MONTHYEARML20217G6971999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Calvert Cliffs Npp,Units 1 & 2.With ML20212A4441999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Ccnpp,Units 1 & 2. with ML20210S6091999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ccnpp,Units 1 & 2. with ML20209F1721999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Calvert Cliffs Npp.With ML20195K2811999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ccnpp,Units 1 & 2. with ML20206R5871999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ccnpp,Units 1 & 2. with ML20205P5441999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20207M8321999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Calvert Cliffs Nuclear Power Plant.With ML20199E2931998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Calvert Cliffs Npp. with ML20198B2631998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20195E5281998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Calvert Cliffs Nuclear Power Station,Units 1 & 2.With ML20154M5841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Calvert Cliffs Nuclear Plant,Units 1 & 2.With ML20151Y1191998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Calvert Cliffs Nuclear Power Plant Units 1 & 2.With ML20237B9371998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Calvert Cliffs Nuclear Power Plant ML20236R0881998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20249A7711998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ccnpp,Units 1 & 2 ML20247H5661998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Ccnpp ML20216G4601998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20248L3641998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20202G6611998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20198N9441997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Calvert Cliffs Nuclear Power Plant,Units 2 & 3 ML20203H3081997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Calvert Cliffs Nuclear Power Plant ML20199D0801997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20198J6631997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Calvert Cliffs Nuclear Power Plant ML20210U7031997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Ccnpp ML20210L0671997-07-31031 July 1997 Monthly Operating Repts for July 1997 for Ccnpp ML20149E2301997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Calvert Cliffs Nuclear Power Plant ML20148L1761997-05-31031 May 1997 Monthly Operating Repts for May 1997 for CCNP ML20141F1401997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20137W8781997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Calvert Cliffs Nuclear Power Plant ML20136J4941997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20134M2891997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20133N1031996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20132D1141996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Calvert Cliffs Nuclear Power Plant,Unit 1 & 2 ML20134L6621996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Calvert Cliffs Nuclear Power Plant Unit 1 & 2 ML20128Q8011996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Calvert Cliffs Npp,Units 1 & 2 ML20117N2171996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20116M6701996-07-31031 July 1996 Monthly Operating Repts for Jul 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20115F7281996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20112J1291996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20112A2421996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20107C1831996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20101D7831996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Ccnpp ML20149K8721996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Ccnpp ML20096D7031995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Ccnpp Units 1 & 2 ML20095H3741995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Calvert Cliffs Nuclear Power Plant Units 1 & 2 ML20096D7171995-11-30030 November 1995 Rev to Monthly Operating Rept for Nov 1995 for Ccnpp Unit 2 ML20094M0161995-10-31031 October 1995 Monthly Operating Repts for Oct 1995 for Calvert Cliffs Nuclear Plant ML20093G5881995-09-30030 September 1995 Monthly Operating