Corrected Monthly Operating Repts for Dec 1994 for Point Beach Nuclear Plant
ML20078R069
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/31/1994
From: Koudelka M
WISCONSIN ELECTRIC POWER CO.
To:
Shared Package
ML20078R066 List:
References
NUDOCS 9502220195
Download: ML20078R069 (9)


Text

OPERATING DATA REPORT DOCKET NO. 50-266 DATE:

02/07/95 COMPLETED BY:

M.

B.

Koudelka M 'Q.0 0 01 TELEPHOIE:

414 755-6480 N

OPEPATING STATUS DM no

1. UNIT NAME:

POINT BEACH NUCLEAR PLANT - UNIT 1

. NOTES X Ut

2. REPORTING PERIOD: December - 1994 og
3. LICDiSED THERMAL POWER (MWT)-.

1518.5 4.

NAMEPLATE RATING (GROSS MWE):

523.8 OM

5. DESIGN ELECTRICAL RATING (NET MWE):

497.0

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

509.0.

n My

7. MAXIMUM DEPDIDABLE CAPACITY (NET MWE) -

485.0 8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST hEPORT, GIVE REASONS:

NA 9.

POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA

10. REASONS FOR RESTRICTIONS, (IF ANY) :

NA THIS MONTH YEAR TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 744.0 8,760.0 211,728.0
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 8,134.6 176,853.5
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 667.3
14. HOURS GENERATOR ON LINE 730.1 8,072.2 173,712.4
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 846.9
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,096,4'.s2 12,063,227 245,544,997
17. GROSS ELECTRICAL ENERGY GEIERATED 371,760 4,084,520 82,938,650
18. NET ELECTRICAL ENERGY GENERATED (MWH) 356,154 3,905,061 79,060,651
19. UNIT SERVICE FACTOR 98.1%

92.1%

82.0%

20. UNIT AVAILABILITY FACTOR 98.1%

92.1%

82.4%

21. UNIT CAPACITY FACTOR (USING MDC NET) 98.7%

91.9%

76.6%

22. UNIT CAPACITY FACTOR (USING DER NET) 96.3%

89.7%

75.1%

23. UNIT FORCED OUTAGE RATE 0.0%

0.0%

1.5%

24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

Refueling, 03/11/95, 36 days

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBE't 22, 1977

I Docket No.

50-266 POINT BEACH NUCLEAR PLANT Unit Name Point Beach, Unit 1 January 5,1995 Date UNTT SIIITFDOWNS AND POWER REDUCTIONS Completed By _ M. B. Koudetka Telephone No.

414 055-6480__ _

REPORT MONTH DECEL1BER - 1994 l

^

I Method of Cause ard Corrective Action Shumng Licensee Event System Component To Prevent Recurrence Duration Down Report No.

Code

  • Code' 2

s No.

Date Type' Olours)

Reason p egng Furmanite repair performed on a leaking lower stearn generator handbole.

4 12-31 S

t3.9 B

5 NA CB IITEXC11

' Exhibit G - Instructions

' Method:

'F: Forced 2 Reason:

for preparation of 1 - Manual 5: Scheduled A - Equipment Failure (exphin) data entry sheets 2 - Manual Scram B - Maintenance or Testing LER file (NUREG-0161) 3 - Automatic Scram C - Refueling 4 - Continuation of D Regulatory Restriction Previous %utdown E - 09erator Training &

5 - Reduced Load Licensing Exam 5 Exhibit I - Same Source 6 - Other (explain)

F - Administrative G - Operational Error (explain)

II - Other (explain)

PBF4Jo28b (03 90)

2 4

POINT BEACH NUCLEAR PLANT DOCKET NO.

50-266 Point Beach, bnit 1 -.

AVERAGE DAILY UNIT POWER LEVEL UNIT NAME

!..on1 H DECEMBER -

1994 DATE January 5,1995-COMPLETED BY M. B. Koude?ka TELEPHONE (414)755-6480 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1

494 11 494 21 496 2

494 12 493 22 496 3

494 13 493 23 496 4

483 14 494 24 495 5

494 15 496 25 465 6

493 16 495 26 494 7

494 17 494 27 495 8

494 18 497 28 495 9

493 19 495 29 494 10 493 20 496 30 488 l

31 52 l

l

7 DdCKET NO.

50-266 UNIT NAME Point Beach Unit 1 DATE January 5, 1995 COMPLETED PY M. B. Koudelka TELEPHONE 414/755-6480 r

Unit 1 operated at an average of 479 MWe net for the report period.

Safety-related maintenance included:

r 1.

1B04 480 V safeguards load center cable ZB1B17BH lugged and meggared.

2.

1B52-10B power to P35A electric fire pump amptector retrofit upgrade.

3.

CO2 main control board new jumper wire installed.

4.

C22 battery room HVAC control panel light socket and bearing replacements.

5.

D07 DOS dc station battery charger adjusted and rewired.

6.

G02 emergency diesel generator air inlet louvers inspected and filed.

7.

1N46 power range comparator channel deviation alarm adjusted.

8.

1P2A charging pump packing replaced.

9.

P32C service water pump packing adjusted.

10.

P32E service water pump packing repaired.

11.

P38B auxiliary feedwater motor-driven pump oil sampled, pump inspected and cleaned.

12.

PI-3909 P70B fuel oil transfer pump discharge pressure indicator snubber replacement.

13.

1PT-940 T34A safety injection accumulator pressure transmitter high pressure alarm adjusted.

14.

ISI-825B T13 refueliry water storage tank outlet to P15A&B safety injection pump valve inspected and cleaned.

