ML20125C845

From kanterella
Jump to navigation Jump to search
Forwards First Quarterly Status Rept Re Plant Operational Status & Util Activities,Per 820216 Order
ML20125C845
Person / Time
Site: Humboldt Bay
Issue date: 03/31/1982
From: Crane P
PACIFIC GAS & ELECTRIC CO.
To: Lazo R, Linenberger G, Schink D
Atomic Safety and Licensing Board Panel
Shared Package
ML20125C784 List:
References
FOIA-85-007 NUDOCS 8506120176
Download: ML20125C845 (2)


Text

, P4CIFIC GW3 AND ELI TRIC COMPANY a

: COPY  %"

~

( U?!".? -C p;,p. p EE:C.: y:.

~~

March 31,1982 Judge Robert M. Lazo Esq., Chairman Atomic Safety and Licensing Board U. S. Nuclear Regulatory Comission Washington, D. C. 20555 Judge David R. Schink Atomic Safety and Licensing Board Department of Oceanography Texas A&M University College Station. Texas 77840 Judge Gustave A. Linenberger Atomic Safety and Licensing Board U. S. Nuclear Regulatory Comission Washington, D. C. 20555

.( Re: Docket No. 50-133 Hirnboldt Bay Power Plant, Unit No. 3 1

Gentlemen:

l In its Memorandum and Order (" Order") dated February 16,1982, the Board directed PGandE to file a detailed status report with the Board starting April 1,1982 and each .three months thereafter until final resolution of the future operation of HLamboldt Bay Power Plant, Unit No. 3.

Enclosed is Pacific Gas and Electric Company's first quarterly status report, dated April 1,1982. This report sumarizes the current plant status and the status of PGandE's studies on both decomissioning alternatives and alternatives related to conversion of the plant to a fossil fired steam system.

- 1 s l 0506120176 850214 ,

ShPLE -007 PDR

.a ,

2 March 31, 19R2

(

In accordance with Iten 1 of the order, PGandE will complete studies ,

i l, to support a decision regarding the future disposition of the Hmboldt Bay Power Plant, Unit No. 3, consistent with the board requirement that.such a fst'j'j'l r

decision be nade within six months of the issuance by the WRC of the final -

safety policy statenent and its associated goals and guidelines. .

(

,- Respectfully subnitted. C 1

[.ith '

ROBERT OHLBACH PHILIP A. CRANE, Jr.. /(s )

RICHARD F. LOCKE Attorneys for Pacific Gas and Electric Conpany By: Philio A. Crane, Jr.

Philip A. Grane, Jr.

JHRaggio/ PAC:IS Enclosure cc (w/ enc.): Service List bec (w/ene.): Hmboldt Distribution Mr. Vern Rooney, Project Manager Mr. R. H. Engelken, Regional Administrator Mr. Dominic Vassallo, Chief Operator Reactor Branch Ib. 2

(

-,,,w, - - , - , - -

. ,