Forwards Const & OL Review Schedules,Per 831025 Meeting. Const Will Be Completed 42-48 Months After Restart.Projected Fuel Load Date Anticipated Between June 1987 & Dec 1989
ML20082F293
Person / Time
Site: Satsop
Issue date: 11/18/1983
From: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Harold Denton
Office of Nuclear Reactor Regulation
References
GO3-83-889, NUDOCS 8311280501
Download: ML20082F293 (15)


Text

1 s

Washington Public Power Supply System Box 1223 - Elma,Weehington 98541-1223 (2061482-4428-DOCKET NO. 50-508 November 18,.19831 G03-83-889 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation.

U. S. Nuclear Regulatory Consnission Washington, D.C.

20555

Subject:

. NUCLEAR PROJECT 3 WNP-3 CONSTRUCTION AND OL REVIEW SCHEDULES

Reference:

Letter, G. C. Sorensen to H.- R. Denton G03-83-0544, dated July 12, 1983 l

Dear Mr. Denton:

0n October 25, 1983, representatives from Supply System management met with management personnel from your Staff to discuss theQtatus of the ongoing review of the WNP-3 Final Safety Analysis Report (FSAR) in view of the delay in construction until an assured source of funding is availablej You were advised of the construction delay in the reference.

During the October 25 meeting, we_ stated that the Supply System would con-tinue to support the safety evaluation effort although, due to the current project delay, not in accordance with the present schedule. We indicated to

.your Staff that the Supply System had completed responses to 170 of the 340 round one questions and-81 of the 107 acceptance review questions received.

We also provided an indication.of which uncompleted responses we could com-

.plete within the present manpower and cash flow constraints.

'It is estimated that it will take.42-48 months after restart to complete con-struction of WNP-3.

Restart could occur as early as January 1984.

The maxi-mum anticipated delay will not extend fuel load more than three and one-half

-(3 1/2) years from the original June 1986 date.

Therefore, the projected fuel load date for WNP-3 ranges anywhere between June 1987 and December

.1989.

The Supply System is committed to completing plant design (nearly 100%

engineering complete already) and dedicating the resources available to re-

solve design affecting regulatory concerns. Other activities (i.e., plan-ning, ' preparing procedures and assuring that trained operators will be avail-able) are also being pursued in order to adequately support the full range of possible fuel load dates.

8311280501 831118

/

PDR ADDCK 05000508

/

A peg

w1 a

E

-Mr. Harold R. Denton November 18, 1983

, Page 2 G03-83-889 1

NUCLEAR PROJECT NO. 3 WNP-3 CONSTRUCTION AND.0L REVIEW SCHEDULES-InLlight-of current NRC practice, we would expect a final SER 16 months-prior to fuel. load.

Consequently, there will be a period of relatively low review

-activity. - In order to minimize the impact of. delay.in construction on the licensing process, we will continue work on potentially design affecting concerns.

In the discussions with your Staff regarding the status of the ongoing review, it was observed that both the Supply System and the NRC expended considerable effort.

In order to preserve that effort, it was

' agreed that' preparation.of a draft SER that would document the review to date is' highly desirable but would entail a resource commitment by both the NRC and the Supply System.

A plan to accomplish the remaining review was discussed with your staff.

That plan has been slightly modified and is proposed here.

The approach is to maximize the reviewers'and engineering personnel most familiar with the project now and to close portions of the review that are presently being worked on. Furthermore, areas of concern not previously identified in NRC questions should be transmitted so the Supply System can attempt timely resolution.

In order to assure.that construction restart and fuel load will

' not be impacted by licensing concerns, the Supply System will follow generic safety issues',.CESSAR-F and issues at other similar design facilities. More precisely, the following planned activities are proposed for your consider-ation and the~ basic schedule for these activities is set forth in Attach-ment 1.

1.

The Supply System completes responses to presently received questions that are potentially design impacting per Attachment 2 prior to issuance of the draft SER.

2..

- NRC reviews the Supply System responses prior to issuance of the draft SER.

3.

NRC transmits all remaining Safety Evaluation Questions (e.g. Instrumen-tation and Control Systems Branch).

4.

