ML20126E855

From kanterella
Jump to navigation Jump to search
Insp Rept 50-285/92-34 on 921207-11.No Violations Noted. Major Areas Inspected:Administrative Controls,Response to Plant Mods & Response to Industry & Plant Events
ML20126E855
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 12/23/1992
From: Stetka T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20126E849 List:
References
50-285-92-34, NUDOCS 9212300014
Download: ML20126E855 (11)


See also: IR 05000285/1992034

Text

..

-

_

.

-

'

'

APPENDIX

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-285/92-34

Operating License: DPR 40

Licensee: Omaha Public Power District (OPPD)

444 South 16th Street Mall

Mail Stop 8E/EP4

Omaha, Nebraska 68102-2247

.

Facility Name:

Fort Calhoun Station (FCS)

Inspection At:

FCS site, Fort Calhoun, Nebraska

Inspection Conducted: December 7-11, 1992

Inspector:

J. E. Whittemore, Reactor Inspector, Plant Support Section

Division of Reactor Safety

)

F

'

'/2-23-72-

'

Approved

.T.

FV Stetka, Chief, Maintenance Section

D' ate

Division of Reactor Safety

Insoection Summary

Areas Insoected: Routi..,

inounced inspection of the facility licensed

operator training (requalification) program including administrative controls,

response to plant modifications, response to industry and plant events,

response to changing administrative or license requirements, and training

staff performance. The inspection also reviewed the program performance in

identifying and responding to poor operator performance.

Results:

The licensee's program for assuring the continued competence of licensed

o

operators was performing well. (paragraph 1.6)

The instructional staff was capable and experienced, with the majority

o

holding a senior reactor operator license for FCS. (paragraph 1.1)

A cooperative relationship existed between the operations and training

o

organizations, which resulted in a beneficial teamwork approach to

resolving training issues. (paragraph 1.4)

9212300014 921224

PDR. ADOCK 05000285

G.

PDR

_ -

.._. _

-

._

. .

__

~ ~ . _ , _

. . .

__

..- .

.-

\\

n

l

-

-2-

So-ary of Insoection Findiggi:

The licensee intended to temporarily reduce the instructor staff for the

o

initial and licensed operator training programs by a tcral of two

personnel. The licensee indicated their intent to monitor this matter

to assure that there was no impact on program effectiveness.

(paragraph 1.1).

A potential to comproelse examinations was identified, in that the

o

Itcense's procedures for developing written examinations allowed

excessive use of identical questions on back-to-back examinations.

However, there was no indication that examination compromise had

occurred and the licensen-initiated action to revise the procedure.

(paragraph 1.3).

Attachments:

Attachment - Persons Contacted and Exit Meeting

o

l-

l

l

'

-

_ _

.

t

.

3

DETAILS

1 LICENSED OPERATOR TRAINING (41701)

This inspection involved a review of the performance of the FCS licensed

operator (requalification) training program which is required by the

regulations in 10 CFR Part 55. The review was conducted to determine if

various processes within the program would respond correctly to industry and

plant events, facility modifications, procedure revisions, and any changes to

administrative and license requirements. The program processes reviewed

included classroom training, trainee evaluation, examination failure

remediation, and the integration of the training staff effort toward program

implementation.

The ins)ection was conducted during the seventh and final

rotation for the 1992 scleduled licensed operator training.

The inspector reviewed the two documents that controlled the licensed operator

training

)rogram. The Licensed Operator Training Program Master Plan (TPHP)

defined tie program and provided a program overview, organizational

responsibilities, department interfacing instructions, qualification

requirements, and the training program task list. The training program was

conducted according to Training Administrative Procedure (TAP)-13. " Licensed

Operator Requalification Training," Revision 21, which contained the detailed

program implementing instructions.

The inspector concluded that the controlling procedures assured compliance

with the licensee's administrative requirements, facility license

requirements, and the regulations in 10 CFR Part 55.

1.1 Trainina Oro.aization And Responsibilities

Within the training organization, the responsibility for the licensed operator

and initial license training programs fell under the supervisor of operations

training. A total of 11 personnel were assigned to the supervisor for

administering the two programs. Two of the assigned personnel were

contractors whose contract was scheduled to end on December 31, 1992. At this

time, it appeared that the licensee did not intend to renew the contract. Of

the remaining nine personnel, eight were currently, or had been, senior

reactor operator licensed on the FCS facility. The remaining individual had

been licensed on another Combustion Engineering plant. The training personnel

were specifically assigned to one of the programs, but assigned duties would

overlap into the other program. Most often, this overlap would occur-in the

simulator training and evaluation area.

