MONTHYEARML20064N2771983-02-0808 February 1983 Forwards Addl Info Re Training for Mitigating Core Damage. Station Superintendent Receives Adequate Experience in Regular Duties Which Abrogates Need for Formal Training for Mitigating Core Damage Project stage: Request ML20072G0341983-03-21021 March 1983 Responds to Generic Ltr 83-10 Re Resolution of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps. Extension to 830701 Requested for Submittal of Schedule for Resolution of Issue Project stage: Other ML20090F6971983-06-30030 June 1983 Notifies of Postponement of Submittal of Plans & Schedules for Resolution of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pump (Generic Ltr 83-10) Until 830815, Due to Delay in Receipt of Generic Rept from B&W Project stage: Other ML20080C1031983-08-12012 August 1983 Responds to Generic Ltr 83-10 Re Resolution of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pump. Schedule to Be Submitted by 830930,since B&W Generic Proposal Re Std Lower Loop Configuration to Be Evaluated Project stage: Other ML20080N9771983-10-0303 October 1983 Forwards Plan & Schedule for Resolution of NUREG-0737,Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps, (Generic Ltr 83-10),per NRC 830208 Request.Operating Procedures for Pumps to Be Revised Project stage: Other ML20085N5701983-10-27027 October 1983 Advises of Delay in Submittal of Operating Procedures for Trip of Reactor Coolant Pumps (TMI Item II.K.3.5 & Generic Ltr 83-10).Program Reviewed in Light of Generic Ltr 83-31 Re Abnormal Transient Operating Guidelines Project stage: Other ML20091H9241984-05-29029 May 1984 Advises That Rept Re Resolution of TMI Action Item II.K.3.5 Automatic Trip of Reactor Coolant Pumps, in Response to Generic Ltr 83-10,will Be Submitted by 840731 Project stage: Other ML20097C7021984-07-31031 July 1984 Best Estimate Steam Generator Single Double-Ended Tube Rupture Analysis Project stage: Other ML20097C6901984-09-0707 September 1984 Forwards Best Estimate Steam Generator Single Double-Ended Tube Rupture Analysis, (B&W Document 77-1152840-00) for Raised Loop Plant in Response to Generic Ltr 83-10 & TMI Item II.K.3.5 Project stage: Other ML20207F6051986-12-29029 December 1986 Forwards Response to Generic Ltr 86-05 Re Implementation of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps, Addressing plant-specific Concerns,Including Instrumentation Uncertainties & Operator Training Project stage: Other ML20155G0611988-06-0909 June 1988 Advises That Implementation of NUREG-0737,Item II.K.3.5 Complete.Util 861229 Response Stated That Facility Procedures Require Reactor Coolant Pump Trip When RCS Subcooling Margin Falls Below 20 F Project stage: Other 1983-08-12
[Table View] |
Text
TOLEDO
%mm EDISON Docket No. 50-346 I$ce License No. NPF-3
"
Serial No. 980 August 12, 1983 Director of Nuclear Reactor Regulation Attention:
Mr. John F. Stolz Operating Reactors Branch No. 4 Division of Operating Reactors United States Nuclear Regulatory Commission Washington, D.C.
20555 l
Dear Mr. Stolz:
This is in response to your letter of February 1983 (Log No. 1222) concerning Resolution of TMI Action Item II.K.3.5, " Automatic Trip of Reactor CooJant Pump" (Generic Letter 83-10). In our letter of June 30, 1983 (Serial No. 962) Toledo Edison planned to submit our plans and schedule by August 15, 1983 for the Davis-Besse Nuclear Power station Unit No. 1 (DB-1).
Toledo Edisoggiaw j/u t received the generic proposal for the schedule for the analysis from p.abcock and Wilcox (B&W). The proposal contains the standard lower loop configuration and modifications to incorporate DB-1 raised loop design. The proposal must be evaluated as it relates to DB-1.
At the present time we.are in an outage which requires manpower and resources allocation and therefore we cannot meet the August date. Toledo Edison plans to submit the plans and schedule by September 30, 1983.
Very truly yours,
/f
= = -
RPC: GAB:lah A046 cc: DB-1 NRC Resident Inspector s