Final Deficiency Rept (55(e)-84-48) Re Separation of Category I Cable in Free Air.Initially Reported on 841031. Electrical Installation Spec NMP2-E061A Revised & Cable Installation Prior to Sept 1984 Reinspected by Field QC
ML20100D299
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 02/21/1985
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
(55(E)-84-48), (NMP2L-0344), (NMP2L-344), NUDOCS 8504020387
Download: ML20100D299 (2)


Text

_ _ _

Y NIAGARA NuMOHAWK NIAGARA MOHAWK POWER CORPORATION /300 ERIE BOULEVARD WEST. SYRACUSE. N Y.13202/ TELEPHONE (3 February 21, 1985 (NMP2L 0344)

Mr. R. W. Starostecki, Director U. S. Nuclear Regulatory Comission Region I Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point - Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

Enclosed is a final report in accordance with 10CFR50.55(e) for the problem concerning the separation of Category I cable in free air. This problem was reported via tel-con to T. Silko of your staff on October 31, 1984 An interim report was submitted via our letter dated November 30, 1984.

Very truly yours, C. V. Mangan Vice President Nuclear Engineering and Licensing CVM/GG:cla xc: Director of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 R. A. Gramm, NRC Resident Inspector Project File (2) 8504020307 850221 PDR ADOCK 05000410 S pDR ', _

jc oy

p

+,o. .e D-NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT - UNIT 2 DOCKET NO. 50-410 Final Report for a Problem Concerning Cable Separation in Free Air (55(e)-84-48)

Description of the Problem Certain cable installations completed prior to August 1984 did not meet the separation criteria for cables in free air as delineated in the specification for cable installation NMP2-E061A.

Analysis of Safety' Implications A - detailed analysis of safety inplications, to determine the effect of the actual separation between cables on the safety of operation of the plant, was not performed because the corrective actions outlined below have been/will be taken. However, it can be concluded, _ that since the separation criteria was not met . for certain applications, a possibility existed that the safety of operation of the plant could have been adversely affected.

Corrective Actions

1. In August 1984, Electrical Installation Specification No. NMP2-E061 A was revised to clarify in detail the separation requirements for cables in Free Air.-
2. In August,1984, Stone & Webster Field Quality Control added an attribute to its inspection plan (Cable Pulling Installations - N20E061AFA025) for the separation requirements for cable in Free Air.
3. Cable installations in Free Air Inspected prior to September,1984, will be re-inspected by Field Quality Control and nonconformities identified during their re-inspection will be corrected. The corrective action is expected to be completed by December 31, 1985