I VIRGINIA EI.ncUtIC AND Powen Co>f PANY RictixoNu, VIRGINIA 20261 January 10, 1996 l
U. S. Nuclear Regulatory Commission Serial No.96-010 Attention: Document Control Desk NL&OS/JHL/ CMC Washington, D.C. 20555 Docket Nos.
50-338 50-339 License Nos. NPF-4 NPF-7 Gentlemen:
VIRGINlA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT Enclosed is the December 1995 Monthly Operating Report for North Anna Power Station Units 1 and 2.
Very truly yours, M. L. Bowling, Manager Nuclear-Licensing and Operations Support Enclosure cc:
U.S. Nuclear Regulatory Commission Region 11 101 Marietta Street, NW Suite 2900 Atlanta, GA 30323 i.gr. R. D. McWhorter i
NRC Senior Resident inspector North Anna Power Station 17zeyb g9 9601170217 951231 PDR ADOCK 05000330 gi R
\\
_ -... - =. -. -
n I
i 4
i 1
4 i
.i
't i
VIRGIN 1.1 POWER COMPANY
I NORTH ANNA POWER STATION j
MONTHLY OPERATING REPORT l-l 4
I MONTH:
December YEAR:
1995 f
4 T
T 4
Approved:
J p
stauon sanager 2
OPERATING DATA REPORT DOCKET No.:
50-338 DATE: January 5,1996 CONTACT: J. A. Stall PHONE: (540) 894-2101 OPERATING STATUS 1.
Un i t N ame r................................ N o r t h Anna 1 2.
Reporting Period:......................... December 1995-3.
L icensed Thermal Power (MWt ):.............
2,893 4.
N ameplate Rating (Gross MWe):.............
994 5.
D sign Electrical Rating (Net MWe):.......
907 6.
Maximum Dependable capacity (Gross MWe):..
940 7.
M2ximum Dependable Capacity (Net MWe):....
893 8.
If changes occu.- in capacity Ratings (Items No. 3 thru 7) since last report, give reasons: ____N/A l
l 9.
Power level to which restricted, if any (Net MWe): ____N/A
- 10. Reasons for restrictions, if any:
N/A This Month Y-t-D Cumulative I
- 11. H ours i n R epor t i ng Pe r i od.................................
744.0 8,760.0 153,636.0
- 12. Number of Hours Reactor was Critical......................
744.0 8, 738.6 117,186.4
- 13. Rsactor Reserve Shutdown Hours......................
0.0 20.9 6,951.4
- 14. Hours Generator 0n-Line...................................
744.0 8,733.8 114,187.5
- 15. Unit Reserve Shutdown Hours...............................
0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH)...................... 2,084,982.1 25,128,157.2 305,313,737.1
- 17. Gross Electrical Energy Generated (MWH)...................
682,434.0 8,242,715.0 100,318,335.0 j
- 18. Het Electrical Energy Gener
,J (MWH).....................
648,964.0 7,838,868.0 95,041,154.0
- 19. Unit Service Factor.........
100.0%
99.7%
74.3%
- 20. Unit Availability Factor..................................
100.0%
99.7%
74.3%
- 21. Uni t Capaci ty Factor (using MDC Ne t )......................
97.7%
99.8%
69.2%
- 22. Unit Capacity Factor (using DER Net)......................
96.2%
98.7%
68.2%
- 23. Forced Outage Rate........................................
0.0%
0.3%
9.3%
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):_ Refueling Outage Scheduled for February 10, 1996, Duration 29 Days
- 25. If Shutdown at end of Report Period, estimated time of Startup: _N/A
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION I
e e
c w
,+,,-4
4 AVERAGE DAILY UNIT POWER LEVEL Docket No.:
50-338 3
Unit:
NA-3 Date:
January 5, 1996 i
Contact J.
A. Stall Phone:
(540) 894-2101 i
)
}
l MONTH: December 1995 i
DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
LEVEL (MWe-Net) 1 894 17 879 l
2 901 18 877 3
901 19 873 4
901 20 871 5
900 21 868 4
6 900 22 856 7
900 23 838 8
900 24 838 d
9 901 25 835 10 900 26 832 11 900 27 829
{
12 900 28 826 j
13 899 29 814 14 899 30 806 15 899 31 804 16 896 j
l 1
i i
Instructions:
On this format, list the average daily unit power level in MWe-Net for each day in the reporting month, compute to the nearest whole megawatt.
l l
NORTH ANNA POWER STATION UNIT-NO.:
1 MONTH:
December
SUMMARY
OF OPERATING EXPERIENCE Page 1 of 1 Listed below in chronological sequence is a
summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.
