Suppl to Part 21 & Deficiency Rept Re Lambda Power Module Failures.Initially Reported on 801218.ACZ6 Capacitor Substituted for C6 Capacitor.Corrective Action & Final Rept by 840601
ML20079N610
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 01/23/1984
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
REF-PT21-84-270-000 PT21-84-270, PT21-84-270-000, NUDOCS 8401300275
Download: ML20079N610 (1)


Text

A TENNESSEE' VALLEY AUTHORITY CH ATTANOOGA/ TENNESSEE 374ol 400 Chestnut Street Tower II

' "l 25 48u.ag3, 1984 BLRD-50-438/81-05 BLRD-50-439/81-06 U.S. Nuclear Regulatory Commission Region II Attn:

Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, h"4, Suite 2900 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

-BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - LAMBDA POWER MODULE FAILURES -

BLRD-50-438/81-05, BLRD-50-439/81 SUPPLEMENTAL REPORT The subject deficiency was initially reported to NRC-0IE Inspector R. W. Wright on December 18, 1980 in accordance with 10 CFR 50.55(e) as NCR BLN EEB 8006. This was followed by our first Interim report dated January 19, 1981; our final report dated July 21, 1981; our revised final report dated March 23, 1982; our second revised final report dated June 17, 1982; and our supplemental reports dated September 27, 1982; and April 11 and September 12, 1983 As discussed with NRC-0IE Inspector P. E. Fredrickson on January 12, 1984, the date of January 15, 1984 for completion of corrective actions indicated in our final report on this matter would not be met. TVA has discovered that an ACZ6 capacitor has been substituted for a C6 capacitor in the power supplies. A nonconformance was written to document this discrepancy with the recommendation that the power supplies be reworked by the vendor. The corrective action on this matter will be completed by June 1,1984. We consider 10 CFR Part 21 applicable to this deficiency.

If you have any questions concerning this matter, please get in touct with R. H. Shell at FTS 858-2688.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Ma ger Nuclear Licensing cc:

Mr. Richard C. DeYoung, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Records Center OFFICIAL COPY Institute of Nuclear Power Operations

_f27 j0 1100 Circle 75 Parkway, Suite 1500 f

g Atlanta, Georgia 30339 8401300275 840123 7 PDR ADOCK 05000438 An Equal opportunity Empioyer O