15.

1SI-826A&B P15A&B safety injection pump suction from boric acid storage tank series and parallel isolation valves inspected and cleaned.

=-

I 1

ISI-870A P14A containment spray pump suction from T13 refueling

~

16.

water storage tank valve inspected and cleaned.

SW-658 HX-13A&B spent fuel pool heat exchanger return drain 17.

cleaned and. rethreaded valve outlet cap.

SW-2869-O north header to west header service water valve 18.

operator adjusted.

TS-4899 and TS-4903 primary auxiliary building battery rooms A 19.

and B alarm / control temperature switch calibrations.

i t

4 6

i 4

OPERATING DATA REPORT DOCKET NO. 50-301 DATE:

01/05/95 COMPLETED BY:

M.

B.

Koudelka

~ '

/-

TELEPHONE:

414 755-6400 OPERATING STATUS

1. UNIT NAME:

POINT BEACH NUCLEAR PLANT - UNIT 2 NOTT',

2. REPORTING PERIOD: December - 1994
3. LICENSED THERMAL POWER (ifdT) -

1518.5 4.

N7.MEPLATE RATING (GROSS MWE) 523.8

5. DESIGN ELECTRICAL RATING (NET MWE);

497.0 6.

MAXIMUM DEPENDABLE CAPACITY (GROSS MWF) 509.0.

7. MAXIMUM DEPENDABLE CAPACITY (NET MWL):

485.0 8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA 9.

PGWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE)-

NA

10. REASONS FOR RESTRICTIONS, (IF ANY)

NA THIS MONTH YEAR TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 744.0 8,760.0 196,513.0
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 7,851.0 172,051.6
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 233.9
14. HOURS GENERATOR ON LINE 744.0 7,828.0 169,694.7
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 302.2
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,115,420 11,610,741 243,981,925
17. GROSS ELECTRICAL ENERGY GENERATED 377,210 3,926,850 82,951,110
18. NET ELECTRICAL ENERGY GENERATED (MWH) 361,051 3,749,875 79,080,515
19. UNIT SERVICE FACTOR 100.0%

89.4%

86.4%

20. UNIT AVAILABILITY FACTOR 100.0%

89.4%

86.5%

21. UNIT CAPACITY FACTOR (USING MDC NET) 100.1%

88.3%

82.4%

22. UNIT CAPACITY FACTOR (USING DER NET) 97.6%

86.1%

81.0%

23. UNIT FORCED OUTAGE RATE 0.0%

0.0%

1.0%

24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

NONE

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977 l

1

POINT BEACH NUCLEAR PLANT Docket No.

50-301 Unit Name Point Beach. Unit 2 UNIT SIIttrDOWNS AND POWER REDUCTIONS Date January S.1995 Completed By _ M. B. Koudelka REPORT MONTil DECEMBER - 1994 Telephone No.

414/755 4280 t

Method of Shutung Cause and Correcnve Action Licensee Evern System Cornponent Duration po,.n No.

Date Type' Olours)

Reasots' p.x,p Report No.

Code' Code' To Prevent Recurrence i

NA NA NA NA NA NA NA NA NA NA I

' Exhibit G - Instructions

' Method:

'F: Forced 2 Reason:

S: Scheduled A - Equiptnent Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing-2 - Manual Scr:un data ent y sheets 3 - Automatic Scram LElt nie (NUREG4)161)

C - Refueling 4 - Continuation of D - Regulatory Restriction Previous Shutdowm E - Operator Training &

5 - Reduced 1. cad Licensing Exam F - Administrative 6 - Other (explain) 5 Exhibit I - Same Source G - Operational Error (explain)

II - Other (explain)

PDF-0028b i U TU)

1 I

POINT BEACH NUCLEAR PLANT DdCKET NO.

50-301 AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point Beach Unit 2 MONTH DECEM8ER -

1994 DATE January 5,1995 t

COMPLETED BY M. B. Koudelka

)

TELEPHONE (414)755-6480 t

AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY

[

POWER LEVEL POWER LEVEL POWER LEVEL

.j DAY MWe NET DAY MWe NET DAY MWe NET b

1 474 11 486 21 486 2

487 12 485 22 487 3

491 13 485 23 486 4

487 14 484 24 486 5

483 15 486 25 486 1

1 6

487 16 484 26 486 7

487 17 483 27 486 8

486 18 486 28 487 i

9 485 19 484 29 484 10 486 20 485 30 486 31 485 i

i i

6

[

DOCKET NO.

50-301 I UNIT NAME Point Beach Unit 2 DATE December 6, 1994 COMPLETED BY M.

B. Koudelka TELEPHONE 414/755-6430 Unit 2 operated at an average of 485 MWe net for the report period.

Licensee Event Report 50-301/94-005-00, Violation of Technical i

Specifications Table 15.3.5-2 Overtemperature AT Minimum Degree of Redundancy Not Achieved, was submitted.

Safety-related maintenance included:

[

2C'l-283B P2B charging pump discharge to T4 volume control 1.

tank relief. valve replacement.

2CC-744A HX-8B boric acid evaporator component cooling 2.

i supply valve bushing replaced.

2DY-01 Red 125 Vdc/120 Vac inverter contact burnished and 3.

bench tested.

4.

2FI-607 and 2FI-116 flow indicators retubed.

5.

2RH-626 HX-11A&B residual heat removal heat exchanger bypass flow control valve local position indicator installed.

t 6.

2P11B component cooling water pump inboard / outboard seals and bearings replaced.

-