ML20078Q357

From kanterella
Jump to navigation Jump to search
Reactor Containment Bldg ILRT Braidwood Nuclear Power Generating Station Unit 2,941027-1109
ML20078Q357
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 02/09/1995
From:
COMMONWEALTH EDISON CO.
To:
Shared Package
ML20078Q335 List:
References
NUDOCS 9502210217
Download: ML20078Q357 (59)


Text

_ __

D REncam camneaur Buuman  ;

INTEGRATED LEAK RATE TEST  ;

D J

BRAIDHOOD NDCLEAR POWER GENERATING STATICN l I

Comed /Uniccxn Company UNIT 2  !

J October 27th to November 9th, 1994 l

)

l l

f

) >

l I

o

) l i

) I

)

0:\depts\rd79g\1.upf

) 9502210217 950209 PDR ADDCK 05000457 i p PDR

O, UNIT 2 ILRT FINAL REPORT O-TABLE OF CONTERES M -

0 INTRODUCTICN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ........................... 1 A. TEST PREPARATIONS .................................................. 2 A.1 Type A Test Procedure ......................................... 2 A.2 Type A Test Program .......................... ............... 2 A.3 Pre-Test Containment Structural Examination . . . . . . . . . . . . . . . . . . . 2 O A.4 Type A Test Instrumentation ....................... ........... 2

a. Temperature
b. Pressure
c. Relative Humidity
d. Flow A.5 Type A Test Subvolume Determination ........................... 3 A.6 ILRT Plant System Lineu .. ................................... 7

^7 TYP* ^ T**' ""*"8""i*^'p*"* ~~~~''''''''''''''''''''''''''7 O

B. TEST METHOD ................................... .................... 7 )

B.1 Statistical Analysis Technique ........................ ...... 7 B.2 Supplemental Verification Test (Induced Leak Rate) . . . . . . .......7 O C. SEQUENCE OF EVEtES ............. .............. .................... 8 C.1 Pretest Preparations ...... .... .................. ......... 8 l C.2 Containment Pressurization .................................... 9 <

C.3 Temperature Stabilization .............. ................. ... 10 l C.4 Statistical Leak Rate Test .............. ................... 10 C.5 Induced Leak Rate Test ............ ....... ................... 11 O C.6 Depressurization and Post Activities ..... .................... 11 D. ILRT DATA ............. ....... ..... ............................. 12 D.1 Temperature Stabilization Data ................................ 12 D.2 Statistical Leak Rate Test .. ... ........................... 12 D.3 Induced Leak Rate Test ........................................ 12 O E. TEST CALCULATIONS ...................................... ........ .. 28 F. TEST RESULTS AND IIEERPRETATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 9 l 1

1 F.1 Statistical Leak Rate Test Results ..... .................... 29 '

F.2 Induced Leak Rate Test ........................................ 30 g F.3 Comparison to Previous ILRT Results.... ................... ... 31 F.4 Type B and C Test Results from A2R04... ............ .......... 32 F.5 Type B and C Test Results from A2R03........................... 32 W

o:\depts\rd79g\1.wpf 11 O

i 1

9s l i

UNIT 2 ILRT FINAL REPORT l

i 0 j TABLE OF CONIENTS  !

PAGE APPENDIX A Instrumentation Specifics ....... ..... .. .. . . .......... 33

$ APPENDIX B Statistical Leak Rate Test Analysis Methods ... . ...... 34 i APPENDIX C Temperature Stabilization Data . . . . . .. .... .. . . .35 APPENDIX D Statistical Leak Rate Test Data ..... . . . ....... .. ... .36 l

APPENDIX E Induced Leak Rate Test Data . . .. ... ..... ..... . ... 37 l i

S APPENDIX F Type A Test Corrections . . . ... . . .. .... . . .38 1

APPENDIX G Type B and C Local Leak Rate Data . .. .... . . . ... .40 b l J

D 1

l i

l l

1 l

l l

)

l l

o;\depts\zd79g\1.wpf iii

)

)+ l l

UNIT 2 ILRT FINAL REPORT

)