At the time of the inspection, the licensee was preparing to start the 1993

licensed operator program.

Additional effort was being expended to complete

the final training phase for an initial licensing class of nine, scheduled for

NRC licensing exams in June 1993. Recognized training technology standards

recommend that experienced instructors be allowed twice the time for

.

.

-

4

preparation as required for presentation of classroom material.

Outside the

classroom, additional time is needed to validate and review materials for

dynamic training and evaluation sessions such as simulator guides and job

performance weasures (JPM).

It was also conceivable that instructors could be

tasked to develop additional training materials. Additionally, it normally

required two instructors to operate the FCS control room simulator. The

inspector conducted discussions with licensee representatives concerning the

instructional- staff and scheduled workload. The inspector asked if the nine

remaining instructors would have adequate preparation time to prepare for

their assigned instructional tasks with the planned reduction of qualified

instructors. The licensee could not provide a definite affirmative answer to

the question. Management indicated they were aware that instructional

personnel availability would be reduced temporarily, but in their opinion, no

significant problems would result from decreased staffing.

In order to avoid

any long-term problems, the licensee planned to limit the number of licenses

held at the facility.

In addition, there were plans to avoid conducting an

initial license class for about 2 years.

Further, when new operators were

licensed in mid 1993, as many as three licensed personnel would be r.ssigned to

the licensed operator training staff.

The inspector concluded that the initial and licensed operator training

programs would be at absolute minimum staffing until the latter part of 1993.

Licensee management stated ar intent to closely monitor program performance

during this period.

1.2 Classroom Trainino

It was not possible to observe operational training during the inspection

because the control room simulator was undergoing a modification outage.

All

scheduled classroom and operational training and evaluation for the 1992

program had been completed. However, the inspector observed three sessions of

,

classroom training provided to licensed operators that had been requested by

'

licensed personnel or the operations supervisor. The subjects of the three

sessions were fire protection, operability determination, and NRC notification

requirements.

The inspector observed two instructors during the administration of the three

classroom lessons. The instructors observed were experienced licensed senior

reactor operators and were well prepared for the training sessions. Both of

,

the instructors had different but effective techniques for motivating the

students and provided good presentations. Additionally, both of the

'

instructors exhibited a superior questioning technique to initiate discussion

of the subject matter.

Interaction was encouraged and several points were

addressed and cleared up by the dialogue between the instructor and students.

During two of the sessions, the students surfaced single issues that were not

finalized or closed out during the classroom session.

The student questions

concerned interpretation of conditions and management policy.

The instructors

did not refer to the issues during the lesson summaries or commit to

addressing the students' concerns later or through uther methods.

The-

-

- -

.

4

r

5

inspector debriefed with the instructors and the supervisor and determined

there was an unwritten policy to address and answer all student questions

which arose in the classroom. There were no formal requirements or methods

specified for obtaining assistance on issues needing expertise from outside of

training. A licensee representative stated the instructor evaluation program

had identified the practice of failing to address issues not answered in the

classroom as a generic problem in classroom training, and would be addressed

in the future.

The inspector concluded that a potential existed for instructors to ignore

student concerns brought up in the classroom. Aside from this single

observat'on, the classroom training phase of the licensed operator training

program was effective.

1.3 Licensed Operator Evaluation And Corrective Action

The inspector reviewed the annual examination results from 1990 to the

present, and the remediation process for each failure.

Individual licensed

operator and crew perfomance on annual examinations indicated improvement

since 1990.

During the 1990 requalification year, 37 licensed individuals

were examined. One crew and two individuals failed the simulator examination.

There was one written examination failure. During the 1991 cycle 44

individuals, including 12 co-examined by the NRC, were tested. The NRC did

not fail any individuals or crews. OPPD failed one crew on the simulator,

four individuals on the simulator, one on JPN walkthrough, and one on the

written examination.

For the 1992 requalification year, 42 individuals were

examined. A total of 12 licensed individuals were declared exempt from the

annual examination because of holding a license for less than 3 months or

being enrolled in a Senior Reactor Operator upgrade training program. There

were no failures of the 1992 examinations.

According to OPPD procedures and policy, the failure of.any phase of the

annual requalification examination required the affected individual to be

removed from shift duties.

