ML20106B894

From kanterella
Jump to navigation Jump to search
Requests Extension of Time to Adequately Review Insp Rept 50-261/84-17.Request Based on Delayed Receipt of Rept
ML20106B894
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 07/27/1984
From: Morgan R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20106B850 List:
References
RSEP-84-502, NUDOCS 8410230564
Download: ML20106B894 (1)


Text

_

fY CD&L Carolina Power A Light _ Company

'E 30 n!0 : 12 H. B. ROBINSON STEAM ELECTRIC PLANT -

POST OFFICE BOX 790 HARTSVILLE, S0tTIH CAROLINA 29550 JUL 271984

' Robinson File No: 13510E Serial: - RSEP/84--502 Mr. James P. O'Reilly-Regional Administrator U. S. Nuclear Regulatory Commission Region II 1101 Marietta Street N.W.

Atlanta, Georgia 30323 H. B. ROBINSON SIT, PLANT, UNIT 2 DOCKET NO. 50-261 LICENSE NO. DPR-23 IE INSPECTION REPORI IER-84-17

Dear Mr. O'Reilly:

Carolina Power and Light (CP&L) has received the subject report and requests an extension to the period allowed for review and response.

IE Inspection Report IER-84-17, dated June 29, 1984, which was addressed to the Plant, has not been received by H. B. Robinson Document Control.

Howeve r, a copy of the report was received July 13, 1984, via the General Office.

Based on the delay in receiving this report, CP&L requests an extension t o Augus t 10, 1984. This will provide the necessary time to adequately review the report and prepare a response in accordance with H. B. Robinson's policy for NRC correspondence.

Very truly yours,

'l -

R. E. Mo n

General Manager H. B. Robinson SEC Plant JCS/mi 8410230564 840918 PDR ADOCK 05000261 G