Forwards SE Which Confirms Granting of Request for Relief from ASME Code Repair Requirements Nuclear Closed Cycle Cooling Sys
ML20126F776
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 12/22/1992
From: Berkow H
Office of Nuclear Reactor Regulation
To: Beard P
FLORIDA POWER CORP.
Shared Package
ML20126F778 List:
References
TAC-M84895, NUDOCS 9212310134
Download: ML20126F776 (2)


Text

_ _ - _ _ _ _ _ _ _ _

. t .

Ducember 22, 1992 Docket No. 50-302 Mr. Percy H. Beard, Jr.

Senior Vice President.

Nuclear Operations florida Power Corporation ATTN: Manager, Nuclear Operations Licensing P.O. Box 219 NA-21 Crystal River, Florida 34423-0219

Dear Mr. Beard:

SUBJECT:

REllEF FROM REPAIR REQUIREMENTS Of ASME CODE CLASS 111 PIPING (TAC NO. 84895)

On November 6,1992, your representatives verbally requested relief of a tc<mporary enn-Code repair c1 a 6-inch segment of your Nucicar Closed Cycle Cooling (S'.1) sySt'm, until the planned spring 1993 maintenance outage. Such relief was granted verbally that day.

By letter also dated November 6, 1992, you documented your request. This .

letter and the attached Safety Eva". ation confirm granting of the requested relief.

Your subsequent relief request of November 13, 1992, covering temporary non-Code repairs of an 18-inch section of the same line will be addressed separately as part of the above TAC number.

Sincerely, (Original Signed By)

Herbert N. Berkow, Project Director Project Directorate 11-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Lnclosure As Stated cc w/ enclosure:

See next page 0FFICIAL RECORD COPY - FILE NAME:\CR84895.LTR Distribution *See Previous Concurrence Docket file NRC & Local PDRs PDil-2 RF S. Varga G. Lainas H. Berkow E. Tana ACRS (10)

OPA M. Sinkule Ril H. Silver T.Murley/f.Hiraglia J. Partlow- B. Grimes OGC J. Lieberman E. Jordan G. Hill (4). OC/LTDCB L. Plisco, EDO OUltE LAtPDil-2* P)tfhDh3N* D: PDM [h3 EMCB* OGC*

mt ETana HSil'vN/ Hiierbok JStrosnider MYoung NE 12/17/92 12/17/92 12/7/92 12/20/92 12/21/92 )

280022 . ,

9212310134 921222  :

g DR ADOCK 0500 2 -

Mr. Percy M. Beard Crystal River Unit No.3 florida Power Corporation Generating Plant CC:

Mr. A. H. Stephens Mr. Robert G. Nave, Director l General Counsel Emergency Management i Florida Power Cornoration Department of Community Affairs 1 MAC-A50 2740 Centerview Orive P. O. Box 14042 Tallahassee, Florida 32399-2100 St. Petersburg, florida 33733  ;

Mr. Bruce J. Hickle, Director Chairman Nuclear Plant Operations Board of County Commissioners florida Power Corporation Citrus County P. O. Box 219-NA-2C 110 North Apopka Avenue Crystal River, florida 34423-0219 Inverness, Florida 32650 1 Mr. Robert B. Borsum Mr. Rolf C. Widell, Director B&W Nuclear Technologies Nuclear Operations Site Support 1700 Rockville Pike, Suite 525 florida Power Corporation Rockville, Maryland 20852 P. O. Box 219-NA-21 Crystal River, Florida 34423-0219 Regional Administrator, Region !!

U. S. Nuclear Regulatory Commission Senior Resident Inspector 101 Marietta Street N.W., Suite 2900 Crystal River Unit 3 Atlanta, Georgia 30323 U.S. Nuclear Regulatory Commission Mr. Jacob Daniel Nash 6745 N. Tallahassee Road Office of Radiation Control Crystal River, Florida 34428 Department of Health and Rehabilitative Services Mr. Gary Boldt 1317 Winewood Blvd. Vice President - Nuclear Tallahassee, Florida 32399-0700 Production florida Power Corporation Administrator P.O. Box 219-SA-2C Department of Environmental Regulation Crystal River, Florida 34423-0219 Power Plant Siting Section State of florida 2600 Blair Stone Road Tallahaseee, Florida 32301 Attorney General Department of L.egal Affairs The Capitol Tallahassee, Florida 32304

-