Date Time Data December 01, 1995 0000 Began month with unit at 100% power, 944 MWe, 1125 Commenced ramp from 100% power, 944 MWe to perform Turbine Valve Freedom Test (TVFT).
1210 Unit stable at 91% power, 870 MWe, 1258 TVFT completed satisfactorily.
1313 Commenced unit ramp to 100% power from 915 power, 867 MWe.
1419 Unit stable at 100% power, 945 MWe.
December 15, 1995 1500 Commenced End of Life coastdown for February 1996 Refueling Outage.
j December 31, 1995 2400 Ended month with unit at 89.4% power, 849 MWe, i
Several small unit ramp-downs (<5% power each) have occurred during this month to match Tave and Tref during end-of-cycle coastdown and are not individually recorded in this report.
..-.__=.___m
. _... _ _ ~ _. _ _ _ _ _, _ _... _ _ _ _ _.. -. _ _ _ _.. _. _. _. _ _... _ _ _ _ _
d 4
1 i
Page 1
of 1
UNIT SHUTDOWN AND POWER REDUCTIONS Explanation Sheet Docket No.:
50-338 Report Month December Unit Name:
NA-1 Year:
1995 Date: Januarv 5, 1996
Contact:
J.
A.
Stall No entry this month.
1 I
a l
i 1
l
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:
50-338 UNIT NAME:
NA-1 DATE: January 5, 1996 REPORT MONTH: December 1995 CONTACT:
J.
A.
Stall PHONE: (540) 894-2101 1
1 2
3 4
5 No.
Date Type Duration Reason Method of Licensee System Component Cause & Corrective (hrs)
Shutting Event Code Code Action to Down Reactor Report #
Prevent Recurrence No Entry This Month o
i 1: Type 2: Reason 3: Method 4:
F= Forced A= Equipment Failure (explain) 1= Manual Exhibit F-Instructions S= Scheduled B= Maintenance or Test 2= Manual Scram for preparation of Data C= Refueling 3= Automatic Scram Entry Sheets for Licensee D= Regulatory Restriction 4= Continuations Event Report (LER) File E= Operator Training & License Examination 5= Load Reduction (NUREG-Ol61)
F= Administrative 9=Other G= Operational Error 5:
H=Other (explain)
Exhibit H - Same Source s
i s
OPERATING DATA REPc4T a.
DOCKET NO.
50-339 DATE: January 5, 1996 CONTACT:
J. A. Statt PHONE: (540) 894 2101 1
OPERATING STATUS s
A 1.
Un i t N ame :................................ N o r t h Anna 2 2.
Reporting Period:......................... December 1995 3.
Licensed Thermal Power (MWt):.............
2893 7
l 4.
Nameplate Rating (Gross MWe):.............
979 j
5.
Ossign Electrical Rating (Net MWe):.......
907 6.
MJtXimun Dependable Capacity (Gross MWe):..
944 7.
MIximun Deperuste Capacity (Net MWe):....
897 i
8.
If changes occur in Capacity Ratings (Items No. 3 thru 7) since test report, give reasons:
N/A 4
i 1
1 n
1 9.
Power Level to which restricted, if any (Net MWe): _ N/A
- 10. Raasons for restrictions, if any:
N/A This Month Y*t-D Cumulative
- 11. Hours in Reporting Period.................................
744.0 8,760.0 131,904.0
- 12. Nunber o f Hours Reac tor was Cri t i ca l......................
744.0 7,124.1 110,057.6
- 13. Reactor Reserve Shutdown Hours............................
0.0 26.1 6,535.0
- 14. Hours Generator 0n-Line...................................
744.0 7,087.4 108,923.1
- 15. Unit Reserve Shutdown Hours...............................
0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH)..................... 2,150,951.2 19,361,274.7 295,977,238.7
- 17. Gross Elect rical Energy Generated (MWH)...................
709,995.0 6,354,561.0 96,831,418.0
- 18. Nst Electrical Energy Generated (MWH).....................
