Monthly Operating Repts for Jan 1992 for Point Beach Nuclear Plant Units 1 & 2
ML20092D835
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 01/31/1992
From: Peterson D
WISCONSIN ELECTRIC POWER CO.
To:
Shared Package
ML20092D829 List:
References
NUDOCS 9202140303
Download: ML20092D835 (8)


Text

.

,~

o.

l

=

OPERATING DATA REPORT DOCKET NO. 50-301 l

l DATE: January 6, 1992 COMPLETED BY:

D. C. Peterson 2"O G TELEPHONE 414/755-2321, Ext. 361 PJ OPERATING STATUS gg Og

1. UNIT NAME: POINT BEACH NUCLEAR PLANT UNIT 2

. NOTES

2. REPORTING PERIOD: DECEMBER 1991
3. LICENSED THERMAL POWER (MNT):

1518.5

4. NAMEPLATE RATING (GROSS MNE):

523.8 Q

5. DESIGN ELECTRICAL RATING (NET MNE):

497.

5 0.-

6. MAEIMUM DEPENDABLE CAPACITY (GROSS MNE):

509.

khO

7. MAEIMUM DEPENDABLE CAPACITY (NET MNE):

485.

S.'IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NOT APPLICABLE

9. POWER LEVEL TO NHICH RESTRICTED, IF ANT (NET MWE): NOT APPLICABLE
20. REASONS FOR RESTRICTIONS, (IF ANY): NOT APPLICABLE THIS MONTH YR TO DATE CUMULATIVE
11. HOURS IN REPORTING PERIOD 744 8,760 170,209
12. NUMBER OF WOURS REACIOR NAS CRITICAL 733.0 7,645.2 148,729.8
13. REACTOR RESERVE SMUTDOWN HOURS 0.0 0.0 216.7
14. HOURS GENERATOR ON LINE 726.4 7,570.1 146,489.5

{

15. UNIT RESERVE SHUTDOWN NOURS 0.0 0.0 302.2
16. GROSS THERNAL ENERGY GENERATED (MNH) 1,064,971 11,302,748 209,467,157
17. GRDSS. ELECTRICAL ENERGY GENERATED (MNH) 362,530 3,862,120 71,159,380
18. NET ELBCTRICAL ENERGY GENERATED (NNH) 346,784 3,687,712 67,819,778
19. UNIT SERVICE FACTOR 97.6 86.4 86.1
20. UNIT AVAIIABILITY PACTOR 97.6 86.4 86.2
21. UNIT CAPACITY FACTOR (USING 3GC NET) 96.1 86.8 81.5
22. UNIT CAPACITY PACTOR (USING DER NET) 93.8 84.7 80.2
23. UNIT FORCED OUTAGE RATE O.O O.4 1.1
24. SEUTDONWS SCHEDULED OVER NEIT 6 MONTHS (TYPE, DATE, AND DURATIOtt OF EACE):

NONE l'

25. IF SHUTDOWN AT END OF REPORT PERICO, ESTIMATED DATE OF STARTUP: NOT SHUTDONE DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DA*tD SEPTEMBER 22, 1977 L

I

~-

~ ' ' ' ' ~

L __.

./ '

~

OPERATING DATA REPORT DOCKET NO. 50-266 DATE: February 5, 1992 COMPLETED BY:

D. C. Peterson TELEPHONE 414/755-2321, Ext. 361 OPERATING STATUS

1. UNIT MAME: POINT BEACH NUCLEAR PLANT UNIT 1

. NOTES

2. REPORTING PERIOD:

JANUARY 1992

3. LICENSED THERMAL POWER (MNT): 1518.5
4. NAMEPLATE RATING (CROSS MWE):

523.8 l

5. DESIGN ELECTRICAL RATING (NET MWE):

497.

6. MAEIMUM DEFENDABLE CAPACITY (GROSS MWE):

509.

7. MAEIMUM DEPENDABLE CAPACITY (NET MWE):

485.

