Clarifies Schedule for Removing & Testing Boraflex Spent Fuel Pool Storage Rack Sample Coupons,Per Request.Schedule Revised to Allow More Frequent Coupon Surveillance During Plant Life
ML20108F387
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 12/14/1984
From: Dixon O
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8412200375
Download: ML20108F387 (2)


Text

e J

SOUTH CAROLINA ELECTRIC Sc GAS COMPANY

, CST OFPrCE M4 cotuusiA. sours canotisa 292ie O. W. Dinom. Je nue$*E.. o',,' I,"[on.

December 14, 1984 Mr. Harold R.

Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Subject:

Virgil C.

Summer Nuclear Station Docket No. 50/395 Operating License No. NPF-12 Spent Fuel Pool Storage Racks Coupon Sampling Dear Mr. Denton On January 23, 1984 South Carolina Electric and Gas Company

( SCE&G) made a submittal requesting approval of a proposed modification to rerack the spent fuel pool at the Virgil C.

Summer Nuclear Station.

This modification and the associated Technical Specification changes were approved by the Nuclear Regulatory Commission (NRC) in a letter to Mr. O. W.

Dixon, Jr.,

dated September 27, 1984.

This modification consisted of removing the old storage racks and replacing them with now, high density storage racks.

These new racks are the free standing, modular design variety, some of which contain Boraflex as a neutron absorber material.

This letter is hereby provided at the NRC Staff's request to clarify the schedule for removing and testing the Boraflex sample coupons.

In the January 23, 1984 submittal, a proposed schedule for removing these samples was outlined.

This schedule called for the removal of two coupon samples at each of the following times:

90 days, 180 days, one year, five years, 10 years, 15 years, 20 years, 30 years, and 40 years following installation of the racks.

After further discussion with the rack manufacturer, they recommended that this schedule be revised and replaced with an alternate schedule.

This schedule, which SCE&G has subsequently proceduralized, is as follows:

At each of the.1cxt eight refueling cycles following installation of the racks, remove and test two coupon samples.

Also remove and test two coupons overy five years for the next 40 years following installation of the racks.

This revised schedule allows for a more frequent sampling of the Boraflex material than the previously identified schedule.

The f

0 n

s o

Mr. Harold R.

Denton, Director Spent Fuel Pool Storage Racks Coupon Sampling December 14, 1984 Page #2 90 and 180 day sampling which was included in the original schedule was deleted from the inspection at the recommendation of the rack manuf acturer.

These particular samples were considered to be too soon after installation to provide any meaningful performanca data on the absorber material.

The new schedule provides for more f requent coupon surveillance to be performed over the life of the plant than the previous schedule, and is therefore considered to be a more thorough testing frequency.

If you have any questions, please advise.

Very truly yours, O. W.

xon, Jr.

AMF/OWD/gj cc V. C. Summer C. A.

Price T.

C. Nichols, Jr./O. W. Dixon, Jr.

C. L. Ligon (NSRC)

E.

H. Crews, Jr.

K.

E. Nodland E. C. Roberts R. A. Stough W. A. Williams, Jr.

G.

Percival D. A. Nauman' C. W.

Hehl J. P. O' Reilly J. B.

Knotts, Jr.

Group Managers NPCF O. S.

Bradham File