Informs That Review of Available Gulfalloy,Inc Documentation Complete & Rept on Findings Encl,Per Generic Ltr 83-06.Rept on Matl Provided W/Purchase Order 38497-24503C Will Be Provided Following Upcoming Unit 3 Refueling Outage
ML20107M042
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 02/15/1985
From: Williams J
FLORIDA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
GL-83-06, GL-83-6, GL-8376, IEB-83-06, IEB-83-6, L-85-76, NUDOCS 8503010138
Download: ML20107M042 (2)


Text

-.

O

.A FLORIDA POWER & LIGHT COMPANY February 15, 1984 L-85-76 l

' Dr.' J. Nelson Grace Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta Street, N.W., Suite 2900 Atlanta, GA 30323 Dear Dr. Grace Re:

Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 IE Bulletin 83-06 Our letter, L-84-259, dated September 28, 1984 described actions FPL was

. taking to determine if Gulfalloy Inc. had supplied FPL with Tube-Line material s.

One of the actions discussed was a review of documentation associated with Gulfalloy Purchase Orders. We have now completed our review of all available Gulfalloy documentation and a report of the findings of this review is attached.

A report on the material provided with Purchase Order 38497-24503C will be provided following the upcoming Unit 3 refueling outage as discussed in our letter L-84-377 dated December 17, 1984. We expect that this report will close out FPL actions on Bulletin 83-06.

Should you have any questions on this infonnation, please contact us.

Very truly yours, b

J. W. Williams, Jr.

Group Vice President Nuclear Energy

~JWW/PLP/cas Attachment

.cc:'

Harold F. Reis, Esquire PNS-LI-85-68/1 8503010138 850215

?"

^

DR fff/ t t PEOPLE.. SERVING PEOPLE

.. _ -....,.. -..,. -. ~. _. -.. -. -

- e c

Attachment Turkey Point Units 3 & 4 Docket No. 50-250, 50-251 I & E Bulletin 83-06 FPL has completed review of all documentation available for materials supplied by Gulfalloy, Houston, Texas.

Based on our review and current actions in L

progress, the following status encompasses all Tube Line Materials received at the Turkey Point Plant.

Line RCR No.

FPL P0/DWA Items Status q.

093-84 38497-39056C 7

Note 1 DWA 38624B 25 Note 2 38625 7

Note 1 39541 11 Note 1 16 Note 2 17 Note 1 18 Note 3 495-84 38497-24503C 12 A sample of each heat 13 has been sent for chemical /

14 physical testing.

572-84 38497-39056C DWA 34626 10 Note 2 l

NOTE 1: A sample from stock was taken for each heat installed; i

engineering evaluation of chemical and physical testing results demonstrates the material as acceptable.

NOTE 2: All materials received are on-hand and downgraded for use only in non-safety related applications.

NOTE 3: All items installed were removed during initial installation; balance on-hand downgraded for use only in non-safety related applications.