8. IF CHANGES OCCUR IN CAPiEITT RATINGS (ITEMS NUMBER 3 THPOUGH 7) SINCE LAST REPORT, GIVE REASONS:

NOT APPLICABLE

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NOT APPLICABLE
10. REASONS FOR RESTRICTIONS, (IT ANY): NOT APPLICABLE THIS MONTH TR TO DATE CCMULATIVE
11. HOURS IN REPORTING PERIOD 744 744 186,168
12. NUMBZR OF HOURS REACTOR WAS CRITICAL 744.0 744.0 154,134.5
13. REACTOR RESERVE SHUTDOWN HOURS O.0 0.0 652.7
14. HOURS GENERATOR ON LINE 744.0 744.0 151,172.7
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 846.9
16. CROSS THERMAL ENERGY GENERATED (MWH) 1,126,601 1,126,601 211,776,604
17. GROSS EIMICAL ENERGY GENERATED (MWH) 381,760 381,760 71,485,490
18. NET ELECTRICAL ENERGY GENERATED (MWH) 365,928 365,928 68,115,701
19. UNIT SERVICE FACTOR 100.0 100.0 81.2
20. UNIT AVAILABILITY FACIOR 100.0 100.0 81.7
21. UNIT CAPACITY FACTOR (USING MDC NET) 101.4 101.4 75.1
22. UNIT C'.P.".CITT TA wn (USING DEM NET) 99.0 99.0 73.6
23. UNIT FORCED OUTAGE RATE O.0 0.0 1.7
24. SHUTDOWNS SCHEDU'ED OVER NEET 6 MONTHS (TYPE, DATE, AND DUFJLTION OF EACH) 2 Unit l' refueling and maintenance shutdown scheduled for April 10, 1992 to May 22, 1992: 42 days.

SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: NOT SHUTDOWN MRTED AND FACTORS CALCULATED AS REque.a Ar.u IN NRC LETTER DATED SEPTEMBER 22, 1977

POINT BEACH NUCLEAR rLAST DOCKET NO.

50-266 AVERAGE DATLY UNIT POWER LEVEL UNTT NAME Point Beadt Unit 1 MONTH JANUARY - 1902 DATE rd, w v5_1902 COMPLETED BY D.C.Pemson TELEPHONE 414 M S m i

AVERAGE AVERAGE A%TRAGE DAILY DAILY DAILY l

rowEn tuvEL rower LEVEL rowEntzvEL DAY MWe NET DAY MWe NET DAY MWe SET i

I 493 11 404 21 494 2

494 12 473 22 494 3

493 13 493 23 403 4

492 14 492 24 404 5

457 15 492 25 404

)

6 491 16 403 26 473 7

491 17 492 27 491 8

493 IS 492 28 403 9

495 19 402 29 425 10 491 20 491 30 495 31 405 rarar2sa (DW)

POINT BEACTI NUCLEAR PLANT Docitet No.

Sry_:tw Unit Name Peint Beadt Unit 1 UNIT SIIUTDOWNS AND IDER REDUCTIONS Date Februarv 5. F?2 -

~

Completed By D. C. Petersen REPORT MONTII JANUARY - IW2 Telephone No.

414/755-232L En. 361.

Mettwd of Sh="m8 Na Date Type' Duratum Reastm 1A=n tremee TW

.W Cause and Cemet ve Action 2

i l

l I

l

-I 2

' Method:

  • Exhht G - Instructions

'F: Forced Reason.

L 5: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C-Refueling 3 - Automatic Scram LER file (NUREG4161)

D - Regulatory Restriction 4 - Continuation of l

E - Operator Training &

Previous Shut &mn Ucensing Exam -

5 - Reduced load F-Administrative 6 - Other (explain)

' Exhibit I - Same Source l

l G - Operational Error (explain)

II - Other (explain) l PfW402Rt>

103 W t_

?

r DOCKET NO.

50-266 UNIT HAME Point Beach Unit 1 DATE February 5, 1992 COMPLETED BY D.

C.

Peterson TELEPHoHE 414/755-2321, Ext. 361 Unit 1 operated at approximately 492 MWe net throughout this report period with no significant load reductions.

Unit i experienced two reportable events in accordance with 10 CFR 50.73:

LER 92-001, Unit 1 turbine runback caused by installing control fuse jumper in the wrong breaker cabinet and 92-002, reactor vessel visual inspection not performed.

Safety-related maintenance included the followings replaced broken fusible link lower air deflector on fire barrier; replaced valve stem, plug and cago on the excess letdown heat exchanger shell side outict; and inutalled new bearings and replaced seal on the "D" component cooling water pump.

g OPERATIIIG DATA REPORT DOCKET 300. 50-301 DATE: February 5, 1992 1

1 i

COMPLETED BY:

D. C. Peterson TELEP90M 414/755-2321, Ext. 361 OPERATING STATUS

1. UIIIT NAIE:. FOINT BEACE IIUCLEAR FIAllT UNIT 2

. ISOFES

2. REPOftTING PERIOD: i JAIBUMtf 1992
3. LICEIISED T MINIEL PO MR (MNT): 1518.5
4. mAIIEFLATE MATING. (enoSS nub):

"523.8

5. DESIGII ELECTRICRL' RhTIWS (MT 3W15):

497.

i 6.. EthEIHUBE DEFmarm MPACITY (GROSS 385):

509.