Meetings between the Supply System and NRC are held as necessary to clarify submitted responses prior to issuance of the draft SER.

5.

NRC documents the status of the Safety Review in a draft SER.

6.

- The Supply System identifies CESSAR-F SER open items, confirmatory items, and required plant specific items and. assures that the WNP-3 FSAR l

adequately reflects resolution of these items.

i 7.

The Supply System follows CESSAR-F, Palo Verde, Unresolved Safety Issues, etc., to assure that WNP-3 adequately addresses these issues.

i.,,:~,

..---c

,..r-

-,n,,

--,r w

.---,.v.

,,,,.,,---r..


.-nn---.,-r

-,, - -. -..,~ww.,,+--..

Mr. Harold R. Denton November 18, 1983 Page 3 G03-83-889 NUCLEAR PROJECT NO. 3 WNP-3 CONSTRUCTION AND OL REVIEW SCHEDULES 8.

A schedule for the final SER is determined at an appropriate time following construction restart.

This plan is being submitted for your concurrence.

The Supply System would appreciate that you provide us with your response by December 5 so that the requisite detailed planning may be initiated.

If you have any questions, please contact Mr. D. W. Coleman, WNP-3 Licensing Project Manager on (206) 482-4428 extension 5436.

Sincerely, ttN G. C. Sorensen, Manager (340)

Regulatory Programs DWC/tn Attachments

-cc:

J. A. Adams, NESCO P. Christofakis, Ebasco NY0 G. Knighton, NRC J. Porrovecchio, Ebasco NY0 S. Prussman, Ebasco NY0 N. S. Reynolds, D&L D. Smithpeter, BPA A. A. Tuzes, CE A. Vietti, NRC Ebasco, Elma M. Yates, Ebasco NY0

SUPPLY SYSTEM PROPOSED OL REVIEW SCHEDULE FURTHER SCHEDULE TO BE 7/83 8/83 9/83 10/83 ll/83 12/83 I/84 2/84 3/84 4/84 5/,84 6/84 DETERMINED WHEN ASSURED I

SOURCE OF FUNDS ARE IDENTIFIED.

5th SET OF h

2nd SET OF 4th SET OF QUESTIONS R

T SER DLISSUES 5th SET OF ist SET OF DES RESPONSES 3rd SET OF RESPONSES RESPONSES l

ATTACHMENT I

ATTACHMENT 2 Status and Schedule of Responses to NRC Safety Review Questions i

e i

11/83

DIVISION OF LICENSING STRUCTURAL ENGINEERING BRANCH Acceptance Review - 08/20/82 Acceptance Review - 08/20/82 100.1 Partial Re-220.1 Complete 10/22/82 mainder Not 220.2 Complete 10/22/82 Scheduled 220.3 Complete 10/22/82

  • 100.2

' Complete 01/17/83 220.4 Complete 10/22/82 100.3 Complete 10/22/82 220.5 Complete 10/22/82 100.4 Complete 10/22/82 220.6 Complete 10/22/82 220.7 Complete 10/22/82 220.8 Complete 01/17/83 MECHANICAL ENGINEERING BRANCH 220.9 Complete 10/22/82 Acceptance Review - 08/20/82 Round One - 05/03/83 210.1 Complete 10/22/82 220.10 Complete 09/02/83 210.2 Complete 10/22/82 220.11 Complete 09/02/83

