|
---|
Category:MONTHLY OPERATING ANALYSIS REPORT
MONTHYEARBVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station BVY-98-068, Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station BVY-98-053, Monthly Statistical Rept for Mar 1998 for Vynp1998-03-31031 March 1998 Monthly Statistical Rept for Mar 1998 for Vynp ML20248L1581998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Vermont Yankee Nuclear Power Station ML20217M7801998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Vynp Station ML20198L6111997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Vynp Station BVY-97-161, Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station1997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station BVY-97-145, Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station BVY-97-126, Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station1997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station BVY-97-111, Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station1997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station BVY-97-098, Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station1997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station BVY-97-088, Monthly Operating Rept for June 1997 for Nynps1997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Nynps BVY-97-074, Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station1997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station BVY-97-059, Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station1997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station BVY-97-042, Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station1997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station BVY-97-033, Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station1997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station BVY-97-021, Monthly Operating Rept for Jan 1997 for VYNPS1997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for VYNPS BVY-97-001, Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station1996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station BVY-96-154, Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station1996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station BVY-96-138, Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station BVY-96-114, Monthly Operating Rept for Sept 1996 for Vynp1996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Vynp BVY-96-103, Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station1996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station BVY-96-095, Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station1996-07-31031 July 1996 Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station BVY-96-087, Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station BVY-96-072, Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station1996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station BVY-96-057, Monthly Operating Rept for Apr 1996 for VT Yankee Power Station1996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for VT Yankee Power Station BVY-96-041, Monthly Operating Rept for Mar 1996 for Vynp1996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Vynp BVY-96-018, Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station1996-02-29029 February 1996 Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station BVY-96-009, Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station1996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station BVY-96-001, Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station ML20095F6601995-11-30030 November 1995 Last Page of Monthly Operating Rept for Nov 1995 for Vermont Yankee BVY-95-131, Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station1995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station BVY-95-118, Monthly Operating Rept for Oct 1995 for Vynp1995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Vynp BVY-95-106, Monthly Operating Rept for Sept 1995 for Vynp1995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Vynp ML20092F5901995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Vermont Yankee Nuclear Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L8831999-10-21021 October 1999 Safety Evaluation Supporting Proposed Alternatives to Code Requirements Described in RR-V17 & RR-V18 ML20217G2041999-10-13013 October 1999 Safety Evaluation Supporting Amend 179 to License DPR-28 BVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With ML20212C2551999-09-17017 September 1999 Safety Evaluation Supporting Amend 175 to License DPR-28 BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-109, Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 9908311999-08-19019 August 1999 Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 990831 BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with ML20209J0081999-07-14014 July 1999 Special Rept:On 990615,diesel Driven Fire Pump Failed to Achieve Rated Flow of 2500 Gallons Per Minute.Pump Was Inoperable for Greater than 7 Days.Corrective Maint Was Performed to Reset Pump Lift Setting BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With