Application for Amend to License DPR-59,proposing TS by Extending Surveillance Test Intervals for Auxiliary Electrical Sys to Support 24 Month Operating Cycles
ML20092H534
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/15/1995
From: William Cahill
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20092H520 List:
References
NUDOCS 9509210068
Download: ML20092H534 (2)


Text

._ - - . - - - - .- .- . . - - - . -- _ . - - .- -- -__ . . _

BEFORE THE UNITED STATES NUCLEAR REGULATORY COMMISSION in the matter of )

NEW YORK POWER AUTHORITY ) Docket No. 50-333 James A. FitzPatrick Nuclear Power Plant )

APPLICATION FOR AMENDMENT TO OPERATING LICENSE The New York Power Authority requests an amendment to the Technical Specifications contained in Appendix A to Facility Operating License No. DPR-59 for the James A.

FitzPatrick Nuclear Power Plant. This application is filed in accordance with Section 10 CFR 50.90 of the Nuclear Regulatory Commission's regulations.

This application for an amendment to the James A. FitzPatrick Nuclear Power Plant Technical Specifications proposes to extend the surveillance test intervals for the auxiliary electrical systems to support 24 month operating cycles. The proposed changes follow the guidance of Generic Letter 91-04. Approval of these changes will eliminate the need to schedule mid-cycle outages to conduct these surveillance tests. This amendment also proposes new commitments for modified performance testing and accelerated performance testing for station batteries.

Surveillance test interval extensions that are justified will be denoted as being performed "every 24 months" or "at least once per 24 monthr." consistent with the guidance provided in NRC Generic Letter 91-04. Other surveillances currently performed "once each operating cycle", "at least once during each operating cycle", "each refueling", or similar notation, that are not being extended at this time will be denoted as being performed "at least once per 18 months."

The signed original of the Application for Amendment to the Technical Specifications is enclosed for filing. Attachments I and lll to this application contain the proposed changes  ;

to the Technical Specifications, and a mark-up of the current Technical Specification i pages. Attachment ll contains the associated Safety Evaluation for the auxiliary electrical j systems. Attachment IV contains References 2 and 4 of the Safety Evaluation. I New York Power Authority

, w$^ '

William J. Cahill, Jr.

Chief Nuclear Officer l

STATE OF NEW YORK  !

COUNTY OF WESTCHESTER l Subscribed and sworn to before me this /44 fay of h 1995.

  1. %1 Nhtary Public KMHLEEN D. gat 1AGHER ,

N888'Y Q g f M 95o92kDO DR hhhoo!33 ouenned mweseetweer PDR Commiseson Expiree Nov.18,1

ATTACHMENT I to JPN-95-044 Proposed Changes to Technical Specification Auxiliary Electrical System Surveillance Test Intervals to Accommodate 24-Month Ooeratina Cveles (JPTS-95-001C) i New York Power Authority JAMES A. FITZPATRICK NUCLEAR POWER PLANT Docket No. 50-333 DPR-59

. . .- - -_ .- _ - - - _ - - - -