Informs That Addl Time Needed to Implement Corrective Actions Listed in 840316 Response to Insp Rept 50-400/83-37-01 Re Failure to Control Electrical Cable Installation.Full Compliance Expected by 850115
ML20099L583
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 08/24/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-254 NUDOCS 8412010183
Download: ML20099L583 (1)


Text

CD&L Carolina Power & Light Company 04AUGJI Pj.49 P. O. Box 101, New Hill, NC 27562 August 24, 1984 Mr. James P. O'Reilly NRC-254 United States N.iclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, GA- 30323

Dear Mr. O'Reilly:

In our March 16, 1984 response to RII:GFM/RLP 50-400/83-37-01, we informed you of the actions taken and planned to resolve the referenced violation concerning " Failure to Control Electrical Cable Installation." At the time of our response, it was projected that corrective actions would be completed by September 1, 1984. This letter is to inform you that we will require additional time to complete the corrective actions as stated in our response.

Harris Plant Engineering Section has completed their review and design criteria needed 1o implement corrective action has been issued. Implementation of the design criteria is now underway. It is ct.rrently projected that full compliance' will be achieved by January 15, 1985.

Thank you for your consideration in this matter.

Yours very truly, ff;f R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/j am cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)