f TENNESSEE VALLEY. AUTHORITY cHITTANOOGA..TEppEfSEE 37401 400 Chestnut Street Tower II BLRD-50-438/83-44 BLRD-50-439/83-37 U.S. Nuclear Regulatory Commission Region II Attn:- Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - VIOLATION OF SPACING REQUIREMENTS FOR GROUTED ANCHORS - BLRD-50-438/83-44, BLRD-50-439/83 FINAL REPORT The subject deficiency was initially reported to NRC-0IE Inspector Linda Watson on July 1, 1983 in accordance with 10 CFR 50.55(e) as NCR 2408. This was followed by our interim report dated July 28, 1983
~
Enclosed is our final report.
If you have any questions, please get in touch with R. H. Shell at s
FTS 858-2688.
Very truly yours, TENNESSEE VALLEY AUTHORITY
/
<///,4 e L. M. Mills, Manager Nuclear Licensing Enclosure i
cc:
Mr. Richard C. DeYoung, Director (Enclosure) j Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.
20555 l
Records Center (Enclosure)
Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 l
l l
n-8312080079 831201 Tj3TGM' CDPY PDR ADOCK 05000438 S
PDR l
t' V 1983-TVA SOTH AN NIVERS ARY y
_,e_,---,_
N ENCLOSURE 9
BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 VIOLATION OF SPACING REQUIREMENTS FOR GROUTED ANCHORS BLRD-50-438/83-44, BLRD-50-439/83-37 NCR 2408 10 CFR 50.55(e)
FINAL REPORT Description of Deficiency General Specification G-32 Appendix D (implemented onsite by BNP-QCP-2.8) requires that in large holes or chipped out areas where grouted anchors are used, the chipped out area shall extend at least three ' nominal bolt diameters for individual and six nominal bolt diameters for maltiple anchors beyond the end of the anchor. These chipped areas should the.' be refilled with concrete for support. Seismic pipe supports have been installed with anchor bolts such that the chipped areas have possibly been chipped only to the bottom of the anchor. This condition occurred because personnel received insufficient training and consequently failed to follow the applicable procedure.
Safety Implications Installation of anchors in violation of G-32 spacing requirements could lead (in this case by increasing loads) to inadequate support of safety-(
related piping systems. This could possibly lead to failure of safety-related piping and subsequently damage safety-related equipment during a seismic event, and thus have adverse affects on the safe operations of the plant.
Corrective Action TVA's Division of Engineering Design (EN DES) has dispositioned NCR 2408 to "use as is." The 47 supports referenced in the subject NCR have been evaluated by EN DES and the anchorage was found to be adequate for the current loads; he'aever, these must be reevaluated if there is any load increase. Engineering change notice (ECN) 2569 has been prepared to add the following note to all involved support drawings:
"Any modification to this support which increases the load on the anchor bolts shall be submitted to EN DES Project Civils for approval." The applicable personnel will be retrained to the requirements of Appendix D of G-32.
j All corrective action will be completed by June 30, 1984.
')-