LIST OF FIGURES l

NUMBER TITLE PJ G A.5.1 Containment Building Sensor Placenent and 4 Subvolume Identification frcm Elevation p 426 to Top of Containment A.5.2 Containment Building Sensor Placement and 5 Subvolume Identification from Elevation  ;

398.5 to 426 A.5.3 Containment Building Sensor Placement and 6 i Subvolume Identification from Elevation 1 377 to 398.5

)

D.1.1 Temperature Stabilization Parameters for 13 Temperature Sensors D.1.2 Temperature stabilization Parameters for 14 RH Sensors D.1.3 Containment Mass during Temperature 15 Stabilization ,

D.2.1 Statistical Leak Rate Mass Point Leak and 16 Mass Point Leak at UCL D.2.2 Containment Mass during the Statistical 17 Leak Rate D.2.3 Containment Average Pressure during the 18 Statistical Leak Rate 1 l

D.2.4 Containment Average Temperature during the 19 l Statistical Leak Rate D.2.5 Containment Average Dew Point during the 20 Statistical Leak Rate D.2.6 Containment Average Vapor Pressure during the 21 Statistical Leak Rate D.3.1 Verification (Induced) Mass point leak 22 D.3.2 Containment Mass during the Induced Leak Rate 23 l D.3.3 Containment Average Pressure during the Induced 24 Leak Rate D 3.4 Containment Average Temperature during the Induced 25 Leak Rate D.3.5 Containment Average Dew Point during the Induced 26 Leak Rate D.3.6 Containment Average Vapor Pressure during the Induced 27 Leak Rate  !

l l

i I

i o:\depts\2d799\1.wpf iv i I

).

UNIT 2 ILRT FINAL REPORT

) LIST OF TABLES Table 1 Data sets for Temperature Stabilization 6 pages after Appendix C

) Table 2 Statistical Mass Point Leak Rate Analysis 7 pages after Appendix D Table 3 Statistical Leak Rate data sets containing Pressure, Temperature and Dew Point Table 4 Induced Mass Point Leak Rate data sets 2 pages after

) Appendix E Table 5 Induced Leak Rate data sets containing Pressure, Temperature and Dew Point

)

l

)

)

l I

)

?

o:\depts\rd79g\1.wpf V

)

).

UNIT 2 ILRT FINAL REPORT

)

INTRODUCTICN This report describes the Second Type A Containment Leakage Rate Test conducted af ter the initiation of comercial service for the Braidwood Nuclear

)

Power Station Unit 2 containment building. This report is prepared pursuant to the requirements of 10CFR50 Appendix J, Section V.B.3. The test was l conducted through the perfomance of Braidwood Procedure 2BWVS 6.1.2.a-1, l " Unit 2 Prima Containment Type A Integrated Leakage Rate Test", dated October 27th h November 9th, 1994. local Leak Rate Testing required to determine the fina values of containment leakage were performed between September 10th through November 15th, 1994. Also included in this report is a

) summary report of all the periodic Type B and C Local Leakage Rate Tests that were performed since the last Type A ILRT performed on September 12th through November 16th, 1991.

The Type A test was performed at the end of the refueling outage. All local leak rate test were performed in the beginning of the outage, with the exception of the ones isolated during the ILRT. Those penetrations were

) re-tested to determine the final leak rate of containment.

The test was perfomed in accordance with 10CFR50 Appemdix J, and the Braidwood Station Technical Specifications. The test method that was used was the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Mass Plot Method During pressurization leak checks were conducted in all penetration 3 areas and both Equipment and Emergency hatches. Some leakage paths were

/ identified and at the time considered not to be significant. Once containment cest pressure was reached and temperature stable the computer results of the total containment leakage rate exceeded the 0.75L . a The identified leakage paths were isolated one at a time and each isolation was given sufficient time for containment to stabilize. With the identified leakage paths isolated the total containment leak rate was below

) 0.75L,.

Approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into the test it was observed that data had not been collected for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 45 minutes and it was determined to stop the test. Found instrumentation problem and restarted test after repairs.