A review of the remediation effort for each

failure over the past 3 years indicated that an in-depth analysis was

conducted to determine the reason for each exaaination failure. The analyses

identified the specific weaknesses that had contributed to the failures, or

,

l

identified problems with the examination. Once an operator's specific

weaknesses had been identified, a specific upgrade program was designed to

'

improve the individuals performance in the weak area (s).

Some of these

l'

upgrade programs were simple and easy to complete while others were complex

and lengthy. The upgrade programs had been approved by managea nt in the

,

operations and training departments.

Prior to being returned to shift duties,

the individuals were re-examined to determine if they had regained proficiency

,

in the previously identified weak areas. Crew failures on the simulator had

l

been handled in the same manner as individual failures. However, individuals

who had performed well and had not contributed to the failure, had been

,

l

exempted from the remediation process.

I

- _ - .

+

-

,

.

__

.

,

'

-6-

The remediation process was effectively implemented.

The crew or individuals

weaknesses were properly identified and the prescribed corrective action had

been beneficial and timely. A review of the makeup examinations indicated

that the affected operators had been tested on the individual simulator

critical tasks (ISCT) and in the knowledge areas where they demonstrated

weaknesses.

Written examinations were constructed from a computer-based examination bank

according to Procedure TAP-8, " Examination Control And Administration,"

Revision 16. Most of the test items in the database were in the preferred

objective (multiple choice) format.

The majority of the questions were

comprehensive or required conceptual knowledge, synthesis, and analysis by the

examinee to obtain the correct answer. One person on the training staff was

responsible for developing the six iterations of the annual exam that were

administered over the 6-week crew rotation. All versions of the examination

" quired peer review and management approval.

Examinations for the annual requalification examinations were developed by

using a sampling plan. The plan was generated from a computer database that

contained tie exact amount of training time that had been expended for each

subject. This time was then reflected as a percentage of the total training

time.

From this data, a plan could be generated to indicate the percentage of

questions to be used in the broad areas of systems, procedures, and

administration. The finished plan also showed the percentage of questions

needed to address smaller areas such as emergency procedures or abnormal

procedures.

The inspector reviewed the sampling plans that had been developed to support

the 1991 and 1992 cycle examinations. A review of the examinations to support

these cycles was also performed. The inspector determined that the quality of

l

the test items used on the annual examinations was good.

Questions that

required memorized response from the examinee occurred infrequently. A rough

estimate comparing two examinations to the sample plan indicated favorable

comparisons to the sample plan. The examinations did not exactly agree with

the plan percentages, but the proportions.were close enough to confirm that

the sample plan h7d been used as intended.

Procedure TAP-8 dealt with using identical questions on back-to-back written

sxaminatibns. According to the procedure, only 30 percent of an examination

had to be different from the previous version. This translated to allowing 70

percent of the questions used on the first weekly examination to be repeated

on the second week of the examination. The inspector told the licensee that

the amount of identical- question overlap appeared to be excessive and could

result in examination compromise. A licensee representative agreed with the

i

inspector's conclusion and expressed an intent to immediately commence a

procedure revision that would not allow an examination to be compromised.

The

licensee representative also stated that very little, if any, question overlap

4

had been used in the past.

l

. _ ,

-

_

--

-_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ .

.

0

'

_7

The inspector reviewed different versions of the last annual examination to

see if any questions had been used more than once. Also, an interview was

conducted with the individual who constructed the most recent set of six

weekly examinations. This review and interview revealed that no test items

had been used more than once on any of the six examinations.

The inspector concluded that the licensee's program for evaluating operators

was strong. The prescribed followup corrective action to address identified

. hile the potential

weaknesses was imaginative, timely, and beneficial.

W

existed for examination compromise within the licensee's procedures, no

instance was identified where this had occurred and procedure revision was

initiated prior to the end of the inspection.

1.4 Trainina Prooram Response

The inspector reviewed the process for changing the training program content

in response to changes and modifications to the plant, procedures,

administrative requirements, license enditions, and regulations. Changes to

training programs content was conducted according to Procedure TAP-7,

" Revision Of Training Program,' Revision 21. Change was initiated within the

training program configuration management (TPCM) system. This system was

administered by a coordinator and committee members that represented each

training program. The committee was notified of all changes and met weekly to

decide what programs would be affected by a specific change. Once the

affected programs were identified, program supervisors determined the required

program content change, subject to management approval.