ML20196G5071999-06-23023 June 1999 Vynp Assessment of On-Site Disposal of Contaminated Soil by Land Spreading BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With ML20206E8741999-04-29029 April 1999 SER Determined That Flaw Evaluation Meets Rules of ASME Code & Assumed Crack Growth Rate Adequate for Application ML20206D9301999-04-27027 April 1999 1999 Emergency Preparedness Exercise 990427 Exercise Manual (Plume Portion) ML20205S4211999-04-16016 April 1999 Non-proprietary Version of Revised Page 4-3 of HI-981932 Technical Rept for Vermont Yankee Spent Fuel Pool Storage Expansion ML20205K7581999-04-0707 April 1999 Safety Evaluation Supporting Alternative Proposal for Reexamination of Circumferential Welds with Detected Flaw Indications in Plant RPV BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With ML20205F6631999-03-0404 March 1999 Jet Pump Riser Weld Leakage Evaluation BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With ML20205P8241999-02-28028 February 1999 Rev 2 to Vermont Yankee Cycle 20 Colr ML20203H9881999-02-18018 February 1999 SER Accepting Alternative to 10CFR50.55a(g)(6)(ii)(A) Augmented Reactor Vessel Exam at Vermont Yankee Nuclear Power Station.Technical Ltr Rept Encl ML20203A6951999-02-0404 February 1999 Revised Rev 2,App B to Vermont Yankee Operational QA Manual (Voqam) ML20199K7151999-01-21021 January 1999 Corrected Safety Evaluation Supporting Amend 163 Issued to FOL DPR-28.Pages 2 & 3 Required Correction & Clarification ML20199K6991999-01-20020 January 1999 Safety Evaluation Concluding That Request to Use YAEC-1339, Yankee Atomic Electric Co Application of FIBWR2 Core Hydraulics Code to BWR Reload Analysis, at Vermont Yankee Acceptable ML20199L5951999-01-14014 January 1999 Safety Evaluation Accepting Licensee Proposed Alternative to Code Requirement,Described in Rev 2 to Pump Relief Request RR-P10 Pursuant to 10CFR50.55a(a)(3)(i) BVY-99-071, Corp 1998 Annual Rept. with1998-12-31031 December 1998 Corp 1998 Annual Rept. with BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station ML20198H5481998-12-23023 December 1998 Rev 2 to Vermont Operational QA Manual,Voqam ML20196H8641998-12-0101 December 1998 Cycle 19 Operating Rept BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With ML20195C4161998-11-0909 November 1998 SER Accepting Request That NRC Approve ASME Code Case N-560, Alternative Exam Requirement for Class 1,Category B-J Piping Welds BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With ML20155B6471998-10-26026 October 1998 Safety Evaluation Accepting Jet Pump Riser Insp Results & Flaw Evaluation,Conducted During 1998 Refueling Outage ML20154N0891998-10-16016 October 1998 Rev 1 to Vermont Operational QA Program Manual (Voqam) ML20154B6951998-10-0101 October 1998 SER Re Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Vermont Yankee Nuclear Power Station BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With ML20239A1361998-09-0202 September 1998 SER Re License Request for NRC Review & Concurrence W/Changes to NRC-approved Fire Protection Program BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With ML20151U0361998-08-28028 August 1998 Non-proprietary Rev 1 to Holtec Rept HI-981932, Vermont Yankee Nuclear Power Station Spent Storage Expansion Project ML20237E9221998-08-20020 August 1998 Vynp 1998 Form NIS-1 Owners Summary Rept for ISI, 961103-980603 BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station ML20205F6491998-07-31031 July 1998 Rev 1 to GE-NE-B13-01935-02, Jet Pump Assembly Welds Flaw Evaluation Handbook for Vermont Yankee ML20236G0011998-06-30030 June 1998 Individual Plant Exam External Events BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station ML20248C5081998-05-31031 May 1998 Rev 2 to 24A5416, Supplemental Reload Licensing Rept for Vermont Yankee Nuclear Power Station Reload 19 Cycle 20 ML20248C4951998-05-31031 May 1998 Rev 1 to Vermont Yankee Nuclear Power Station Cycle 20 Colr BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station ML20247J8341998-05-31031 May 1998 Peak Suppression Pool Temp Analyses for Large Break LOCA Scenarios, for May 1998 ML20247G4001998-05-12012 May 1998 Interview Rept of Ej Massey ML20247E6351998-04-30030 April 1998 Rev 1 to GE-NE-B13-01935-LTR, Jet Pump Riser Welds Allowable Flaw Sizes Ltr Rept for Vermont Yankee 1999-09-30
[Table view] |
Text
,
TERMONT YANKEE- j NUCLEAR POWER CORPORATION
- s. ;
~
>% % P.O. Box 157, Governor Hunt Road Vernon, Vermont 05354-0157 J (802) 257-7711 :
I '. -
August 10, 1995 VY-RCE-95-018 BVY-95-82 ;
I U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555
Reference:
a) License No. DPR-28 (Docket No. 50-271) i In accordance with section 6.7.A.3 of the Vermont Yankee ,
Technical Specifications, submitted herewith is the Monthly l Statistical Report for the Vermont Yankee Nuclear Power Station for the month of July, 1995. j l
Sincerely, Vermont Yankee. Nuclear Power Corp. '
Robert J. 3 nczyk Plant. Manager cc: USNRC Region I Administrator USNRC Resident Inspector - VYNPS USNRC Project Mananger - VYNPS E
6
.o g- e .*>e 2 J U 2. : w) 9508150179 950731 /
{DR ADOCK 05000271 PDR 8 .