    • 210.3 Scheduled 12/31/83 220.12 Complete 09/02/83 210.4 Complete 01/17/83 220.13 Scneduled 03/31/84
  • 210.5 Complete 10/22/82 220.14 Complete 09/02/83 210.6 Complete 10/22/82 220.15 Scheduled 03/31/84 210.7 Complete 10/22/82 220.16 Scheduled 03/31/84 220.17 Complete 09/02/83 220.18 Scheduled 12/31/83 5 tiff Clamps - 06/25/82 220.19 Partial Re-mainder Not 210.1 Complete 07/30/82 Scheduled
  • 210.2 Complete 07/30/82 220.20 Complete 09/02/83
  • 210.3 Complete 07/30/82 220.21 Complete 09/02/83 210.4 Complete 07/30/82 220.22 Scheduled 03/31/84 210.5 Complete 07/30/82 220.23 Complete 09/02/83
  • 210.6 Complete 07/30/82 220.24 Complete 09/02/83 210.7 Complete 07/30/82 220.25 Scheduled 12/31/83 210.8 Complete 07/30/82 220.26 Scheduled 12/31/83 210.9 Complete 07/30/82 220.27 Complete 09/02/83 210.10 Complete 07/30/82 220.28 Complete 09/02/83
  • 210.11 Complete 07/30/82 220.29 Complete 09/02/83 210.12 Complete 07/30/82 220.30 Scheduled 12/31/83 210.13 Complete 09/14/82 220.31 Complete 09/02/83 220.32 Complete 09/02/83 220.33 Complete 07/15/83 Stiff Clamps - 04/04/83 220.34 Complete 09/02/83 220.35 Complete 09/02/83 210.14 Complete 06/15/83 220.36 Complete 09/02/83 210.15 Complete 06/15/83 220.37 Scheduled 12/31/83 210.16 Not Scheduled 220.38 Complete 09/02/83 210.17 Complete 06/15/83 210.18 Complete 06/15/83 210.19 Complete 06/15/83 210.20 Complete 06/15/83 11/83

STRUCTURAL ENGINEERING BRANCH GEOSCIENCES BRANCH-GEOLOGY (Cont'd)

Audit - 11/02/83 Round One - 05/03/83 Item 1 Scheduled 03/31/84 231.1 Not Scheduled Item 2 Complete 11/02/83 231.2 Not Scheduled Item 3 Complete 11/02/83 231.3 Not Scheduled Item 4 Scheduled 12/31/84 231.4 Not Scheduled

  • Item 5 Scheduled 03/31/84 231.5 Not Scheduled Item 6 Complete 11/02/83 231.6 Not Scheduled
  • Item 7 Complete 11/02/83 231.7 Not Scheduled
  • Item 8 Complete 11/02/83 Item 9 Complete 11/03/83 Item 10 Complete 11/02/83 HYDROLOGIC AND GE0 TECHNICAL
  • Item 11 Complete 11/02/83 ENGINEERING BRANCH-HYDROLOGICAL Item 12 Scheduled 03/31/84 Item 13 Complete 11/02/83 Item 14 Scheduled 03/31/84 Acceptance Review - 08/20/82 Item 15 Scheduled 03/31/84 Item 16 Complete 11/02/83 240.1 Complete 11/30/82 Item 17 Scheduled 03/31/84 Item 18 Scheduled 03/31/84 Item 19 Scheduled 12/31/83 Round One - 07/08/83 Item 20 Scheduled 03/31/84 Item 21 Scheduled 03/31/84 240.2 Scheduled 03/31/84 Item 22 Scheduled 03/31/84 240.3 Scheduled 03/31/84 Item 23 Scheduled 03/31/84 240.4 Scheduled 03/31/84 Item 24 Scheduled 03/31/84 240.5 Scheduled 03/31/84 Item 25 Scheduled 03/31/84 240.6 Scheduled 03/31/84 240.7 Scheduled 03/31/84 240.8 Scheduled 03/31/84 GEOSCIENCES BRANCH-SEISMOLOGY 240.9 Scheduled 03/31/84 240.10 Scheduled 03/31/84 240.11 Scheduled 03/31/84 Round One - 05/03/83 240.12 Scheduled 03/31/84 240.13 Scheduled 03/31/84 230.1 Not Scheduled 240.14 Scheduled 03/31/84 230.2 Not Scheduled 230.3 Not Scheduled 230.4 Not Scheduled 230.5 Not Scheduled 230.6 Not Scheduled 11/83 i

HYDROLOGIC AND GE0 TECHNICAL QUALITY ASSURANCE BRANCH ENGINEERING BRANCH-GE0 TECHNICAL (Cont'd)

Round One - 10/17/83 Acceptance Review - 08/20/82 260.1 Scheduled 03/31/84 241.1 Complete 10/22/82 241.2 Complete 10/22/82 241.3 Complete 10/22/82 EQUIPMENT QUALIFICATION BRANCH-241.4 Complete 10/22/82 ENVIRONMENTAL 241.5 Complete 10/22/82 241.6 Complete 02/03/83 241.7 Complete 10/22/82 Acceptance Review - 08/20/82 241.8 Complete 10/22/82 241.9 Complete 10/22/82 270.1 Partial Next 241.10 Complete 10/22/82 Submittal

