Letter Sequence Request |
|---|
|
|
MONTHYEARML20096C6401984-08-27027 August 1984 Forwards Application to Amend License NPF-3,revising Tech Specs to Reflect Changes in Reactor Vessel Matls Irradiation Surveillance Schedule & Flow Verification of Auxiliary Feedwater Sys Project stage: Request ML20096C6821984-08-27027 August 1984 Proposed Tech Specs Reflecting Changes in Reactor Vessel Matls Irradiation Surveillance Schedule & Flow Verification of Auxiliary Feedwater Sys Project stage: Other ML20096C6631984-08-27027 August 1984 Application for Amend to License NPF-3,revising Tech Specs to Reflect Changes in Reactor Vessel Matls Irradiation Surveillance Schedule & Flow Verification of Auxiliary Feedwater Sys.Fee Paid Project stage: Request ML20100A7681985-03-21021 March 1985 Submits Info Re Property Insurance Coverage,Per 10CFR50.54(w)(4) Requirements Project stage: Request ML20117L5491985-05-0909 May 1985 Informs That Response to 850321 Request for Addl Info Re Redundant Safety Features Actuation Signal Channel Independence Will Be Submitted in Jul 1985 Project stage: Request ML20133D7961985-08-0101 August 1985 Responds to Re NUREG-0737,Item II.E.1.1 Concerning Auxiliary Feedwater Sys Tech Specs & Request to Review SER & Submit Revised Amend Application.Revised Application Will Be Submitted by 850830 Project stage: Other ML20138C9801985-08-29029 August 1985 Proposed Tech Spec Changes,Identifying Water Source for Auxiliary Feedwater Pumps,Safety Grade Flow Indication Used for Flow Verification & Bases Project stage: Other ML20138C9731985-08-29029 August 1985 Application for Amend to License NPF-3,identifying Water Source for Auxiliary Feedwater Pumps,Safety Grade Flow Indication for Flow Verification & Bases Project stage: Request ML20138C9651985-08-29029 August 1985 Forwards Application for Amend to License NPF-3,revising Tech Specs Re Water Source for Auxiliary Feedwater Pumps, Safety Grade Flow Indication for Flow Verification & Bases Project stage: Request ML20212C8791986-12-22022 December 1986 Safety Evaluation Supporting Amend 96 to License NPF-3 Project stage: Approval ML20212C8351986-12-22022 December 1986 Amend 96 to License NPF-3,modifying Tech Spec Sections 3.7.1.2 & 4.7.1.2 & Associated Bases to Clarify Applicability of Limiting Condition for Operation & to Add New Surveillance Requirements for Auxiliary Feedwater Sys Project stage: Approval 1985-05-09
[Table View] |
Text
_
TOLEDO
%mm EDISON Docket No. 50-346 RICHARD P. CROUSE Vce Prendert License No. NPF-3'
%.nm Serial No. 1152 May 9, 1985 Director of Nuclear Reactor Regulation Attention:
Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Licensing United States Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Stolz:
This is in response to your letter dated March 21, 1985 (Log No. 1723) concerning Redundant SFAS Channel Independence; Request for Additional Information (RAI). In the two years since our last correspondence, the personnel who were involved in this concern have left our employment. To provide the RAI, we will review our records and evaluate the data requested.
Toledo Edison will submit the response to the RAI in July, 1985 for the Davis-Besse Nuclear Power Station Unit No. 1.
Very truly yours, ffk RPC:LCS: GAB:lah cc: DB-1 NRC Resident Inspector y0 p%2R !!83lip y