676,339.0 6,031,671.0 92,571,639.0
- 19. Unit Service Factor.......................................
100.0%
80.9%
82.6%
- 20. Unit Availability Factor..................................
100.0%
80.9%
82.6%
- 21. Unit capacity Factor (using MDC Net)......................
101.3%
77.2%
78.0%
- 22. Unit Capacity Factor (using DER Net)......................
100.2%
75.9%
77.4%
- 23. Forced Outage Rate........................................
0.0%
0,4%
4.9%
l
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
N/A i
1
- 25. If Shutdown at end of Report Period, estimated time of Startup:
N/A
- 26. Units in Test Status (Prior to comercial Operation):
Forecast Achieved INITIAL CRITICALITY 1
INITIAL ELECTRICITY COMMERCIAL OPERATION J
AVERAGE DAILY UNIT POWER LEVEL Docket No.:
50-339 Unit:
NA-2 Date:
Januarv 5, 1996 Contact J.
A. Stall Phone:
(540) 894-2101 MONTH: December 1995 i
DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER j
LEVEL (MWe-Net)
LEVEL (MWo-Net) 1 911 17 907 i
2 911 18 909 3
911 19 910 4
911 20 912 l
5 910 21 912 6
910 22 910 i
7 909 23 911 l
8 909 24 911 l
9 901 25 912 i
l 10 911 26 912 11 910 27 910 f
12 910 28 908 13 909 29 908 14 909 30 908 15 893 31 908 16 907 l
i l
Instructions:
On this format, list the average daily unit power level in MWe-l Net for each day in the reporting month.
Compute to the nearest whole megawatt.
l
NORTH ANNA POWER STATION UNIT NO.:
2 MONTH:
December
SUMMARY
OF OPERA'IING EXPERIENCE Page 1 of 1 Listed below in chronological sequence is a summary of operating j
experiences for this month which required load reductions or resulted in significant non-load related incidents.
Date Time Data December 01, 1995 0000 Began month with unit stable at 100% power, 955
- MWe, December 08, 1995 2320 Commenced rampimg unit from 100% power, 953 MWe to allow removal of 2-FW-E-1B relief valve.
December 09, 1995 0100 Unit stable at 99% power, 935 MWe, I
1347 Feedwater
- heater, 2-FW-E-1B, returned to service.
Commenced ramp to 100% power.
1400 Unit stable at 100% power, 954 MWe.
December 15, 1995 0907 Commenced ramping unit from 100% power, 953 MWe
]
for Turbine valve Freedom Test (TVFT).
0940 Unit stable at 90% power, 855 MWe.
1046 TVFT Completed satisfactorily.
1324 Commenced ramping unit from 90% pcwer, 871 MWe to 100% power.
1441 Unit stable at 100% power, 953 MWe.
December 31, 1995 2400 Ended month with unit stable at 100% power, 957 Mwe.
t 1
4 1
]
i Page 1
of 1
1 UNIT SHUTDOWN AND POWER REDUCTIONS Explanation Sheet i
Docket No.:
50-339 l
Report Month December Unit Name:
NA-2 Year:
1995 Date: Januarv 5, 1996
Contact:
J.
A.
Stall 1
No entry this month.
l c
i i
a
]
f i
r 4
DOCKET NO.:
50-339 UNIT NAME:
NA-2 DATE: January 5, 1996 REPORT MONTH: December 1995 CONTACT:
J.
A.
Stall PHONE: (540) 894-2101 1
2 3
4 5
No.
Date Type Duration Reason Method of Licensee System Component Cause & Corrective (hrs)
Shutting Event Code Code Action to Down Reactor Report #
Prevent Recurrence
- No Entry This Month 1: Type 2: Reason 3: Method 4:
F= Forced A= Equipment Failure (explain) 1= Manual Exhibit F-Instructions S= Scheduled B= Maintenance or Test 2= Manual Scram for preparation of Data C= Refueling 3= Automatic Scram Entry Sheets for Licensee D= Regulatory Restriction 4= Continuations Event Report (LER) File E= Operator Training & License Examination 5= Load Reduction (NUREG-0161)
F=Adulinistrative 9=Other G= Operational Error 5:
H=Other (explain)
Exhibit H - Same Source o
.