7. MhEIHUN DEPEImh3E2 CRFACITY (IIET 335):

485.

8. IF CEMIGES OCCUR IN ChrhCITY RATINGS (ITERIS IM 3 THROUGH 7) SINCE IAST ItEPORT, GIYg momensmeg IIOT AFFLICASE2
9. POIIER I2 VEL TO WIIIM DESTRICTED, IF. AIIT (IRT IEEE):.ISOT APPLICABLE

- 10. memenang yon ngSTRICTICIIS, ' (IF AIIY):..IIOT APPLIchELE

'THIS MOIITH TR TO DATE CUIIUEATIVE

11. NOURS IN BEFORTIIIG PERIOD-744 744 170,953 12.. IIGIMER OF MDURS REAC3OR IIES CRITICAL 744.0 744.0 149,473.8 13.- REACTUR RESEIETE sWUTDomi IBOUIIS 0.0 0.0 216.7
14. EDUIts GEIWARIOR CII LIM 744.0

'744.0 147,233.5 l.

15. UBIIT RESEUITE SIIUTDOISI IIDURS 0.0..

0.0 302.2

16. GIIOSS TIBIWIhL EIIEEIGT eEIBIIATED (MINI) 1,127,958 1,127,958 210,595,115
17. enOSS ELECTRIchL ENERGY GENERATED (BWIH) -

357,730.

387,730 71,547,110

18. NET EEECTRICAL EIERGY GENEftATED (38085) 371,749 371,749 68,191,527
19. DIBIT.SEIIVICE FACTOR 100.0 100.0 86.1

' 20. UNIT AVAIIABILITY FACTOR 100.0 100.0 86.3 21..UIIIT ChrACITY FAC5OR (USIIIG Isc NET)

-103.0 103.0 81.6

~ 22. UIIIT CAPACITY FACTOR.(USIIIG DER NET) 100.5 100.5 80.3 23..UIIIT FORCED OUTAGE RATE O.0 0.0 1.1

24. SHUTDOINBS SCHEDUI2D OVER NEIT 6.MOIITHS (TYPE,JDATE, AND DURATION OF EACH):

IIOISE

25. IF'.SHUTDOINE AT'EIID OF REPORT PERIOO, ESTIMATED DATE OF STARTUP ISOY SHUTDOIIN DATA REPORTED AND FACTORS CALCULATED AS REQUESTED: IN IIRC LETTER DATED SEPTEMBER 22,.1977

o

~,

POINT BEACII NUCLEAR FI_ ANT DOCKET NO.

50-301 AVERAGE DAILY UNIT PtDVER LEVEL UNTT NAME Point Beacit Unit 2 MONTII JANUARY - IW2 -_

DATE rd,sv5.tw2 COMPLETED BY D. C. Peterson TELEfHONE 414/NS-2321 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET _

DAY MWe NET DAY MWe NET 1

501 11 MS 21 501 2

501 12 493 22 501 3

500 13 500 23 90 24 500 4

500 14 50rs 5

500 15 496 25 500 6

499 16 500 26 431 7

500 17 500 27 498 8'

501 18' 499 23 4W 9

505 19 500 29 MI 10 4%

20 499 30 500 31 M1 PDF-0028a (03-90)

,- ~,

POINT BEACli NUCLEAR PLANT Docket No.

50-301 4

Unit Name Point BerJt Unit 2 UNIT Sl!UTDOWNS AND POWER REDUCTIONS Date Februarv 5.1*C

  • Completed By D. C Peterson REPORT MONT11 JANUARY-1972 Telephone No_

414/755-232L Ett. 36L Methed c(

Shutt +pg No.

Date "

Type' Duration Remsca gy,,

g,rensee Bent System Coreponent Cause end Cornetwe Action r

fhrs)

L m' +'

Ru- - No.

Cd' Crv3e' To Pm Recumace l

l

'F: Forced

' Reason:

' Method:

' Exhibit G - Instructions S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C - Refueling 3 - Automatic Scram LER file (NUREG-0161)

D - Regulatory Restriction 4 - Continuation of E - Operator Training &

Previous Shutdown Licensing Exam 5 - Reduced Load F-Administrative 6 - Other (explain)

' Exhibit I - Same Source G - Operational Error (explain)

H - Other (explain)

PDF4r8b (0190)