  • 241.11 Complete 10/22/82 Scheduled 12/31/83 270.2 Complete 02/03/83 Round One - 04/12/83 EQUIPMENT QUALIFICATION BRANCH-241.12 Complete 07/15/83 SEISMIC 241.13 Complete 07/15/83 241.14 Complete 07/15/83 241.15 Complete 07/15/83 Acceptance Review - 08/20/82 241.16 Complete 07/15/83 241.17 Complete 07/15/83 271.1 Partial Next 241.18 Complete 09/02/83 Submittal 241.19 Complete 09/02/83 Scheduled 12/31/83 241.20 Scheduled 12/31/83 241.21 Complete 09/02/83 241.22 Complete 09/02/83 CHEMICAL ENGINEERING BRANCH-241.23 Complete 11/03/83 FIRE PROTECTION 241.24 Complete 09/02/83 241.25 Complete 09/02/83 Acceptance Review - 08/20/82 i

MATERIALS ENGINEERING BRANCH-280.1 Complete 10/22/82 INSERVICE INSPECTION 280.2 Complete 10/22/82 280.3 Complete 10/22/82 280.4 Scheduled 03/31/84 Acceptance Revicw - 08/20/82

  • 280.5 Complete 10/22/82 250.1 Complete 10/22/82 250.2

[Not Used]

250.3 Complete 10/22/82 OUALITY ASSURANCE BRANCH Round One - 05/03/83 260.0 Scheduled 03/31/84 11/83

CHEMICAL ENGINEERING BRANCH-EFFLUENT TREATMENT SYSTEMS CHEMICAL BRANCH Acceptance Review - 08/20/82 Round One - 04/12/83 281.1 Partial Re-321.1 Complete 09/02/83 mainder Not 321.2 Complete 09/02/83 Scheduled 321.3 Complete 11/03/83 281.2 Complete 10/22/82 321.4-Complete 09/02/83 281.3 Complete 10/22/82 321.5 Complete 07/15/83 281.4 Not Scheduled 321.6 Complete 09/02/83 Round One - 04/12/83 AUXILIARY SYSTEMS BRANCH 281.5 Complete 07/15/83 281.6 Scheduled 12/31/83 281.7 Partial Re-Acceptance Review - 08/20/82 mainder Not Scheduled 410.1 Complete 10/22/82 281.8 Complete 07/15/83 410.2 Complete 02/03/83 281.9 Complete 07/15/83 410.3 Not Scheduled 281.10 Complete 07/15/83 410.4 Not Scheduled 281.11 Complete 07/15/83 410.5 Complete 10/22/82 281.12 Complete 07/15/83 410.6 Complete 10/22/82 281.13 Complete 09/02/83 410.7 Complete 01/17/83 281.14 Partial Re-410.8 Complete 03/24/83 mainder Not 410.9 Complete 10/22/82 Scheduled 410.10 Complete 10/22/82 281.15 Complete 07/15/83 410.11 Complete 10/22/82 281.16 Complete 09/02/83 410.12 Complete 02/03/83 281.17 Complete 09/02/83 410.13 Complete 10/22/82 410.14 Not Scheduled SITING ANALYSIS BRANCH-SITE IMPACT Acceptance Review - 08/20/82 311.1 Complete 10/22/82 311.2 Complete 10/22/82 311.3 Scheduled 12/31/83 11/83

AUXILIARY SYSTEMS BRANCH INSTRUMENTATION AND CONTROL (Cont'd)