A problem had occurred recently when the training organization had not been

'

notified that planned modifications to the facility had been completed. This

resulted in failure to implement training program content changes until after

the facility had recovered from an outage and was back on line. This issue

was resolved by changing the distribution methodology for design packages.

[

The current practice was to provide training with the initial modification

package, significant revisions, and the final completed package, which

provided a signal to implement the training changes.

Also the supervisor of

licensed operator training had developed and implemented a special plant

modification status tracking system to prevent recurrence of the problem. The

TPCM system appeared to be effective in providing the necessary changes to

.

program content.

There was a variety of methods for dispensing information about a change to

the licensed operators. Generally, existing training material such as lesson

plans or simulator guides would be revised.

Sometimes completely new material

would be developed.

For matters of relatively low importance, a licensed

operator required reading file was administered from the training department.

In the past, immediate training had been administered by the training

organization to licensed crews, prior to the assumption of shift duties. This

had become necessary when plant modifications had not been completed until

just before a crew assumed the shift.

The most frequently used approach was

to develop and administer a special topics classroom session for each

i

I

_ _ _ __ -

_ _ _ _ _ _

_ _

_ _ _ - _ _ _

_

._

_

.

,

-8-

rotation. There were typically seven rotations during a requalification

program year.

For each rotation a handbook was developed for the operators to

follow the classroom presentation. One instructor within the licensed

o)erator training program was responsible for developing and administering

t11s training. The session content was jointly agreed to by operations

management.

The inspector reviewed training material that had been developed for three

recent special topics sessions. The material for a session consisted of a

handbook and a generic lesson plan. The generic lesson plan contained

learning objectives specific to the lesson material and-the instructor had

highlighted the handbook to use as a presentation guide.

From discussions

with instructors, supervisors, and operators, the inspector detemined that

this method of instructing operators about plant and program revisions and

modifications had been very effective. However, the inspector noted that the

material development and presentation appeared to lack formal control.

In the

past, session content had been determined in telephone conversations between

operations management and an instructor.

It was not clear that training

supervision and management were systematically included in the concurrence of

the session content. The inspector informed licensee representatives of the

apparent lack of forni control for this otherwise effective effort and the

potential for excluding training meagement and supervision from the control

process.

The ins)ector tracked seven Licensee Event Reports (LER) through the-TPCM to

assess iow the licensed operator training progr u had responded.

It was

possible to determine how the training issues had been addressed and what

basic changes had been made. However it was not possible to determine the

details of revisions that had been made to existing classroom lesson plans. A

record hard copy of the revision request form was available, but this did not

provide the detail.

During the approval process, the detailed markup of the

change would have been attached to the revision request, but was not retained

af ter the change was final. The previous versions of the lesson plans were

not vaulted or retained, and there was no requirement to do so. The program

supervisor was able to point out most of the changes to the lesson plans, and

it appeared that the required changes had been made in all cases. The only

issue was that the licensee's methodology did not provide for a historical

change record, and this was not considered to be significant.

The inspector reviewed in detail the event that occurred on July 3, 1993 at

FCS.

This event consisted of a loss of coolant accident (LOCA) caused by a

pressurizer safety valve opening prematurely and failing to close after a

turbine valve closure at power.

The entire event was precipitated by an

interruption of the power supply to the turbine control system which caused

the turbine valves to close without a turbine trip signal which would have

-

caused a reactor trip.

The training response to this event had been minimal as the licensed crew's

performance during the event was considered to be good.

A crew communication

problem had been identified, but the corrective action had been to revise the

.

.

.

.

._

-

-.

-

-

-

..

.

4

'

-9-

Emergency Operating Procedures. Another issue had arisen regarding which

reactor coolant system (RCS) subcooling instrumentation was the most viable

during the event. The training department's response had been to initiate an

extensive retlew of the event in the rotational special topics training.

Another training action was to fine tune a simulator scenario to duplicata the

event as precisely as possible. This effort was undertaken mainly to validate

the performance of RCS subcooling that was observed during the event. However

there were plans to use this information to develop training th.t would

encourage operators to consider long term effects of stopping and throttling

safety injection system flow during LOCA conditions. A final effort of the

training organization was to draft the detailed event report that would be

distributed to the industry.

The inspector interviewed three of the licensed operators that had been on

shift d9 ring the event of July 3,1993.

Ecch individual was candid and

expressed general satisfaction with their own performance during the event.