j
4-- -; -- ~ . - -
9 i
hl
.i
-j
[ .)
I
-.j
~!
?
VERMONT YANKEE NUCLEAR POWER STATION -
's i
MONTHLY STATISTICAL REPORT 95-07' i .
FOR THE MONTH OF JULY 1995 '!
i
, .l
-f
~l t
- (
1 t
b DP 0411 Rev. 6 ';
Page 1 of 1 l t
T s
)
)
_ .I
')
1 l
1
OPERATING DATA REPORT-
. DOCKET NO.50-271 DATE 950810 1 COMPLETED BY G.A. WALLIN !
TELEPHONE (802)258-5414' l OPERATING STATUS
- 1. Unit Name: Vermont Yankee
- 2. Reporting Period: Julv NOTES:
- 3. Licensed Thermal Power (MWt):1593
- 4. Nameplate Rating (Gross MWe): 540
- 5. Design Electrical Rating (Net MWe): 122
- 6. Maximum Dependable Capacity (Gross MWe): 535 7._ Maximum Dependable Capacity (Net MWe): 510
- 8. If changes, occur in capacity ratings (Itams Number 3 through 7) since last report, give reasons:
- 9. Power level to which restricted, if any(Net MWe): N/A
- 10. Reasons for restrictions, if any: N/A This Month Yr-to-Date Cumulative'
- 11. Hours in Reporting Period 744.00 5087.00 198671.00
- 12. Number Of Hours Reactor was Critical 744.00 4000.96 163864.62 ,
- 13. Reactor Reserve Shutdown Hours 0.00 0.00 0.00 -
- 14. Hours Generator On-Line 744.00 3951.45 160668.56
- 15. Unit Reserve Shutdown Hours 0.00 0.00 0.00.
- 16. Gross Thermal Energy Generated (MWH) 1181447.35 6191916.60 240361791.60
- 17. Gross Electrical Energy Generated 393819.00 2094331.00 80131683.00
- 18. Net Electrical Energy Generated (MWH) 371194.00 1996413.00 76158987.00
- 19. Unit Service Factor 100.00 77.68 80.87
- 20. Unit Availability Factor 100.00 77.68 80.87
- 21. Unit Capacity Factor (Using MDC Net) 97.83 76.95 75.17
- 22. Unit Capacity Factor (Using DER Net) 95.58 75.18' 73.44'
- 23. Unit Forced Outage Rate 0.00 0.00 4.85
- 24. Shutdowns scheduled over next 6 months (Type, Date, and Duration of.
Each: N/A
- 25. If shut down at end of report period, estimated date of startup:N/A
- 26. Units In Test Status (prior to commercial operation): N/A Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION VYDPF 0411.01 l i
DP 0411 Rev. 6 Pege 1 of 1 RT No. 13.F01.19F- !
1 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-271
. UNIT Vermont Yankee DATE 950810 COMPLETED BY G.A. WALLIN-TELEPHONE (802)258-5414 MONTH Julv DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net)
- 1. 499 17. 504
- 2. 500 18. 502
- 3. 505 19. 509
- 4. 503 20. 504
- 5. 500 21. 498
- 6. 497 22. 501
- 7. 498 23. 498
- 8. 499 24. 499
- 9. 503 25. 487
- 10. 501 26. 492
- 11. 479 27. 501
- 12. 501 28. 502
- 13. 497 29. 497
- 14. 494 30. 505
- 15. 490 31. 301
- 16. 499 INSTRUCTIONS:
On this format, list the average daily unit power level in MWE-Net for each day in the reporting month. Compute to the nearest whole megawatt.