SYSTEMS BRANCH Round One - 04/12/83 Acceptance Review - 08/20/82 410.15 Complete 07/15/83 421.1 Complete 02/03/83 410.16 Partial Re-mainder Not 421.2 Complete 10/22/82 Scheduled 410.17 Complete 09/02/83 410.18 Complete 09/02/83 410.19 Complete 09/02/83 410.20 Scheduled 03/31/84 410.21 Scheduled 03/31/84 410.22 Scheduled 03/31/84 410.23 Complete 07/15/83 410.24 Complete 09/02/83 410.25 Complete 09/02/83 410.26 Scheduled 03/31/84 410.27 Complete 07/15/83 410.28 Complete 07/15/83 410.29 Complete 09/02/83 410.30 Complete 09/02/83 410.31 Complete 11/03/83 410.32 Complete 09/02/83 410.33 Complete 07/15/83 410.34 Not Scheduled 410.35 Complete 09/02/83 410.36 Complete 09/02/83 410.37 Complete 07/15/83 410.38 Complete 09/02/83 410.39 Scheduled 03/31/84 410.40 Scheduled 12/31/83 410.41 Complete 07/15/83 410.42 Scheduled 03/31/84

  • 410.43 Complete

'07/15/83 410.44 Complete 07/15/83 410.45 Complete 09/02/83 410.46 Complete 07/15/83 410.47 Complete 09/02/83 410.48 Complete 07/15/83 410.49 Complete 07/15/83 410.50 Complete 09/02/83 410.51 Complete 07/15/83 410.52 Complete 09/02/83 410.53 Scheduled 03/31/84 11/83

f POWER SYSTEMS BRANCH POWER SYSTEMS BRANCH (Cont'd)

Acceptance Review - 08/20/82 Round One - 05/03/83 (Cont'd) 430.1 Complete 10/22/82 430.2 Complete 10/22/82 430.46 Not Scheduled 430.47 Not Scheduled 430.48 Not Scheduled Round One - 05/03/83 430.49 Complete 09/02/83 430.50 Not Scheduled 430.3 Complete 09/02/83 430.51 Complete 09/02/83 430.4 Complete 09/02/83 430.52 Not Scheduled 430.5 Complete 09/02/83 430.53 Not Scheduled 430.6 Complete 09/02/83 430.54 Complete 09/02/83 430.7 Complete 09/02/83 430.55 Complete 09/02/83 430.8 Complete 09/02/83 430.56 Complete 09/02/83 430.9 Complete 09/02/83 430.57 Complete 09/02/83 430.10 Complete 09/02/83 430.58 Not Scheduled 430.11 Not Scheduled 430.59 Not Scheduled 430.12 Complete 09/02/83 430.60 Complete 09/02/83 430.13 Complete 09/02/83 430.61 Scheduled 12/31/83 430.14 Scheduled 03/31/84 430.62 Complete 09/02/83 430.15 Complete 09/02/83 430.63 Complete 09/02/83 430.16 Complete 09/02/83 430.64 Scheduled 12/31/83

  • 430.17 Complete 07/15/83 430.65 Complete 09/02/83 430.18 Complete 09/02/83 430.66 Complete 09/02/83 430.19 Complete 09/02/83 430.67 Complete 09/02/83 430.20 Complete 09/02/83 430.68 Complete 09/02/83 430.21 Scheduled 12/31/83 430.22 Complete 09/02/83 430.23 Scheduled 12/31/83 430.24 Complete 09/02/83 430.25 Complete 09/02/83 430.26 Not Scheduled 430.27 Not Scheduled 430.28 Not Scheduled 430.29 Not Scheduled 430.30 Not Scheduled 430.31 Not Scheduled 430.32 Complete 09/02/83 430.33 Not Scheduled 430.34 Complete 09/02/83 430.35 Complete 09/02/83 430.36 Scheduled 12/31/83 430.37 Scheduled 12/31/83 430.38 Not Scheduled 430.39 Not Scheduled 430.40 Complete 09/02/83 430.41 Complete 09/02/83 430.42 Not Scheduled 430.43 Not Scheduled 430.44 Not Scheduled 430.45 Not Scheduled 11/83

POWER SYSTEMS BRANCH REACTOR SYSTEMS BRANCH (Cont'd)

(Cont'd)