All three thought that the training they had received on responding to a LOCA

had been more than adequate. Another common area was the high regard for the

training they have received on the simulator. One individud expressed a

desire to receive more than the 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> of simulator training and evaluation

given during each rotation.

An operator also stated that he now understood

why the training scenarios usually consisted of multiple complex events with

difficult circumstances.

The inspector concluded that the licensed operator training was responding

properly to changes or events. The rotational special topics training was

very effective but appeared to lack formal control.

1.5 Trainina performange Indicators

The training department had initiated its own trending program in the form of

training performance indicators. Only one of the indicators was specific to

licensed operator training, but numerous indicators addressed all programs.

The program tracked 19 different indicators and issued a report every other

month.

The reports received wide distribution, including corporate

management. Below is a sample of indicators tracked that related to licensed

operator training:

Training Personnel Budgeted versus Actual Hours

o

Student Contact Hours by Program

o

Requests for Training

o

Instructor Hours In Plant, Development, Continuing Training

o

Trainee Progress

o

o

Instructors With Licenses

Number of Critique Reports

o

Test Item Development

o

o

Number of Observations

Examination Pass / fall

o

Attendance Percentage for Licensed Operator Training

o

._.

.

__

.

-10-

The inspector reviewed performance indicators dating back to August 1991. The

reports indicated that when the data was reduced and a trend was identified,

corrective action was initiated.

For example, the trend report for

September / October 1991 indicated that attendance at licensed operator training

sessions was low for some individuals.

In subsequent bi-monthly reports, the

attendance of the identified individuals, had increased significantly.

Several other examples of this type of identified trend and ensuing corrective

action caused the inspector to conclude that the performance indicator program

was effective.

1.C CONCLUSIONS

.

The inspector concluded that the Itcensee's training program for maintaining

the skill and knowledge of the licensed operators was effective. One of the

indicators that supported this conclusion was the performance of the licensed

crew during the LOCA event of July 3,1993. A siellar but less severe event

occurred on August 22, 1993, and a different crew responded well. Another

indicator of success was the 100 percent pass results of the last annual

licensed operator requalification examination.

The licensee acknowledged the

inssector's finding concerning potential examination compromise and appeared

entiusiastic about correcting the problem. Management also understood the

concern about staffing and indicated that this situation would be closely

watched.

i

l

i

E

.

.*

AIIACHMEhT

1 PERSONS CONTACTED

1.1 Omaha Public Power District Personnel

  • R. Andrews, Division Manager, Nuclear Services

'

J. Braun, Licensed Reactor Operator

  • G. Cook, Supervisor, Station Licensing

D. Daily, Licensed Operator Training Instructor

C. Darrow, Licensed Operator Training Instructor

  • S. Gambhir, Division Manager, Production Engineering
  • J. Gasper, Manager, Training
  • G. Gu11ani, Supervisor, Operations Training
  • R. Jaworski, Manager, Station Engineering
  • L. Kusek, Manager, Nuclear Safety Review

R. Lewis, Principle Engineer, Design Engineering

  • D. Lippy, Licensing Engineer
  • R. Mehaffey, Principal Engineer, Electrical Engineering
  • S. Miller, System Engineer
  • R. Mueller, Supervisor, Electrical Engineering
  • J. O'Connor, Manager, Design Engineering - Electrical
  • W. Orr, Manager, Quality Assurance and Quality Control
  • T. Patterson, Manager,. Fort Calhoun Station
  • R. Phelps, Manager, Design Engineering

T. Reisdorff, Shift Supervisor

C. Rennerfeldt, Licensed Operator Training Instructor

R. Schreurs, Licensed Senior Reactor Operator

  • R. Short, Manager, Nuclear Licensing and Industry Affairs
  • C

Simmons, Station Licensing Engineer

J. Tesarek, Supervisor Operations and Technical Training (Acting)

  • J. Tills, Assistant Manager, Fort Calhoun Station

R. Ward, Licensed Operator Training Instructor

1.2 NRC Personnel

  • P. Goldberg, Reactor Inspector
  • D. Kelly, Reactor Inspector
  • P. Wagner, Team Leader
  • Denotes personnel that attended the exit meeting conducted on

December 11, 1992.

2 EXIT MEETING

An exit meeting was conducted with licensee management personnel on

December 11, 1992. During this meeting, the inspector reviewed the scope and

findings of the inspection. The licensee did not identify as proprietary any

of the materials provided to, or reviewed by, the inspector during the

inspection.

.