Commonwealth Edison one First Nati:;nal Plaz', Chicago, litanois Address Reply to: Post Office Box 767 Chicago. Illinois 60690 March 6, 1985 Mr. James G. Keppler Regional Administrator U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137

SUBJECT:

Braidwood Station Units 1 and 2 10 CFR 50.55(e) No. 84-15 Interim Report G. K. Newberg Welding Program Deficiencies NRC Docket Nos. 50-456/457 References (a):

D. H. Smith letter to J. G. Keppler dated September 10, 1984.

(b):

D. H.

Smith letter to J. G. Keppler dated October 22, 1984.

Dear Mr. Keppler:

References (a) and (b) provided information concerning a potential deficiency reportable pursuant to 10 CFR 50.55(e) regarding deficiencies in the Gust K. Newberg Welding program at our Braidwood Station.

The purpose of this letter is to provide an updated status of the corrective actions taken to resolve this issue.

This letter is considered to be an Interim Report.

Status of Resolution It was previously reported in the above references that all Structural Steel Installation Traveler (SSIT) packages would be reviewed following approval of G. K. Newberg's document review procedure.

Review completion by January 15, 1985, was projected.

Because of the number of issues to be addressed during the SSIT Review (see also Braidwood 50.55(e) 84-05), procedure development has taken much longer than anticipated.

It is currently anticipated that procedure approval will be obtained by March 15, 1985.

Actual SSIT review will take approximately three months.

An interim report will be submitted by May 1, 1985 updating the status of procedure development and implementation.

MAR 1 l' N h[I 8503270027 850306 PDR ADOCK 05000456 S

PDR tg

a

, s*

J. G. Keppler March 6, 1985.

Please address any questions that you or your staff may have concerning this matter ~to this office..

yaytrulyyours, hiLWJ David H. Smith Nuclear Licensing Administrator

-bs cc:

NRC Resident Inspector - Braidwood Director of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 9850N

.