Round One - 05/11/83 Round One - 05/11/83 430.69 Scheduled 03/31/84 440.2 Not Scheduled 430.70 Scheduled 03/31/84 440.3 Not Scheduled 430.71 Not Scheduled 440.4 Not Scheduled 430.72 Not Scheduled 440.5 Not Scheduled 430.73 Scheduled 03/31/84 440.6 Not Scheduled 430.74 Not Scheduled 440.7 Not Scheduled 430.75 Not Scheduled 440.8 Not Scheduled 430.76 Scheduled 03/31/84 440.9 Not Scheduled 430.77 Not Scheduled 440.10 Not Scheduled 430.78 Not Scheduled 440.11 Not Scheduled 430.79 Not Scheduled 440.12 Not Scheduled 430.80 Not Scheduled 440.13 Not Scheduled 430.81 Scheduled 03/31/84 440.14 Not Scheduled 430.82 Scheduled 03/31/84 440.15 Not Scheduled 430.83 Not Scheduled 440.16 Not Scheduled 430.84 Not Scheduled 440.17 Not Scheduled 430.85 Not Scheduled 440.18 Not Scheduled 430.86 Scheduled 03/31/84 440.19 Not Scheduled 430.87 Scheduled 03/31/84 440.20 Not Scheduled 430.88 Scheduled 03/31/84 440.21 Not Scheduled 430.89 Not Scheduled 440.22 Not Scheduled 400.9G Not Scheduled 440.23 Not Scheduled 430,91 Not Scheduled 440.24 Not Scheduled 430.92 N9t Scheduled 440.25 Not Scheduled 430.93 Not Scheduled 440.26 Not Scheduled 430.94 Scheduled 03/31/84 440.27 Not Scheduled 430.95 Scheduled 03/31/84 440.28 Not Scheduled 430.96 Not Scheduled 440.29 Not Scheduled 430.97 Scheduled 03/31/84 440.30 Not Scheduled 430.98 hot Scheduled 440.31 Not Scheduled 440.32 Not Scheduled 440.33 Not Scheduled REACTOR SYSTEMS BRANCH 440.34 Not Scheduled Acceptance Review - 08/20/82 440.1 Complete 01/17/83 l

l 11/83

~-

ACCIDENT EVALUATION BRANCH-RADIOLOGICAL ASSESSMENT BRANCH-SYS. AND RAD. ANALYSIS RADIATION PRdTECTION Round One - 04/12/83 Acceptance Review - 08/20/82 450'.1 Scheduled 12/31/83 471.1 Scheduled 12/31/83 450.2 Complete 07/15/83 471.2 Complete 10/22/82 450.3 Complete 07/15/83 471.3 Complete 10/22/82 450.4 Complete 09/02/83 471.4 Complete 10/22/82 450.5 Complete 11/03/83 471.5 Complete 10/22/82 450.6 Scheduled 12/31/83 471.6 Scheduled 12/31/83 450.7 Complete 09/02/83 471.7 Complete 10/22/82 450.8 Scheduled 03/31/84 471.8 Complete 10/22/82 450.9 Complete 09/02/83 471.9

[Not Used]

450.10 Complete 11/03/83 450.11 Complete 09/02/83 450.12 Scheduled 12/31/83 Round One - 04/12/83 471.10 Complete 07/15/83 ACCIDENT EVALUATION BRANCH-471.11 Complete 09/02/83 METEOROLOGY 471.12 Scheduled 12/31/83 471.13 Complete 09/02/83 471.14 Not Scheduled Acceptance Review - 08/20/82 471.15 Complete 09/02/83 471.16 Complete 09/02/83 451.1 Complete 10/22/82 471.17 Complete 07/15/83 451.2 Complete 10/22/82

  • 471.18 Complete 07/15/83 471.19 Complete 09/02/83 471.20 Complete 11/03/83 Round One - 04/12/83 471.21 Scheduled 03/31/84 471.22 Complete 09/02/83
  • 451.3 Complete 07/15/83 471.23 Scheduled 12/31/83 451.4 Complete 09/02/83 471.24 Complete 07/15/83 451.5 Complete 07/15/83 471.25 Scheduled 12/31/83 451.6 Scheduled 03/31/84 451.7 Complete 07/15/83 CONTAINMENT SYSTEMS BRANCH EFFLUENT TREATMENT SYSTEMS BRANCH Acceptance Review - 08/20/82 Acceptance Review - 08/20/82 480.1 Complete 10/22/82 480.2 Complete 01/17/83 460.1 Scheduled 12/31/83 480.3 Not Scheduled 480.4 Complete 10/22/82 480.5 Partial Re-mainder Not Scheduled 480.6 Partial Re-mainder Not Scheduled 11/83

\\_

CONTAllENT SYSTEMS BRANCH HUMAN FACTORS ENGINEERING BRANCH

Cont'c )

Round One -' 05/03/83 Acceptance Review - 08/20/82

~480.7 Complete 09/02/83 620.1 Complete 10/22/82 480.8 Complete.