The test was then successfully continued until completion. The isolated

) pathways were left isolated during the entire test. A Minimum Pathway As Found penalty was later assessed for each penetration isolated.

Using the Mass Plot Method the total primary containment leak rate was calculated to be less than the allowable leak rate of 0.075wt%/ day (0.75L ) .

The leakage rate was calculated to be 0.04853 wt%/ day at a test pressure greater than 45.4 psig (P ) . The associated 95% Upper Confidence Limit (UCL) was 0.04944 wt%/ day.

l The verification induced leak rate test result was measured at 0.1285 wt%/ day. This compares with the sum of the measured leak rate phase result (0.04853 wt %/ day)and the induced leak of 7.8 scfm (0.1010 wt%/ day) .

The ecmposite leak rate of 0.1285 wt%/ day lies within the allowable tolerance band of 0.14953 wt%/ day 2. 0.025 wt%/ day.

l 0:\depts\zd799\1.wpf pg 1

q a.

UNIT 2 ILRT FINAL PEPORT n

LJ Before and after the ILRT, LLRTs were ptrformed. The results from some of these test are added to the final ILRT total as the corrective leak rate.

These are added for the systems that were not properly challenged during the ILRT. The AS FOUND minpath leakage for all corrections was 17.3 scfh or 0.00373 wt%/ day. Adding this leakage to the ILRT 95% UCL yields a total of 0.05317 wt%/ day which is less than the 0.075 wt%/ day acceptance criteria.

q s

A. TEST PREPARATIONS A.1 TYPE A TEST PROCEDURE

.g The ILRT was performed in accordance with Braidwood Procedure 2BWVS 6.1.2.a '., Revision 1. Temporary Procedure Changes were made to the procedure to correct for typos, add or delete steps to ensure the proper execution of the test. The original intent of the surveillance was never change.

A.2 TYPE A TEST PROGRAM AND DATA PROCESSING g The program used for this test is the Duke Power Integrated Leak Rate program Rev 1.75, software ID# GN09405. Containment parameters were acquired by the program every 10 minutes. This included data set number, time, temperature, relative humidity in degree F and absolute pressure readings.

The data was sent to a personal lap top computer via proper computer cables.

The computer stored the data everytime the data was collected and every 30 minutes the data was manually stored to disc. Personnel monitored the data either in araph form or numerical. Each data set was real time, this O facilitateil the identifications of trends as they developed.

A.3 PRE-TEST COtEAINMETE STRUCIURAL EXAMINATION Prior to the containment pressurization, a visual examination of all accessible interior and exterior surfaces was performed. The results of this inspection were compared to the findings of the structural inspection

$ performed during A2R02. No degradation of the containment structure, was noticed since the previous inspection was performed.

A.4 TYPE A TEST INSTRUMETEATION

a. Temperature Thirty-one thermistors were used through out the containment. Type G Graftel smart sensor model 9202. All sensors were calibrated using standards traceable to the National Bureau of Standards (ISS).
b. Pressure Two Paroscientific Precision absolute pressure monitors model 760-100-A range 0-100 psia. Calibrated using standards traceable to the National Bureau of Standards (NBS)

O

c. Relative Humidity Nine relative humidity sensors were used through out the containment.

Type Graftel smart sensor model 9203. All sensors were calibrated using standards traceable to the National Bureau of Standards (?BS),

d. Flow g One flowmeter was used for the induced leakage rate tested. Type Fisher-Porter model 10A3555-S range 0-10.2 scfm. Calibrated using standards traceable to the National Bureau of Standards (NBS).

o:\oepts\rd79 9\1.wpf pg 2 9

i

).

UNIT 2 ILRT FINAL REPORT J

A.5 TYPE A TEST SUBVOLUME DETERMINATION The containment is divided into 9 discrete subvolumes. Subvolume demarcation, size and weighing factors are indicated in Figures A.5.1 through A.5.3, also shown on the figures are the temperature and relative humidity sensors placed in containment. The

) installed in the auxiliary building. pressure monitors and the flowmeter were

)

J-

)

)

)

)

)

o:\depts\rd79g\1.wpt pg 3

).