Repts for Sept 1995 for Calvert Cliffs Nuclear Power Plants Units 1 & 2 ML20092G3521995-08-31031 August 1995 Monthly Operating Repts for Aug 1995 for Calvert Cliffs Nuclear Power Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217G6971999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Calvert Cliffs Npp,Units 1 & 2.With ML20216J8731999-09-10010 September 1999 Rev 52 to QA Policy for Calvert Cliffs Nuclear Power Plant ML20212A4441999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Ccnpp,Units 1 & 2. with ML17326A2011999-08-23023 August 1999 LER 99-004-00:on 990724,reactor Tripped Due to Main Transformer Bushing Flashover.Plant Was Brought to SS & Components Were Tested & Performed Satisfactorily.With 990823 Ltr ML20210S6091999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ccnpp,Units 1 & 2. with ML20210N6001999-07-27027 July 1999 ISI Summary Rept for Calvert Cliffs Unit 2. Page 2 of 3 in Encl 1 of Incoming Submittal Not Included ML20210B7941999-07-15015 July 1999 SER Denying Licensee Request for Changes to Current Ts,Re Deletion of Tendon Surveillance Requirements for Calvert Cliffs LD-99-039, Part 21 Rept Re Defect of Abb 1200A 4kV Vacuum Breakers. Initially Reported on 990625.Defect Results in Breaker Failing to Remain in Closed Position.Root Cause Evaluation & Corrective Action Plan Being Developed.Licensee Notified1999-06-30030 June 1999 Part 21 Rept Re Defect of Abb 1200A 4kV Vacuum Breakers. Initially Reported on 990625.Defect Results in Breaker Failing to Remain in Closed Position.Root Cause Evaluation & Corrective Action Plan Being Developed.Licensee Notified ML20209F1721999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Calvert Cliffs Npp.With LD-99-035, Part 21 Rept Re Abb 1200A 4KV Vacuum Breakers Performing Trip Free Operation When Close Signal Received by Breaker. Defect Results in Breaker Failing to Remain in Closed Position.Root Cause & CAP Being Developed1999-06-25025 June 1999 Part 21 Rept Re Abb 1200A 4KV Vacuum Breakers Performing Trip Free Operation When Close Signal Received by Breaker. Defect Results in Breaker Failing to Remain in Closed Position.Root Cause & CAP Being Developed ML20196C6981999-06-21021 June 1999 Safety Evaluation Concluding That Use of ASME Section XI Code Including Summer 1983 Addenda as Interim Code for Third 10-year Insp Interval at Calvert Cliffs Units 1 & 2 Until Review of 1998 Code Completed,Would Be Acceptable ML20195K2811999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ccnpp,Units 1 & 2. with ML20206R5871999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ccnpp,Units 1 & 2. with ML20195B3891999-04-30030 April 1999 0 to CENPD-279, Annual Rept on Abb CE ECCS Performance Evaluation Models ML20205N2951999-04-13013 April 1999 Special Rept:On 990314,fire Detection Sys Was Removed from Svc to Support Mod to Replace SRW Heat Exchangers in Unit 2 SRW Room During Unit 2 Refueling Outage.Contingency Measure 15.3.5.A.1 Will Continue Until Fire Detection Sys Restored ML20210T5211999-04-0101 April 1999 Rev 0 to Ccnpp COLR for Unit 2,Cycle 13 ML20205P5441999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20204H6471999-03-21021 March 1999 SER Re License Renewal of Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20207M8321999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Calvert Cliffs Nuclear Power Plant.With ML20203D4311999-02-0505 February 1999 Safety Evaluation Accepting Procedure Established for long-term Corrective Action Plan Related to Containment Vertical Tendons ML20199G4671999-01-20020 January 1999 SER Accepting USI A-46 Implementation for Plant ML20206Q3221999-01-11011 January 1999 Special Rept:On 981226,wide Range Noble Gas Effluent RM Was Removed from Operable Status.Caused by Failure of mid-range Checksource to Properly Reseat.Completed Maint & post-maint Testing & RM Was Returned to Operable Status on 990104 ML20207L0451999-01-0808 January 1999 Cost-Benefit Risk Analyses:Radwaste Sys for Light Water Reactors ML20199F4781999-01-0808 January 1999 Safety Evaluation Concluding That Bg&E Performed Appropriate Evaluations of Operational Configurations of safety-related power-operated Gate Valves to Identify Valves Susceptible to Pressure Locking.Concludes GL 95-07 Actions Were Addressed