..t IMSCORSin Electnc POWER COMPANY 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 July 11, 1984 Director of Regulatory Operations U. S. NUCLEAR REGULATORY COMMISSION Washington, D.
C.
20555 Gentlemen:
MONTHLY OPERATING REPORTS POINT BEACH NUCLEAR PLANT Attached are monthly operating reports for Units 1 and 2, Point Beach Nuclear Plant, for the calend.r month of June 1984.
Also attached is a revision to the May 1984 monthly operating report form AD-28B " Unit Shutdowns and Power Reductions" for Point Beach Unit 2.
This report has been revised to correct the sequential number for the shutdown listed on the form.
Very truly yours, n
de Vice Presiden Nuc ear Power C. W. Fay Attachments Copies to J.
G. Keppler - NRC, Region III NRC Resident Inspector C.
F. Riederer - PSCW k
[
O R
';1
N.
a e.
OPERATING DATA REPORT DOCKE T NO. SC -2 56 DATE July 1, 1984 COMPLETED BY
- 0. U. FAY TELEPHONE 414 277 2811 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT UNIT 1
. NOTES
- 2. REPORTING PERIOD:
JUNE 1984
- 3. LICENSED THERMAL POWER (NUT):
1518.
- 4. NAMEPLATE RATING (GROSS MWE):
523.8
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
485.
- 8. IF CHANGES DCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NOT APPLICA0LE
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (HET MWE): NOT APPLICABLE
- 10. REASONS FOR RESTRICTIONS, (IF ANY): NOT APPLICABLE THIS NONTH YR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 720 4,367 119,663
- 12. NUMPER OF HOURS REACTOR WAS CRITICAL 720.0 2,018.4 96,096.9
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 3.0 629.3
- 14. HOURS GENERATOR ON LINE 720.0 1,984.5 93.592.0
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 5.8 799.3
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,076,350 2,870,430 126,405,742
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 369,630 991,280 42,387,260
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 353,890 941,040 40,303,474
- 19. UNIT SERVICE FACTOR 100.0 45.4 78.2
- 20. UNIT AVAILABILITY FACTOR 100.0 45.6 78.9
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 101.3 44.4 68.9
- 22. UNIT CAPACITY FACTOR (USING DER NET) 98.9 43.4 67.8
- 23. UNIT FORCED OUTAGE RATE 0.0 0.0 2.6
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
{Ti NONE
)
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: NOT SHUTDOWN O
DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22. 1977 n
?
DOCKl:T NO.
50-266 UNIT NAME Point Beach Unit 1 DATE July 9, 1984 COMPLETED BY C.
J.
Krause TELEPHONE 414/277-2001 AVERAGE DAILY UNIT POWER LEVEL MONTH June, 1984 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1
501 11 490 21 496 2
501 12 489 22 497 3
484 13 497 23 496 4
500 14 497 24 437 5
501 15 492 25 478 6
-499 16 496 26 469 7
501 17 496 27 479 8
498 18 496 28 494 9
500 19 496 29 500 10 499 20 490 30 478 31 EQR-28a 501-79) n v
m
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-266 UNIT NAME Point Beach Unit 1 REPORT MONTH June, 1984 COMPLETED C
. Kr TELEPHONE 414/277-2001 e
m 4
C
'M tv o D
o-N oCD Ev C
e-4 e4 to C
-< o ee en e
ou o
mee em Ce No.
Date g
eg y
jjg Licensee Event gg o'g Cause and Corrective Action g
am e
v4 Report No.
m EU To Prevent Recurrence Q-M gmg g
8 i
i 1
3 4
F: Forced Reason:
Method:
Exhibit G-Instruc-S: Scheduled A-Equipment Failure (explain) l-Manual tions for Prepar-B-Maintenance or Test 2-Manual Scram ation of Data Entry C-Refueling 3-Automatic Scram Sheets for LER File l D-Regulatory Restriction 4-Other (explain)
(NUPEG-0161)
E-Operator Training & License Exam F-Administrative 5 Exhibit I-Same AD-28B G-Operational Error (explain)
Source 301-78)
H-Other (explain) x
.m
NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE Docket No.
50-266 Unit Name Point Beach Unit 1 Date July 9, 1984 Completed By C. W. Krause Telephone 414/277-2001 Unit 1 operated at approximately 498 MWe net throughout the period with no significant load reductions.
There has been no indication of primary-to-secondary steam generator leakage.
Significant safety-re' lated maintenance included modifying the steam-driven auxiliary feed pump discharge valves, work on the " fire system water backup to the bearing coolers" modifi-cation on the steam-driven auxiliary feed pumps, and a visual bearing inspection and oil change on the 3D emergency Diesel.
d
e t
OPERATING DATA REFORT DOCKET NO. 5t -:-01 DATE July 5, 1984 COMPLETED BY C. W. FAY TELEPHONE 414 277 2811 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT UNIT 2
. NOTES
- 2. REPORTING PERIOD:
JUNE 1984
- 3. LICENSED THERMAL POWER (MUT): 1518.