UNIT 2 IIRT FINAL REPORT '

(

) N E 596' Subvolume #1 QH1 417880 cubic feet 15.12%

H Q2) GQ 555.281' Subvolume #2 470388 cubic feet 17.03%

)

H2]

" kS) k6) _ 524.7241 Subvolume #3 464803 cubic feet lH3l 16.82%

(7) h (9) 494.333' Subvolume #4 451546 cubic feet l H4 l 16.34%

8 ee 465 Subvolume #5 462583 cubic feet Hs 16.74%

) L",3J bb 426' Relative humidity sensor (H) ,

) O Tempereture sen or (T)

)

)

Figure A.5.1 Containment building sensor placement and subvolume identification from elevation 426 to top of containment.

)

o:\depts\rd79 9\1.wpf pg 4

)

4

).

UNIT 2 ILRT FINAL REPORT J

l ELEVATION 398.5' TO 426'

)

R 32 D

l H9 l j

R 27 g SUBVOLUME 7 @ Q R 38 l H6 l SUB UME 6 I

T19 R 22 Subvolume 6: 154567 cubic feet 5.60%

Subvolume 7: 123669 cubic feet 4.48%

b l l Relative humidity r,ensor ( H )

O Temperature ser.sor (T)

Figure A.5.2 Containment building sensor placement and subvolume identification from elevation 398.5 to 426.

)

0:\depts\rd79 9\1.wpf pg 5

)

)e UNIT 2 ILRT FINAL REPORT J

ELEVATION 377' TO 398.5' R 32 l H7 lh SIG SIG 2C 2B

) @ @ SUBVOLUME 9 Q Q R 38  !

l SIG SIG l H8 l '

2D 2A J s SUBVO UME 8 T23 R 22 9,

)  %

Subvolume 8: 120846 cubic feet 4.37%

Subvolume 9: 96688 cubic feet 3.50%

)

l l Relative humidity sensor (H)

O Temperature sensor (T)

)

Figure A.S.3 Containment building sensor placement and subvolume identification from elevation 377 to 398.5.

o:\depts\rd79g\1.wpf pg 6

)

UNIT 2 IIRT FINAL REPORT A.6 ILRT PI1MI' SYSTEM LINEUP The valve and equipment lineups were detailed and specified by component with individual signoffs. This ensured containment integrity conditions as close as possible to those which would exist after a design basis loss of

) Coolant Accident (LOCA) . This also assured that penetrations were properly drained and vented. Since the, ILRT was perfonned at the end of the outage 3 penetrations were not properly challenged. This was due to the amount of water and time it would take to p.operly align the penetrations.

A penalty was assessed for these penetrations.

A.7 TYPE A TEST PRESSURIZATION

) To pressurize containment to full test pressure, a system of 11 diesel driven, oil free compressors were used. The compressors were located outside on the northeast side of the containment building. Pressurization was accomplished through a six inch header which penetrates containment at penetration P-4. Once the containment was pressurized, the pressurization header was isolated and vented.

)

B. TEST METHOD B.1 STATISTICAL ANALYSIS TEO NIQUE

) The absolute method of leak rate detennination was used. The absolute method uses the ideal gas laws to calculate the measured leak rate, as defined in ANSI N45.4-1972. The inputs to the measured leak rate calculation include subvolume weighted containment temperature, subvolume weighted vapor pressure, and total absolute air pressure.

B.2 SUPPLEMENTAL VERIFICATION TEST (Induced Leak Rate)

)

The supplemental verification test is perfonned by intentionally inducing a controlled leak of a magnitude approximately equal to L. (0.1 wt%/ day). This induced leak is superimposed on the previously detennined leak rate (Statistical Test) and compared with the leak rate calculated during the Statistical leak rate phase. The combined leak rate (calculated leak rate from Statistical Test plus the induced leak rate) provides a basis for

) resolving any uncertainty associated with the calculated leak rate of the statistical leck rate test. The acceptance criterion for the induced leak rate shall be within 10.251,4 of the sum of the statistical leak rate and the flowmeter induced leak rate.