ML20198S7591999-01-0707 January 1999 SER Accepting Quality Assurance Program Description Change for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20207M2281998-12-31031 December 1998 1998 Annual Rept for Bg&E. with ML20199E2931998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Calvert Cliffs Npp. with ML20206R9911998-12-0808 December 1998 Rept of Changes,Tests & Experiments (10CFR50.59(b)(2)). with ML20198B2631998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20195H1001998-11-16016 November 1998 Safety Evaluation of First Containment Insp Interval Iwe/Iwl Program Alternative ML20196E2211998-10-31031 October 1998 Non-proprietary Rev 03-NP to CEN-633-NP, SG Tube Repair for Combustion Engineering Designed Plant with 3/4 - .048 Wall Inconel 600 Tubes Using Leak Limiting Alloy 800 Sleeves ML20195E5281998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Calvert Cliffs Nuclear Power Station,Units 1 & 2.With ML20154Q7191998-10-21021 October 1998 Special Rept:On 980923,unit 1 Wrngm Was Removed from Operable Status.Caused by Failure of Process Flow Transducer.Completed Maint to Remove Process Flow Transducer Input to Wrngm Microprocessor & Completed Formal Evaluation ML20154G3931998-10-0505 October 1998 Safety Evaluation Concluding That Flaw Tolerance Evaluation for Assumed Flaw in Inboard Instrument Weld of Pressurizer Meets Rules of ASME Code ML20154M5841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Calvert Cliffs Nuclear Plant,Units 1 & 2.With ML20153C2571998-09-18018 September 1998 Special Rept:On 980830,wide Range Noble Gas Monitor (Wrngm) Channel Was Removed from Operable Status.Caused by Need to Support Performance of Required 18-month Channel Calibr.Will Return Wrngm to Operable Status by 980925 ML20153C1091998-09-18018 September 1998 Part 21 Rept Re Defective Capacity Control Valves.Trentec Personnel Have Been in Contact with Bg&E Personnel Re Condition & Have Requested Potentially Defective Valves ML20151U5441998-09-0404 September 1998 Bg&E ISI Summary Rept for Calvert Cliffs ML20151T5281998-09-0101 September 1998 Special Rept:On 980819,declared Rv Water Level Monitor Channel a Inoperable.Caused by Failure of Three Heated Junction Thermocouples (Sensors) in Lower Five Sensors. Channel a & B Rv Water Level Probes Will Be Replaced ML20151Y1191998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Calvert Cliffs Nuclear Power Plant Units 1 & 2.With ML20237D4981998-08-19019 August 1998 Safety Evaluation Accepting Licensee Request for Extension of Second ten-year Inservice Insp Interval ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML20237B9371998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Calvert Cliffs Nuclear Power Plant ML20237D5941998-07-22022 July 1998 Rev 2 to Ccnpp COLR for Unit 2,Cycle 12 ML20236L7521998-07-0606 July 1998 Safety Evaluation Granting Bg&E 980527 Request for Relief from Requirement of Section IWA-5250 of ASME Code for Calvert Cliffs Unit 2.Alternatives Provide Reasonable Assurance of Operational Readiness ML20236F7791998-06-30030 June 1998 Safety Evaluation Authorizing Request for Temporary Relief from Requirement of Subsection IWA-5250 of ASME Code,Section XI for Plant,Unit 1 ML20236R0881998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20236X3101998-06-19019 June 1998 Rev 1 to Calvert Cliffs Nuclear Power Plant COLR for Unit 2,Cycle 12 ML20249A9571998-06-15015 June 1998 Special Rept:On 980430,fire Detection Sys Was Removed from Svc to Support Mod to Purge Air Sys 27-foot Elevation & 5-foot Elevation East Piping Penetration Rooms.Installed Temporary Alteration & Returned Fire Detection Sys to Svc ML20249A7711998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ccnpp,Units 1 & 2 1999-09-30
[Table view] |
Text
.
B ALTIMORE I GAS AND
( ELECTRIC CHARLES CENTER e P.O. BOX 1475
- BALTIMORE. MARYLAND 21203-1475 H E DENTON GENEF4At MANAGEH cal. VERT CLIFFS November 13,1991 U. S. Nuclear Regulatory Commission Washington, DC 20555 NITENTION: Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 October 1991 Operatine Data Reports Gentlemen:
The subject reports are being sent to you as required by Technical Specification 6.9.1.6.
Should you have any further questions regarding this matter, please contact Mr. Bruce Mrowca at (410) 260 3989.