VYDPF 0411.02 DP 0411 Rev. 6 Page 1 of 1 !
RT No. 13.F01.18V _
UNIT SHUTDOWNS AND POWER REDUCTIONS
- REPORT MONTH JULY DOCKET NO 50-271 UNIT NAME Vermont Yankee" DATE 950810 COMPLETED BY G.A. Wal-lin TELEPHONE (802)258-5414-1 2 3 4 5 No. Date Type Duration Reason Method of License System Component 'Cause and. Corrective (hours) Shutting Event Code Code Action.to Prevent Down Report / Recurrence Reactor 95-05 950711 S 0.00 B,H* 4 N/A RB' CONROD Bypass valve tests; Power MSIV full closure test Reduction and a rod pattern exchange 1 F: Forced 2_ Reason: 3 Method: 4 Exhibit G- Instructions S: Scheduled . A-Equipment Failure-(Explain)' 1 -- Manual for, Preparation of Data B-Maintenance or Test 2 - Manual Scram Entry Sheets for License C-Refueling 3 - Automatic Scram Event Report (LER) File
'D-Regulatory Restriction 4 - Other (Explain) (NUREG 0161)-
E-Operator Training'and
! License Examination 5 Exhibit I - Same Source VYDPF 0411.03 F-Administrative DP 0411 Rev. 6 .G-Operational-Error (Explain)
Page 1 of 1 *H-(Explain) - Rod Pattern Exchange i
l l
l
I
^*
. . . . )
'e .. ,
i' DOCKET NO. 50-271 DATE 950810 I t .
. COMPLETED BY G.A. WALLIN
, TELEPHONE (802)258-5414 i Li REPORT MONTH Julv l
SUMMARY
-OF OPERATING EXPERIENCES !
-Hiahliahts !
.1 Vermont Yankee operated at 99.7% of rated thermal power for the month. ,
Gross electrical generation was 393,819 MWHe or 96.9% design electrical
. capacity.
j Operatina Summary The following is a chronological description of plant operations including :
other pertinent items of interest for the month: l At the beginning of the reporting period the plant was operating at 99.9%
of rated thermal power. >
t l
950711 At 0100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br />, initiated a power reduction to minimum recirculation' j flow to perform turbine bypass valve tests, MSIV full closure- i tests, and a rod pattern exchange. (See Unit Shutdowns and Power ,
Reductions) '
950711 At 0230 hours0.00266 days <br />0.0639 hours <br />3.80291e-4 weeks <br />8.7515e-5 months <br />, initiated turbine bypass valve testing. i 950711 At 0240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br />, completed turbine bypass valve testing.
950711 At 0247 hours0.00286 days <br />0.0686 hours <br />4.083995e-4 weeks <br />9.39835e-5 months <br />, initiated MSIV fast closure testing. j i
950711 At 0252 hours0.00292 days <br />0.07 hours <br />4.166667e-4 weeks <br />9.5886e-5 months <br />, completed MSIV fast closure testing.
950711 At 0255 hours0.00295 days <br />0.0708 hours <br />4.21627e-4 weeks <br />9.70275e-5 months <br />, initiated a rod pattern exchange.
950711 At 0316 hours0.00366 days <br />0.0878 hours <br />5.224868e-4 weeks <br />1.20238e-4 months <br />, completed the rod pattern exchange.
950711 At 0400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br />, initiated a return to full power..-
j At the end of the reporting period the plant was operating at 99.9% of rated thermal power.
VYDPF 0411.04 DP 0411 Rev. 6 Page 1 of 1 RT No. 13.F01.18X