)

?

o:\depts\rd79g\1.wpf pg 7

)

O.

UNIT 2 ILRT FINAL REPORT O

C. SEQUENCE OF EVENTS The following narrative describes the sequence of events associated with the ILRT.

C.1 i> RETEST PREPARATICN D

DATE 10/27/94 0755 Started system line ups DATE 10/31/94

] 2220 Operations opened 2CC9413B to fill and vent CC system . Testing in progress tag retroved.

DATE 11/1/94 1115 2RE022 put in close position to drain reactor cavity. Testing in progress tag removed. Need to repeat pages D-42 and D-43 when system status allows.

3 DATE 11/2/94 0925 2SI8964,2FE8888 and 2SI8880 were stroked for indication test BwVS 0.5-2.SI.3 then put in the close:d position for final ILRT lineups. They are with in the isolation boundary so they had no g effects on draining of system.

2300 Data sheets 1.15.2-D page D-42 and 1.15-F page D-43 were reperformed to ensure FC return line to the refueling cavity has been completely drained. A small amount of water came out of 2RE022. This water partially refilled the subsystem during containment decon activities. A drain hose is still connected downstream of 2RE022 and will need to be removed prior to containment pressurization.

DATE 11/3/94 0800 Contacted.MMD to remove Containment Pressurization Penetration blind flange. Contacted Containment Coordinator to perform walkdown to look for any items that may be a pressurization source into containment (fire extinguishers, pressurized cans etc).

D 1330 2LT-RYO49 was valved in by opening 2RY106A,B,C and E per BwOP RC-4 1405 2CV8105 and 2CV8106 were opened to fill pressurizer following head vents.

1426 Closed 2CV8105 and 2CV8106.

1450 Call Security at 2828 to request access to Emergency Hatch if leak checks are required.

DATE 11/4/94 0150 Called Tide Air technician to look over the compressors prior to start.

)

o:\depts\rd79g\1.wpf pg 8

)

3 UNIT 2 ILRT FINAL REPORT

)

0325 Water discovered coming out to 2RE012 vent in the Unit 2 curve wall area. Valve was isolated and further isolation points are being pursued. Water coming from unit 1 RCUT pump down to the Huts, suspect unit cross-tie valves are leaking by.

) 0330 Tide-Air Rep completed inspection of compressor equipment.

Everything sat. need 15 minutes to warm up prior to press up.

0407 Decision made to close and cap 2RE011 AND 2RE012 for penetration

11. Due to problems isolating water frun the test zone. Suspect valve 2AB8551 is leaking by. Action request written.

) 0437 Notified by work control to continue with procedure if blocking attempts of 2RY455A were unsuccessful. Rescind TPC 6947.

0443 Notified (0437 entry by) .work control to disregard previous direction C.2 COtEAINMEtE PRESSURIZATION

)

DATE 11/4/94 0557 Started pressurizing containment. Data set 61 0553 0710 Randy Krbec working with compressor rep to optimize pressurization rate.

)

0720 Contacted work planning to generate Action Request for repacking of 2RY455A.

0815 Contacted HELP desk regarding access for work groups to curve wall area. Determination made to totally restrict access.

) 1100 Backed up data in computer (backing up hourly). Started leak checks l in curve wall area.

1130 Rad protection started collecting air sample of containment.

1145 Contacted operations to have operators check closed 2CV8399, 2CV8396A and 2SI8965A/B.

)

1615 Report from compressor skid 2 compressors tripped due to clogged fuel filters. Filters replaced and compressors restarted.

1620 Compressors fuel tanks topped off. Vender truck ran out of fuel.

The lith compressor was topped off with Ceco fuel truck.

) 1815 Shutdown 2 compressors at 59.8 psia. Wanted to gradually reach 61.3 psia.