M yours,
/o N c u
RED /LBS/bjd Attachments cc: D. A. Brune, Esquire J. E. Silberg, Esquire R. A. Capra, NRC D. G. Mcdonald, Jr., NRC T. T. Martin, NRC A. G. Howe, NRC R. I. McLean, DNR J. II. Walter, PSC R. A. Hartfield, NRC J. Wheelock, INPO o gogs24 *'
am o _< \
\
9111210058 911031 FDR ADOCK 05000317 R PDR f$$E
't o
oooo********************************+'**************************************
UNIT =1 OPERATING DATA REPORT o**o************************************************************************-
Docket No. 50-317 November 13, 1991 '
Prepared by. Leo Shanley Telephone:(410)260-6744 OPERATING STATUS 1.. UNIT 1NAME Calvert Cliffs Unit 1 2.-REPORTING PERIOD OCTOBER 1991
- 3. LICENSED. THERMAL POWER-(MWT). 2700
-4.-NAMEPLATE RATING (GROSS MWe)- 918
- 5. DESIGN. ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM DEPENDABLE CAP'Y (GROSS MWo) 860 7.fMAXIMUM DEPENDABLE' CAP'Y (NET MWe) 825
- 8. CHANGE-IN CAPACITY. RATINGS none
-9. POWER LEVEL TO WHICH RESTRICTED n/a 10.' REASONS FOR RESTRICTIONS n/a Cumulative This month Year-to-Date. to Date ill.. HOURS-IN REPORTING PERIOD 745 7,296 144,493
- 12. NUMBER 10F HOURS REACTOR WAS-CRITICAL 711.5 5,412.5 101,929.3
- 13. REACTOR. RESERVE' SHUTDOWN HOURS 0.0 0.0 3,019.4 114._ HOURS GENERATOR ON LINE 701.8 5,374.0 99,663.8
- 15. UNIT RESERVE SHUTDOWN ~ HOURS 0.0 0.0 0.0
- 16. GROSS' THERMAL ENERGY GENERATED (MWH) 1,804,452 13,975,042.251,005,756 17.1 GROSS-ELECTRICAL ENERGY GEN'TED(MWH) 590,088 4,606,131- 83,436,898
'18. NET, ELECTRICAL ENERGY. GENERATED (MWH) _564,570 4,411,616 79,301,793-
'19. UNIT SERVICE FACTOR 94.2 73.7 69.0
- 20. UNITLAVAILABILITY FACTOR 94.2 73.7 69.0.
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 91.9 73.3 66.5-
-22. UNIT CAPACITY FACTOR-(USING DER NET) 89.7 71.6 65.0
- 23. UNIT FORCED OUTAGE RATE 5.8 11.4 9.5
- 24. SHUTDOWNS' SCHEDULED OVER THE NEXT SIX MONTHS-(TYPE, .DATE AND DURATION):
Refuel / Test,: March 6, 1992_for;77 days 225.[IF SHUTDOWN AT-END OF1 REPORT PERIOD, ESTIMATED'DATE OF START-UP:
N/A
UNIT SIIUTDOWNS AND POWER REDUCTIONS -
DOCKET NO. 50-317 UNITNAME Cahrrt ClifTwU1 DATE November 13,1991' '
COMPLETED BY Leo Shanley TELEPHONE (410126fL6744 REPORT MONTII October 1991 METilOD OF SiltTITING LICENSEE CAUSE & CORRECHVE DURATION DOWN EVENT SYSTEM COMPONENT ACTION TO NO. DAlli TYPEI (IIOURS) REASON 2 REACTOR 3 REPORT # CODE4 CODES PRLNENT RECURRENCE 91-08 911001 F 43.2 A 3 91-003 CH XXXXXX 1) Reactor Trip due to low Steam Generator (SG) water level
- 2) A loose fuse (due to a bent fuse clip) in the power supply to 12 Feed Regulating Valve dP controller and 12 SG Feed Pump turbine speed controller caused a rapid . [
reduction in ft.ed flow, resulting in low '
SG levels. i
- 3) Surveyed other fuse holders for similar problems. Training win be amended to include instruction on proper fuse installation and ;
remc val :
i I
i L
1 F: Forced 2 Reason: 3 Method: 4 Exhibit F- Instructions S: Scheduled A-Equipment Failure 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram- Entry Sheets for License C-Refueling 3-Automatic Scrant Event Report (LER) File D-Regulatory Restriction 4 Continued (NUREG-0161) ;
E-Operator Training & License Examination 5-Reduced Lead ,
F-Administrative 9-Other 5 Exhibit H - Same Source G-Operational Error e H-Other
AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-317 Calvert Cliffs Unit No. 1 November 13, 1991 Completed by Leo Shanley Telephone: (410) 260-6744 OCTOBER 1991 Average Daily Power Level Average Daily Power Level Day (MWo-Net) Day (irde-Net) 1 328 17 854 2 0 18 853 3 97 19 849 4 373 20 851 5 756 21 851 6 781 22 853 7 838 23 853 8 839 24 853 9 818 25 852 10 842 26 853 11 832 27 852 12 802 28 853 13 849 29 854 14 849 30 853 15 849 31 852 16 851
DOCKET 150-317 CALVERT CLIFFS. UNIT 1 November 13,1991 -
SUMMARY
OF OPERATING EXPERIENCE October 1991 The unit began the month at 93% power (760 MWe) awaiting repairs to 13A Waterbox Inlet MOV.
