Monthly Operating Repts for Apr 1995 for Braidwood Nuclear Power Station Units 1 & 2
ML20117D699
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 04/30/1996
From: Pershey C, Tulon T
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
BW-96-0055, BW-96-55, NUDOCS 9605140166
Download: ML20117D699 (10)


Text

  • ,

Commonucalth Edimn Company

+

liraidwuni Generating Station Route

  • 1. Ikn 8 6 liracesille. IL 60 6073)619 Tel 815-45R bull May 6,1996 BW/96-0055 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Monthly Operating Report for April 1996 Braidwood Nuclear Power Station, Units 1 and 2 Facility Operating Licenses NPF-72 and NPF-77 NRC Docket Nos. 50-456 and 50-457 Ladies and Gentlemen:

In accordance with Technical Specification 6.9.1.8, enclosed you will find the Monthly Operating Report for Commonwealth Edison Company's (Comed's) Braidwood Nuclear Power Station, Units 1 and 2, covering the period April 1,1996 through April 30,1996.

Please address any comments or questions regarding this matter to Chris Pershey at (815) 458-2801, extension 2173.

Very truly yours, T

ulon tion Manager Braidwood Nuclear Station l

TJT/CP/dm O:iCORREsP2CSTECirDW96 0055 Enclosures cc:

H. J. Miller, Regional Administrator - RIII R. R. Assa, Braidwood Project Manager - NRR C. J. Phillips, Senior Resident Inspector - Braidwood J. L. Roman, IDNS Resident Inspector - Braidwood Oflice of Nuclear Facility Safety - IDNS 9605140166 960430 f[

PDR ADOCK 05000456 R

PDR I I A l!nkuin OsmpJny

BRAIDWOOD NUCLEAR POWER STATION UNIT 1 AND UNIT 2 MONTHL'Y PERFORMANCE REPORT Comed NRC DOCKET NO. 050-456, LICENSE NO. NPF-72 NRC DOCKET NO. 050-457, LICENSE NO. NPF-77 i

i i

i l

4

l A. OPERATING DATA REPORT i

Docket No: 50 - 456 Unit: Braidwood 1 Cate: 05/06/1996 Completed by: Chris Pershey l

Telephone: 815-458-2801

. OPERATING STATUS l

1) Reporting Period: April 1996 Gross Hours:

719

2) Currently Authorized Power Level (MWt):

3411 Design Electrical Rating (MWe-gross):

1175 Design Electrical Rating (MWe-net):

1120 Max Dependable Capacity (MWe-gross):

1175 l

Max Dependable Capacity (MWe-net):

1120

3) Power level to which restricted (if Any):

None l

4) Reasons for restrictions (If Any):

None t

l This Mo.

Yr to Date Cumulative

5) Report Period Hours:

719 2903 67976

6) Hours Reactor Critical:

719.0 2459.1 53437.0

7) RX ReseNe Shutdown Hours:

00 0.0 0.0 l

8) Hours Generator on Line:

719.0 2451.5 52632.2

9) Unit Reserve Shutdown Hours:

0.0 0.0 0.0 10 Gross Thermal Energy (MWHt):

2,438,749 8,072,043 168,995,608 11 Gross Elect. Energy (MWH):

850,528 2,811,851 56,202,171 12 Net Elect. Energy (MWH):

826,489 2,710,956 53,838,316 13 Reactor Service Factor:

100.0 84.7 78.6 14 Reactor Availability Factor:

100.0 84.7 78.6 15 Unit Service Factor:

100.0 84.4 77.4 16 Unit Availability Factor-100.0 84.4 77.4 17 Unit Capacity Factor (MDC NET):

102.6 83.4 70 7 18 Unit Capacity Factor (DER NET):

102.6 83.4 70.7 19 Unit Forced Outage Rate:

0.0 15.6 8.1 20 Unit Forced Outage Hours:

0.0 451.5 4666.0 21 Shutdown Schedule Over Next 6 Months: Mid-cycle outage - 05/25/1996

}

22 If Shutdown at End of Reporting Period,

}_

Estimated Date of Startup:

i i

l

l B. AVERAGE DAILY UNIT NET POWER LEVEL LOG Docket No: 50-456 Unit: Braidwood 1 Date: 05/06/1996 Completed by: Chris Pershey Telephone: 815-458-2801 MONTH: April 1996 Qay MWe-net Ray MWe-net 1) 1150

  • 16) 1154
  • 2) 1151
  • 17) 1155
  • 3) 1152
  • 18) 1156
  • j 4) 1151
  • 19) 1153
  • l 5) 1151
  • 20) 1153
  • l 6) 1151
  • 21) 1155*

l 7) 1151

  • 22) 1155*

8) 1151

  • 23) 1154
  • 9) 1152
  • 24) 1155
  • 10) 1154
  • 25) 1151
  • 11) 1154
  • 26) 1150
  • 12) 1154
  • 27) 1148
  • 13) 1154
  • 28) 1055
  • 14) 1154
  • 29) 1147
  • 15) 1154
  • 30) 1146 *
  • Due to condenser efficiency i

I l

l l

l h

e 1

i j

i.

C.

