Amends Response to NRC Re Violations Noted in IE Insp Rept 50-261/82-20.Completion of Flow Diagrams & Corresponding Procedures for Q-list Portion of Sys Extended to 831231
ML20080M841
Person / Time
Site: Robinson 
Issue date: 09/01/1983
From: Starkey R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20080M787 List:
References
RSEP-83-1146, NUDOCS 8310040285
Download: ML20080M841 (2)


Text

_

e Cp&L E

3

--a Carolina Power & Light Company 3

p L,

CD 55 W

H. B. RTINSW STEAM ErHTRIC PLANP POST TFICE BW 790 r3 HARPSVTTLE, SOUIH CAROLINA 29550 SEP 11983 Fabinson File No: 13510E Serial: RSEP/83-1146 Mr. James P. O'Reilly Regional Mministrator Region II U. _ S. Nuclear Regulatory Canaission 101 Marietta Street, N.W., Suite 3100 Atlanta, Georgia 30303 H. B. RTINSW STEAM FTHTRIC PLANT DOCKEP NO. 50-261 LICENSE NO. DPR-23 I.E. INSPECTI N REPORP NO. 82-20

Dear Mr. O'Reilly:

Carolina Power and Light Cmpany (CP&L) subnits a change in the response to the subject Inspection Ibport dated August 20, 1982.

In response to Violation A of the subject Inspection Report, CP&L described a two phase Drawing Update Program. Phase one involved the as-built walkdowns of systems which were identified as "inportant to safety." mese walkdowns were cmpleted in July,1982. m e second phase incorporated these as-built walkdowns into permanent Plant drawings and involved walkdowns of the remaining systes l

(determined not to be "inportant to safety") by Septenber 1,1983. %e changes identified as a result of the phase one walkdowns have been incorporated into the permanent Plant drawings. Mditionally, a nunber of the systems included in phase two have been walked down (e.g., all systes inside containment).

However, to assure consistency of Plant drawings, once phase two was well underway, a program to walk down the phase one Plant systems was started in January, 1983. h is greatly expanded the scope of the Drawing Update Program but was considered necessary to achieve quality results.

S e Drawing Update Program, which in its final form really started in January, 1983, is close to its revised schedule and is expected to be back on schedule by the end of the year. %e NBC Senior Resident Inspector has been kept abreast of the progress of this Drawing Update Precuu. Due to the expanded scope of this Drawing Update Program, therefore, not all systen walkdowns have been cmpleted.

l In addition, the response to Violation B of the subject response stated that the l

corresponding procedure changes for these other as-built walkdowns would also be cmpleted by September 1,1983.

8310040285 830913 l

PDR ADOCK 05000261 l

G PDR l

m

os Ietter to Mr. James P. O'lheilly

~'

Serial: RSEP/83-ll46 Page 2 i

Because the walkdowns are not otxnpleted, the corresponding procedures are not yet cmpleted.

We believe.that the Drawing Update Program, as it is being implemented today under a-revised schedule, will result in accurate drawings which will assist in the safe operation of the Plant.

Because of the additional effort required, the response ommitments to Violations A and B of the subject Inspection Report should be revised to read:

"'Ihe flow diagrams and corresponding procedures for Q-list portions of systems will be cmpleted by Decerber 31, 1983. Changes to other procedures will be cmpleted in accordance with the long Term Inprovement Program."

If you have any questions concerning this response, please contact my staff or me.

Very truly yours, b

R. B. Starkey, r.

General Manager H. B. Robinson SEG Plant CLW:FM3:JMC/ bas cc: