Docket No. 50-336 B15422 Millstone Nuclear Power Station, Unit No. 2 Proposed Revision to Technical Specifications One-Time Only A.C.

Sources Allowed Outage Time Extension Marked-up Pages November 1995 YDR h

.P

6/14/94

~

3/4.8 ELECTRICAL POWER SYSTDi$

y4.3.1 A.C. SOURCES 2

SPDIATING

. LINITING COWITION FOR OPDIATION 3.8.l.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a.

Two physically independent circuits between the offsite trans-mission network and the switchyard, and b.

Two separate and independent diesel generators each with a separate fuel oil supply tank containing a minimum of 12,000 gallons of fuel.

IPPLICABILITY: MODES, 1, 2, 3 and 4.

ACIl0N:

a.

With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by perfoming Surveillance Requirement 4.8.1.1.1 within I hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.

If either diesel generator has not been successfully tested within the past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, demonstrate its OPERABILITY by performing Surveillance Requirement 4.8.1.1.2.a.2 separately for each such diesel generator within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Restore the offsite circuit to OPERABLE status within 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least NOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

b.

With one diesel generator inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing Surveillance Requirement 4.'8.1.1.1 within I hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and if the diesel generator became inoperable due to any cause other than preplanned preventative maintenance or testing, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing Surveillance Requirement 4.8.1.1.2.a.1 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> *; restore the diesel 4

generator to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least i

HDT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the followino

  1. Excep+ bt once. clurin ne 64illsbe. Wi+ No.1 C ele.15 Refwelin Ouh e.' Oii, ~72. hour Allowaci o h e Me. cem he ex4en 3

d to

'7 clays.

  • This test is re utred to be completed regardless of when the inoperable j

diesel generator s restored to an OPERABLE status.

RILLSTONE - 181IT 2 3/48-1 Amendment No.#,

177, i

i t'

Dpcket No. 50-336 B15422 I

i l

i L

i Millstone Nuclear Power Station, Unit No. 2 Proposed Revision to Technical Specifications One-Time Only A.C.

Sources Allowed Outage Time Extension Retyped Version of Current Technical Specifications I

i l

I i

November 1995

_i

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a.

Two physically independent circuits between the offsite trans-mission network and the switchyard, and b.

Two separate and independent diesel generators each with a separate fuel oil supply tank containing a minimum of 12,000 i

gallons of fuel.

APPLICABILITY: MODES, 1, 2, 3 and 4.

ACTION:

a.

With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.

If either diesel generator has not been successfully tested within the past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, demonstrate its J

OPERABILITY by performing Surveillance Requirement 4.8.1.1.2.a.2 separately for each such diesel generator within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Restore the offsite circuit to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> **

l or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

b.

With one diesel generator inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing Surveillance Requirement 4.8.1.1.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and if the diesel generator became inoperable due to any cause other than preplanned preventative maintenance or testing,

)

demonstrate the OPERABILITY of the remaining 0PERABLE diesel generator by performing Surveillance Requirement 4.8.1.1.2.a.2 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> *; restore the diesel generator to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least H0T STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

  • This test is required to be completed regardless of when the inoperable diesel generator is restored to an OPERABLE status.
    • Except that once during the Millstone Unit No.1 Cycle 15 Refueling Outage, this 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Allowed Outage Time can be extended to 7 days.

MILLSTONE - UNIT 2 3/4 8-1 Amendment No. M. 177, 0221

-.