ML20092L308
Jump to navigation
Jump to search
| ML20092L308 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 06/25/1984 |
| From: | PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| To: | |
| Shared Package | |
| ML20092L297 | List: |
| References | |
| NUDOCS 8406290346 | |
| Download: ML20092L308 (1) | |
Text
v
~
"*Q; TABLE:3.2.B (CONTINUED)
INSTRUMENTATION'THAT INITIATES OR CONTROLS THE CORE AND CONTAINMENT' COOLING SYSTEMS NInimum No.
Of Operable Number of Instru-Instrument Trip Function Trip Level Setting ment Channels Pro-Remarks Channels Per
_vided by Design Trip System (l) 2 per 4 KV Emergency Trans-87% (+/- 5%) of
- 1. Trips emergency Bus former Degraded Rated Voltage.
transformer feed to voltage (Inverse Tests at 2940 4KV emergency bus, time - voltage).
' volts in 30 seconds
- 2. Fast transfer (CV-6 )
(+/- 10 %).
permissive.
I 8406290346 840625 PDR ADOCK 050002{
P