- 4. NAMEPLATE RATING (GROSS MUE):
523.8
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.
- 8. IF. CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NOT APPLICABLE
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NOT APPLICABLE
- 10. REASONS FOR RESTRICTIONS, (IF ANY): NOT APPLICABLE THIS HONTH "R TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 720 4,367 104,448
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,341.6 92,769.8
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 8.8 207.1 14 HOURS GENERATOR ON LINE 720.0 4,277.9 91,180.7
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 15.4 198.1
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,083,029 4,375,044 127,269,821
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 369,260 2,153,340 43,113,170
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 352,925 2,057,767 41,058,367
- 19. UNIT SERVICE FACTOR 100.0 98.0 87.3
- 20. UNIT AVAILABILITY FACTOR 100.0 98.3 87.5
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 101.1 97.2 80.0
- 22. UNIT CAPACITY FACTOR (USING DER NET) 98.6 94.8 79.1
- 23. UNIT FORCED OUTAGE RATE 0.0 0.0 1.4
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH):
Five-week refueling outage scheduled to begin on September 28, 1984.
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: NOT SHUTDOWN DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977
DOCKET NO.
50-301 UN:.T NAME Point Beach Unit 2 D A'..'E July 9, 1984 COllPLETED BY C.
W.
Krause TELEPHONE 414/277-2001 AVERAGE DAILY UNIT POWER LEVEL MOUTH June, 1984 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1
495 11 494 21 491 2
496 12 493 22 492 3'
496 13 495 23 491 4
495 14 494 24 468 5
496 15 489 25 495 6
494 16 493 26 483 7
494 17 437 27 489 8
494 18 495 28 493 9
495 19 494 29 493 10 495 20 493 30 482 31 EQR-28a (01-79)
'e UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-301 UNIT NAME Point Beach Unit 2 REPORT MONTH June, 1984 COMPLETED Y C W.
Kr s
TELEPHONE 414/277-2001
'"u c
tH tn o o
M "c
.St Pe en
- e ou o
mee om ce No.
Date g
- g g
jyy Licensee Event gg g'g Cause and Corrective Action e
om e
v.c Report No.
m Eo To Prevent Recurrence Q~
M e t/) C o
2:
U 0
1 F: Forced Reason:
3 Method:
Exhibit G-Instruc-S: Scheduled A-Equipment Failure (explain) l-Manual tions for Prepar-B-Maintenance or Test 2-Manual Scram ation of Data Entry C-Refueling 3-Automatic Scram Sheets for LER File D-Regulatory Restriction 4-Other (explaia)
E-Operator Training & License Exam F-Administrative 5
4D-28B Exhibit I-Same G-Operational Error (explain)
Source (01-78)
H-Other (evnlain)
~
NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE Docket No.
50-301 Unit Name Point Beach Unit 2 Date July 9, 1984 Completed By C. W.
Krause Telephone 414/277-2001 Unit 2 operated at approximately 494 MWe net throughout the period with no significant load reductions.
On June 21, 1984, Unit 2 achieved 43 billion kilowatt hours of generation.
Primary-to-secondary steam generator leakage remains at less than 10 gallons per day.
A Licensee Event Report was submitted regarding the inadvertent safety injection actuation during shutdown described in last month's report.
There was no significant safety-related maintenance performed during this period.
Revision 1 07-09-84 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-301 UNIT NAME Point Beach Unit 2 REPORT MONTH May, 1984 COMPLETED C
kr s
TELEPHONE 414/277-2001 m
4 C
W tD o 4
on N
oc4 Ev c
,a wm c
-et u oe en e
ou o
mee o
as No.
Date D.
5D m
ooe Licensee Event v 'o m
05 Cause and Corrective Action N
$.5
- Report No.
gu g.O To Prevent Recurrence o-gmg g
8 2
840518 S
89.1 B
1 N/A ZZ 5ZZZZZ Conducted corrective maintenance on moisture separator reheater, con-denser waterboxes and incore flux thimble plugs.
~
1 4
F: Force 8 Reason:
Method:
Exhibit G-Instruc-S: Scheduled A-Equipment Failure (explain) l-Manual tions for Prepar-B-Maintenance or Test 2-Manual Scram ation of Data Entry C-Refueling 3-Automatic Scram Sheets for LER File D-Regulatory Restriction 4-Other (explain)
E-Operator Training & License Exam F-Administrative 5
LD-2 8B Exhibit I-Same G-Operational Error (explain)
Source (01-78)
H-Other (explain)
.