U- 0789 054-84 01-18 )L 1A.120
\\
ILLINDIS POWER 00MPANY IP CLINToN POWER STATION. P.o. BOX 678. CLINToN. ILLINOIS 61727 January 18, 1985 Docket No. 50-461 Director of Nuclear Reactor Regulation Attention:
Mr. A. Schwencer, Chief Licensing Branch No. 2 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Subj ect: Clinton Power Station Unit 1 Clinton Power Station Evacuation Time Estimates
Dear Mr. Schwencer:
Enclosed are 10 copics of the final " Evacuation Time Estimates for the Clinton Power Station Plume Exposure Pathway Emergency Planning Zone" dated December 1984. These evacuation time estimates have been revised to reflect comments received from state and local agencies.
Sin er
- yours, t
, www F. A.
. pang berg i
Director - Nuclear Licensing and Configuration Nuclear Station Engineering TLG/cm cc:
B.L. Siegel, NRC Clinton Licensing Project Manager D. Rohrer, Division of Emergency Preparedness and Engineering Responses NRC Resident Office Regional Administrator, Region III USNRC Illinois Department of Nuclear Safety Enclosures k1 DR 0
F pop a
i