OPERATING DATA REPORT DOCKET NO.
050-0298 UNIT CNS DATE March 10. 1992
_ 402) 825-5766
(
OPERATING STATUS TELEPHONE 1.
Unit Name:
COooet Nuclear Station Notes 2.
Reporting Period; February 1992 3
Ucensed Thermal Power (MWt):
2381 4.
Nameplate Rating (Gross MWe):
836 5.
Design Electrical Rating (Net MWe): 778 6
Maximum Dependable Capacity (Gross MWe): 787 7.
Maximum Dependable Capacity (Net MWe):
764 8
If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report, Give Reasons:
9.
Power Level To Which Restricted, if Any (Net MWe):
10.
Reasons For Restrict:on,if Any:
This Month Yr.-to-Date Cumulative 11.
Hours in Reporting Period 696 0 1.440.0 154.873 0 12.
Number of Hours Reactor Was Critical 576 7 1,320.7 117.821.0 13.
Reactor Reserve Shutdown Hours 0.0 0.0 0.0 14.
Hours Generator On-Une 565_0_
1.309 0 116.081.5 0
15.
Unit Reserve Shutdown Hours 00 00 0.0 16.
Gross Thermal Energy Generated (MWH)
_1.280.256 0 3.041.544.0 236.597.596 0 17.
Gross Electric Energy Generated (MWH) 426.823 0 1.018.966.0 76.589.118.0 18 Not Electric Energy Generated (MWH) 414.200.0 987.589 0 73.917.976 0 19.
Unit Service Factor 81.2 90.9 75 0 20 Unit Availability Factor 81.2 90.9 75.0 21.
Unit Capacity Factor (Using MDC Net) 77.9 89 8 62_5._
22.
Unit Capacity Factor (U9q DER Net) 76 5 88.2 61.3 23.
Unit Forced Outage Rate 18 8 9.1 4.6 24 Shutdown Scheduled Over Next 6 Months (Type. Date, and Duration of Each):
BaMery replacement shutdown - April 17. Duration 7 days 25 If Shut Down At End of Report Period, Estimated Date of Startup:
26 Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITlAL CRITICAUTY INITIAL ELECTRICITY COMMERCLAL OPERATION 9212160196 921204 PDR ADOCK 05000298 R