ML20108B559

From kanterella
Jump to navigation Jump to search

Forwards Application to Amend License NPF-3,allowing Startup & Operation Utilizing Current Startup Feedwater Pump Configuration
ML20108B559
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/12/1984
From: Crouse R
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
Shared Package
ML20108B562 List:
References
1100, TAC-57023, NUDOCS 8411160104
Download: ML20108B559 (1)


Text

-

A v -

l t l l

l TCM E DO Docket No. 50-346

%: IEEllEBCIPJ Asw.aa P C .

License No. NPF-3 w . p.., .

us +a Serial No. 1100 November 12, 1984 Director of Nucle:r Reactor Regulation Attention: Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Operating Reactors United States Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Stolz:

Under separate cover, we are transmitting three (3) original and forty (40) conformed copies of an application for Amendment to Facility Operating License No. NPF-3 for the Davis-Besse Nuclear Power Station Unit No. 1.

This application requests that the Davis-Besse Nuclear Power Station Unit No. 1 Operating License be amended to include the attached License Condition 2.C.(3)(t) regarding the Startup Feedwater Pump (SUFP).

The attachments identify the change and provide the Safety Evaluation and Significant Hazards Consideration for the License Condition concerning the SUFP. The NRC has requested Toledo Edison (TED) submit a License Condition for the operation of the SUFP and completion of the new SUFP system. This request results from a TED submittal dated October 18, 1984 (Serial No.

1070) concerning NRC review of the SUFP operation and approval for interim operation until the new SUFP is operable. The new SUFP project will be designed, procured and installed under the procedures of the Integrated Living Schedule Program and will be designated a Category A item. Any changes to the committed schedule will, therefore, require the prior approval of the NRC. This submittal is a reviaton to our letter dated October 18, 1984 and, therefore, no fee is incurred.

Toledo Edison requests expeditious review of this application to support the December, 1984 plant startup from the current refueling outage.

Very truly yours, R411160104 841112 PDR ADOCK 05000346 p POR QT kop s