Second Supplemental Final Deficiency Rept Re Auxiliary Bldg Fuel Handling Zone Ventilation Fans.Initially Reported on 810506.Corrective Action Will Be Completed by 840917.Delay Due to Extended Cold Weather
ML20092M166
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 06/22/1984
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8407020152
Download: ML20092M166 (1)


Text

(

t 4

TENNESSEE VALLEY AUTHORITY CHATTANOOGA, TENNESSEE 37401 400 Chestnut Street Tower II BLRD-50-438/81-35 BLRD-50-439/81-38 U.S. Nuclear Regulatory Commission

Region II Attn: Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia ~ 30323

Dear Mr. O'Reilly:

BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - AUXILIARY BUILDING FUEL HANDLING ZONE VENTILATION FANS - BLRD-50-438/81-35, BLRD-50-430/81 SECOND

' SUPPLEMENTAL REP 03 The subject deficiency was initially reported to NRC-0IE Inspector

R. Y. Crlenjak on May 6,1981 in accordance with 10 CFR 50.55(e) as NCR BLN BLP 8111. This was followed by our interim reports dated June 5 and December 14,1981; June 11 and September 28, 1982; and February 16,1983, our final report dated August 3,1983 and our supple-mental report dated January 13, 1984.. Below is our second supplemental report.

As-discussed with NRC-0IE Inspector P. E. Fredrickson on June 11, 1984, the date of June 15, 1984 for completion of corrective acticds indicated in our final report would not be met. The extended cold weather of this past

, winter prevented TVA from deenergizing the heating coils, thus the

- necessary modifications could not be performed. The corrective action on this matter will be completed by September. 17, 1984.

If. you have any questions concerning this matter, please get in touch with R.' H.'.Shell at FTS 858-2688..

Very truly yours, TENNESSEE VALLEY AUTHORITY hO L. M. Mills, Manager i

Nuclear Licensing cc: Mr. Richard. C. DeYoung, Director Office of. Inspection and Enforcement

-U.S. Nuclear Regulatory Commission.

Washington, D.C.

20555 Records Center l

Institute of Nuclear Power Operations O N 3t, copy l

1100 circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 s

g g/Q l

1983-TVA 50TH ANNIVERSARY f

An Equal Orportunity Employer i

,..