An automatic reactor trip occurred at IM8 on October 1 due to low Steam Generator (SG) water levels.12 Feed Regulating Vahe differential pressure controller and 12 SG Feed Pump turbine speed controller lost power resulting in a rapid reduction in feed flow. The reactor was taken critical at 2020 on October 2 and the generator was paralleled to the grid at 0600 on October 3. Power was held at 30% (150 MWe) until 1030 on October 4 to correct SG Chemistry and troubleshoot problems with #2 and #4 Main Turbine Control Valves.
The unit reached 93% (740 MWe) at 2145 on October 4. Power was held there until 1715 on ,
October 6 to repair leaking tubes in 13A Main Condenser.100% power (830 MWe) was achieved at 1840.
Power was reduced to %% from 2130 to 2358 on October 8 for Nuclear Instrument (NI) calibrations.
Power was reduced to 95% (805 MWe) from 0640 on October 9 to 0200 on October 10 due to oscillations in Channel D Delta-T Power indication.
Power was reduced to 9&c (810 MWe) from 2147 to 2350 on October 10 for NI calibrations.
l-Power was reduced to 93% (775 MWe) from 1945 on October 11 to 2000 on October 12 due to a tube leak in 11B Main Condenser.
Power was reduced to 97% (825 MWe) at 2200 on October 31 for Moderator Temperature
- CoefGeient Testing.
i The unit ended the month at 97% power (825 MWe).
l l
t
November 7, 1991 REFUEL.lHG llEQEMATION REQt)fSl
- 1. Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No.1.
- 2. Scheduled date for next refueling shutdown: March 6, 1992.
3 Scheduled date for restart following refueling: May 17, 1992.
- 4. Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?
Resumption of operation after refueling will require changes to Technical Specifications. The anticipated changes will effect consistency between the Unit 2 Cycle 9 Tech Specs and the Tech Specs for Unit 1 Cycle 11,
- 5. Scheduled date(s) for submitting proposed licensing action and supporting information.
December 15, 1991. *
- 6. Important licensing considerations associated with the refueling.
None identified at this time.
- 7. The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.
(a) 217. (b) 1326.
Spent fuel pools are comon to Units 1 and 2.
- 8. (a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.
(a) 1830. (b) 2880.
- 9. The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core of f-load.
March 1992.
- Entry has changed since it was last reported.
l l
60.60************************************************************************
UNIT.2 OPERATING DATA REPORT coce************************************************************************ ;
Docket No. 50-318 November 13, 1991 Prepared by. Leo Shanley Telephone:(410)260-6744 OPERATING STATUS
- 1. UNIT NAME Calvert Cliffs Unit 2
- 2. REPORTING PERIOD OCTOBER 1991
- 3. LICENSED' THERMAL POWER (MWT) 2700
- 4. NAMEPLATE RATING (GROSS MWe) 918
- 5. DESIGN. ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM DEPENDABLE' CAP'Y (GROSS MWe) 860
- 7. MAXIMUM DEPENDABLE CAP'Y-(NET MWe) 825 l
- 8. CHANGE-IN CAPACITY RATINGS none H
- 9. POWER-LEVEL TO WHICH RESTRICTED n/a
- 10. REASONS-FOR RESTRICTIONS n/a l
Cumulative This month Year-to-Date to Date )
- 11. HOURS'IN REPORTING PERIOD 745 7,296 127,848
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 438.0 3,736.5 91,173.8 13.-REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1,296.6 L 14. HOURS GENERATOR-ON LINE 436.8 3,610.7 89,839.6 L 15.; UNIT RESERVE-SHUTDOWN' HOURS ..