09/02/83 480.3 Scheduled 03/31/84-480.10 Complete 09/02/83.

LICENSEE QUALIFICATIONS BRANCH 480.11' ' Complete 09/02/83 480.12 Scheduled 12/31/83 480.13 Scheduled 12/31/83 Acceptance Review - 08/20/82 480.14 Complete 09/02/83 480.15 Complete 09/02/83 630.1 Complete 10/22/82

.480.16 Not Scheduled 630.2

. Complete 10/22/82 480.17

' Scheduled 12/31/83

'480.18 Scheduled 12/31/83 480.19 Scheduled-12/31/83 Round One - 04/12/83 480.20

. Scheduled 03/31/84 480.21 Scheduled 12/31/83 630.3 Complete 07/15/83 480.22 Complete 11/03/83 630.4 Partial Re-480.23 Complete.

.09/02/83 mainder Not 480.24 Scheduled.

12/31/83 Scheduled 480.25 Complete 09/02/83 630.5 Complete 09/02/83 480.26 Scheduled 12/31/83 630.6

. Complete 09/02/83 630.7 Complete 07/15/83 630.8 Complete 07/15/83 CORE PERFORMANCE BRANCH-FUELS 630.9 Complete 09/02/83

  • 630.10 Complete 09/02/83 630.11 Complete 09/02/83 Acceptance Review - 08/20/82 630.12 Complete-07/15/83 490.1-Not Scheduled PROCEDURES AND TEST REVIEW BRANCH Round One - 05/03/83 490.2 Not Scheduled Acceptance Review - 08/20/82
  • 640.1 Complete 10/22/82

' CORE PERFORMANCE BRANCH-

  • 640.2

. Complete 10/22/82 THERMAL HYDRAULICS

  • 640.3 Complete 10/22/82 Round One - 05/03/83 492.1 Complete 09/02/83 492.2 Partial Scheduled 03/31/84 492.3 Partial Scheduled.

03/31/84 11/83

PROCEDURES AND TEST REVIEW ACCEPTANCE REVIEW LETTER BRANCH ENCLOSURE 4 (Cont'd)

Acceptance Review - 08/20/82 Round One - 06/01/83 1

Complete 02/03/83 640.1 Complete 09/02/83 2

Not Scheduled 640.2 Complete 09/02/83 3

Scheduled 03/31/84 640.3 Complete 09/02/83 4

Complete 10/22/82 640.4 Complete 09/02/83

  • 5 Scheduled 03/31/84 640.5 Complete 03/02/83
  • 6 Complete 01/17/83 640.6 Complete 09/02/83 7

Complete 10/22/82 640.7 Complete 09/02/83 8

Not Scheduled 640.8 Complete 09/02/83 9

Not Scheduled 640.9 Complete 09/02/83

  • 10 Partial Next 640.10 Complete 09/02/83 Scheduled 12/31/83 640.11 Complete 09/02/83 11 Scheduled 03/31/84 640.12 Complete 09/02/83 12 Complete 10/22/82 640.13 Complete 09/02/83 13 Complete 10/22/82 640.14 Complete 11/03/83
  • 14 Completa 10/22/82 640.15 Complete 11/03/83 Round One - 10/14/83 640.16 Scheduled 12/31/83 GENERIC ISSUES BRANCH Round One - 06/01/83 730.0 Not Scheduled EMERGENCY PREPAREDNESS LICENSING BRANCH Acceptance Review - 08/20/82 810.1 Not Scheduled
  • Response to question resulted in further commitmelit.
    • Expect responses to be transmitted to the NRC no later than the scheduled dates indicated.

11/83