUDOCS 8505200611
Download: ML20127F857 (3)


See also: IR 05000250/1984041

Text

y(ll w

%

'-;

.; .

a

,

,_

April 4, 1985

Florida Power and ' Light Company

ATTN: Mr. J. W. Williams, Jr.

Group Vice President

Nuclear Energy Department-

P. O. Box 14000-

Juno Beach, FL 33408

Gentlemen:

-SUBJECT: REPORT.NOS. 50-250/84-41 AND 50-251/84-42

Thank you for your response of March 18, 1985, to our Notice of Violation issued

on February 15, 1985, concerning activities conducted at your Turkey Point

facility under NRC Operating License Nos. DPR-31 and DPR-41.

We have evaluated

your response and found that it meets the requirements of 10 CFR 2.201. We will

examine the implementation of your corrective actions during future inspections.

We appreciate your cooperation in this matter.

Sincerely,

Original Signed by

Roger D. Walker

Roger D. Walker, Director

Division of Reactor Projects

-

.cc:

C. M. Wethy, Vice President

Turkey Point Nuclear Plant

C. J. Baker, Plant Manager

--

Turkey Point Nuclear Plant

K. N. Jones, Plant QA

Superintendent

[

bec: NRC Resident Inspector

Document Control Desk

>

State of Florida

'

8505200611 850404

gDR

ADOCK 05000250

PDR

I

RII

RII

RII

RII

  • See previous concurrence

b

CSmith:cdg

.CUpright

AGibson

VBrownlee

03/ /85

03/ /85

03/ /85

99/3/85

H

I ffo/

_

C

'

..[

...

.

.

Florida Power and Light Company

ATTN: Mr. J. W. Williams, Jr.

Group Vice President

Nuclear Energy Department

P. O. Box 14000

Juno Beach, FL 33408

Gentlemen:

SUBJECT: REPORT NOS. 50-250/84-41 AND 50-251/84-42

Thank you for your response of March 18, 1985, to our Notice of Violation issued

on February 15, 1985, concerning activities conducted at your Turkey Point

facility under NRC Operating License Nos. DPR-31 and DPR-41.

We have evaluated

your response and found that it meets the requirements of 10 CFR 2.201. We will

examine-the implementation of your corrective actions during future inspections.

We appreciate your cooperation in this matter.

Sincerely,

Roger D. Walker, Director

Division of Reactor Projects

cc:

K. N. Harris, Vice President

Turkey Point Nuclear Plant

C. J. Baker, Plant Manager

Turkey Point Nuclear Plant

K. N. Jones, Plant QA

Superintendent

bec: NRC Resident Inspector

Document Control Desk

State of Florida

.

'

RII

RII

RII

RII

5d

  • CSmith:cdg

4 Upright

AGi

n

VBrownlee

  • See previous concurrence

03/ /85

03/ /85

% /85

03/ /85

.

L

  • '

',

.

.

.

Florida Power and Light Company

ATTN: Mr. J. W. Williams, Jr.

Group Vice President

Nuclear Energy Department

P. O. Box 14000

Juno Beach, FL 33408

Gentlemen:

SUBJECT: REPORT NOS. 50-250/84-41 AND 50-251/84-42

Thank you for your response of March 18, 1985, to our Notice of Violation issued

. on February ~ 15, 1985, concerning activities conducted at your Turkey Point

-facility under NRC Operating License Nos. DPR-31 and DPR-41.

We have evaluated

your response and found that it meets the requirements of 10 CFR 2.201. We will

examine the implementation of your corrective actions during future inspections.

We appreciate your cooperation in this matter.

Sincerely,

Roger D. Walker, Director

Division of Reactor Projects

cc w/ encl:

K. N. Harris, Vice President

Turkey Point Nuclear Plant

C. J. Baker, Plant Manager

Turkey Point Nuclear Plant

K. N. Jones, Plant QA Superintendent