UNIT SHUTDOWNS / REDUCTIONS

[

Docket No.:

50 - 456 l

Unit:

Braidwood 1 Date: 05/06/96 Completed by:

Chris Pershey Telephone:

815-458-2801' REPORT PERIOD:

April 1996 i

LER Cause & Corrective Action l

NA Date Iype_

Hours Reason Method Number System Component to Prevent Recurrence j

None F

i i

SUMMARY

Unit 1 entered the month of April 1996 with 100% capability and operated routinely the entire month.

TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A-Equipment Failure Maint or Test 1 - Manual S - Scheduled B - Maint or Test 2 - Manual Scram Exhibit F & Instructions for i

C - Refueling 3 - Auto Scram Preparation of Data Entry Sheet D - Regulatory Restriction 4 - Continued Licensee Event Report (LER) File E - Operator Training & Licensee Examination 5 - Reduced Load (NUREG-0161).

F - Administration G - Operator Error H - Other j

k D.

SWETY/ RELIEF VALVE OPERATIONS Docket No.:

50 - 456 Unit:

Braidwood 1 Date: 05/06/96 Completed by:

John Lewis Telephone:

815-458-2801 Valves No. & Type Plant Date Actuated Actuation Condition Description of Event None i

i L

A. OPERATING DATA REPORT Docket No: 50- 457 Unit: Braidwood 2 Date: 05/06/1996 Completed by: Chris Pershey Telephone: 815-458-2801 OPERATING STATUS

1) Reporting Period: April 1996 Gross Hours:

719 j

2) Currently Authorized Power Level (MWt):

3411 Design Elec'ncal Rating (MWe-gross):

1175 Design Electrical Rating (MWe-net):

1120 Max Dependable Capacity (MWe-gross):

1175 j

Max Dependable Capacity (MWe-net):

1120

3) Power level to which restricted (if Any):

None

4) Reasons for restrictions (if Any):

None 1

i This Mo.

Yr to Date Cumulative i

5) Report Period Hours:

719 2903 66058

6) Hours Reactor Critical:

0.0 1802.5 55223.9

7) RX Reserve Shutdown Hours:

0.0 0.0 0.0

8) Hours Generator on Line:

0.0 1801.4 54827.5

9) Unit Reserve Shutdown Hours:

0.0 0.0 0.0 10 Gross Thermal EnerDy (MWHt):

0 5926620 174268461 11 Gross Elect. Energy (MWH):

0 2048430 57954217 12 Net Elect. Energy (MWH):

-9492 1959285 55595053 13 Reactor Service Factor:

0.0 62.1 83.6 14 Reactor Availability Factor:

0.0 62.1 83.6 15 Unit Service Factor:

0.0 62.1 83.0 16 Unit Availability Factor:

0.0 62.1 83.0 17 Unit Capacity Factor (MDC NET):

-1.2 60.3 75.1 18 Unit Capacity Factor (DER NET):

-1.2 60.3 75.1 l

19 Unit Forced Outage Rate:

0.0 0.0 5.1 20 Unit Forced Outage Hours:

0.0 0.0 2947.6 21 Shutdown Schedule Over Next 6 Months:

22 If Shutdown at end of Reporting Period, May 9,1996 Estimated Date of Startup:

{

s 1

B. AVERAGE DAILY UNIT NET POWER LEVEL LOG Docket No: 50 - 457 Unit: Braidwood 2 i

Date: 06/06/1996 Completed by: Chris Pershey i

Telephone: 815-458-2801 MONTH: April 1996 QE MWe-net p_ay MWe-net l

a 1)

-13 16)

-13 2)

-13 17)

-13 3)

-13 18)

-13 1

4)

-13 19)

-13 5)

-13 20)

-13 6)

-13 21) 13 7)

-13 22)

-13 8)

-13 23)

-13 9)

-13 24)

-13 10)

-13 25)

-14 1

11)

-13 26)

-14 12)

-13 27)

-14 13)

-13 28)

-14 14)

-13 29)

-14 15)

-13 30)

-14

  • Due to condenser efficiency I

e

~.

C.

UNIT SHUTDOWNS / REDUCTIONS Docket No.:

50 - 457 Unit:

Braidwood 2 Date: 05/06/96 Completed by:

Chris Pershey REPORT PERIOD:

April 1996 LER Cause & Corrective Action h

Date Type Hours Reason Method Number System Component to Prevent Recurrence 2

960401 S

719.0 C

4 Scheduled fifth refueling outage

    • 0

SUMMARY

Unit 2 entered the month of April 19be continuing it's fifth refueling outage which started March 16,1996.

TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure Maint or Test 1 - Manual S - Schedulec B - Maint or Test 2 - Manual Scram Exhibit F & Instructions for C - Refueling 3 - Auto Scram Preparation of Data Entry Sheet D - Regulatory Restriction 4 - Continued Licensee Event Report (LER) File E - Operator Training & Licensee Examination 5 - Reduced Load (NUREG-0161).

F - Administration G - Operator Error H - Other

~

o D.

SAFETY / RELIEF VALVE OPERATIONS Docket No.:

50 - 457 I

Unit:

Braidwood 2 Date: 05/06/96 Completed by:

John Lewis Telephone:

815-458-2801 Valves No. & Type Plant Date_

Actuated Actuation Condition Description of Event None 4

-