0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED-(MWH) 1,151,705 9,313',778 227,703,196
- 17. GROSS ELECTRICAL-ENERGY GEN'TED(MWH)- -379,947 2,994,374 75,279,006 j
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 363,698 2,862,627 71,905,198 i l
- 19. UNIT SERVICE FACTOR 58.6 4 9.5~ 70.3 l H20. UNIT AVAILABILITY FACTOR 58.6. 49.5 70.3
- 21. UNIT. CAPACITY FACTOR (USING MDC NET) 59.2 47.6 68.2
- 22. UNIT CAPACITY FACTOR (USING DER NET) '57.8 46.4. 66.6 r 23. UNIT FORCED OUTAGE RATE 0.0 11.6 5.6 l 124.JSHUTDOWNS; SCHEDULED OVER THE NEXT-SIX MONTHS:(TYPE, DATE~AND DURATION):-
-N/A i-I I: -25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
November 22, 1991 I
l l
L 1
! 1
UNIT SIIUTHOWNS AND POWER REDUCTIONS DOCKETNO. 50-318 UNITNAME Calvert Cliffs-U2 DATE November 13.1991 COMPLETED BY Leo Shantev TELEPHONE (410)260 4744 REPORTMONTII October 1991 MEHIOD OF S'tIUTHNG UCENSEE CAUSE & CORRECEVE DURATION DOWN EVENT SYSTEM COMPONENT ACHONTO NO. DATE TYPEI (llOURS) REASON 2 REACIlOR3 REPORT # CODE 4 CODE 5 PRLTrETRECURRENCE 91-13 911019 S 308.2 B 1 N/A Unit shutdown for scheduled testing and maintenance.
t 1 F: Forced 2 Reason: 3 Method: 4 Exhibit F-Instructions S: Scheduled A-Equipment Failure 1-Manual for Preparation of Data B-Maintenance orTest 2-Manual Scram. Entry Sheets for Ucense C-Refueling 3-Automatic Scram. Event Report y_ER) File D-Regulatory Restriction 4-Continued (NUREG-0161)
E-Operator Training & Ucense Examination ' 5-Reduced Load F-Administrative 9-Other 5 Exhibit H -Same Source G-Operational Error H-Other
AVERAGE DAILY UNIT POWER LEVEL oco*********************************************************************
Docket No. 50-318 Calvert Cliffs Unit No. 2 Novereber 13, 1991 Completed by Ieo Shanley Telephone: (410) 260-6744 OCTOBER 1991 Average Daily Power Level Average Daily Power Level Day (MWe-Net) Day (MWe-Net) 1 838 17 851 2 800 18 840 3 839 19 47 4 840 20 0 5 840 21 0 6 841 22 0 7 844 23 0 8 843 24 0 9 844 25 0 10 843 26 0 11 842 27 0 12 844 28 0 13 823 29 0 14 845 30 0 15 845 31 0 16 847
\
DOCKET #50-318 CALVERT CLIFIS - UNIT 2 November 13,1991
SUMMARY
OF OPERATING EXPERIENCE October 1991 The unit began the month at 100% power (835 MWe).
Power was reduced to 80% (645 MWe) from 0840 to 1400 on October 2 due to an oil leak on a Low Pressure Turbine Intercept Valve operator.
Power was reduced to 90% (740 MWe) from 16(X) to 2130 on October 13 due to a loss of the plant computer.
Power reduction for the scheduled Fall Surveillance Outage was commenced at 2115 on October 18.
The generator was removed from the grid at (M49 on October 19 and the reactor was shutdown at 0600.
The unit ended the month in cold shutdown (Mrxic 5).
. . . - . - . - . . ~ - . .- -.-. - . . . - . . . .~. . - _ . . - -
+'. . . . !" '
l l
November 7, 1991 BiftJEllNR___lMDBMATION RQUESI 1, Name of facility: Calvert Cliffs Nuclear Power Plant. Unit No. 2,
- 2. Scheduled date for next refueling shutdown: March 5, 1993.
- 3. . Scheduled date for restart following refueling: May 17, 1993.
- 4. . Will refueling or resumption of operation thereaf ter ' require a Technical -
Specification change or other license amendment?
.Not identified at this time.
- 5. Scheduled date(s) for. submitting proposed licensing action and supporting information. >
November 17, 1992.
- 6. Important licensing considerations associated with the refueling.
~
- None-identified at this time.
- 7. The' number of= fuel assemblies (a) in the core and (b)- in the spent fuel
. storage pool..
(a) 217.- (b) 1326.
- Spent fuel pools are common to Units 1 and 2.
'8. (a);The present licensed spent fuel pool storage capacity, and-(b) the sizeLof any increase in licensed storage capacity that has been
- requested: or is planned, in number of fuel assemblies, i
-(a)- 1830.- (b) 2880.
9.- _ The projected date of.the last refueling that can-be discharged -to- the Spent Fuel Pool assuming the present licensed capacity and maintaining space-for one full core off-load.
March 1992.