1825 Shutdown 2 more compressors. Pressure 60.2 psia.

1848 Closed OVQ002, 2VQO11 and 2VQO12 Shutdown all compressors pressure 61.31 psia.

) 1855 Vented containment pressurization line by opening OVQ003 and renoving the pipecap downstrer '

valve.

o:\depts\rd799\1.wpf P9 9

)

).

UNIT 2 IIRT FINAL REPORT

) C3 TEMPERATURE STABILIZATION 1954 Started temperature stabilization Data Set 197 2030 Closed and capped 2SIO56 for penetration 55. Valves 2 SIB 880 and

. 2SI8968

) 2120 Decided to see if leak on penetration 55 was from containment or nitrogen supply to SI accumulators. Put balloon back on 2SIO56 and opened valve. Closed down on 2 SIB 965A/B, verified that leak was from the nitrogen supply because balloon wasn't filling up like before. 2 SIB 965A/B were leaking by.

) DATE 11/5/94 0150 Equipment hatch inner door shaft seal leak discovered. Outer equipment hatch door closed and inner door opened.

0210 Outer equipment hatch door snooped for leaks, none found.

0240 Emergency hatch snooped for leaks, none found.

)

0445 Isolated PS vent valve 2PS133 at penetration 70. Containment isolation valves being tested 2PS9355A/B.

l 0530 Isolated CS vent valve 2CS084A at penetration 1. Containment  !

isolation valves being tested 2CS007A and 2CS008A.  !

) 0615 Air identified coming out of the Mainsteam vent valve 2MS0022A.

Not apparent whether air is leaking from containment at this time, i Closing vent would fail test, left open. j Locked out temperature sensor T26 and replaced with T27.

[ C.4 STATISTICAL LEAK RATE TEST 0725 Started leak rate test at data set 268 1030 Checked Emergency hatch for leaks, none found.

1100 When calling NSO to get cold cal and RH temperatures, NSO stated that data trend shows .5% increase in 2D steam generator water level. High pressure clean-up is in progress. ops will try to

) secure high pressure clean-up or try to isolate flowpath. A,B and C steam generators levels will be trended by ops.

1130 Stopped test due to Instrument malfunction.

]

1200 NSO report that high pressure clean-up is secured and that all steam generator levels are stable.

) 1251 Restarted test with data set 291, after instrument repairs made.

(replaced black box (signal converter)) .

1312 Had Rad Protection take air samples of the Mainsteam isolation valve rooms. Reports negative results frcxn samples.

)

1332 Monitored leak rate program, data looks good might try a 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> test.

o:\depts\rd79g\1.wpf pg 10

)

).

UNIT 2 ILRT FINAL REPORT

)

1745 Isolated seal return 2CV063 vent to check effect on leak rate penetration 28. Due to large air leak occurred.

DATE 11/6/94

) 0413 Data set 1 minute late due to files being copied to floppy disk.

0530 Received phone call from Unit 2 Supervisor on pulling chemistry sample from the operating RH train. Told Ops to pull sample, No effects expected on ILRT.

1312 Statistical test ccmplete with data set 437.

) C.5 I"DUCED LEAK RATE TEST 1322 Started Induced Leak rate stabilization with data set 438.

Flow rate from flowmeter 7.8 scfh.

1422 Started Induced leak rate test flow remained the same.

1812 Ended test Induced leak rate is complete with data set 467.

1815 Notified shift engineer to start depressurization of containment C.6 DEPRESSURIZATICN AND POST ACI'IVITIES 1926 Started depressurization of containment with one sparger valve open.

)

1930 Opened 2nd sparger valve.

1935 Opened 3rd sparger valve.

2010 Opened 4th sparger valve.

) 2115 Opened 5th sparger valve. l 2125 Opened 6th sparger valve.

DATE 11/7/94 0800 Started restoration of system lineups.

DATE 11/9/94 0800 Signed out of procedure.

DATE 11/11/94

) 0800 Reviewed results from procedure.

1415 Data looks good procedure complete.

Last entry into log.

o:\depts\rd79g\1.wpf pg 11

)

).

UNIT 2 ILRT FINAL REPORT

)

D. ILRT DATA A temperature survey of the containment was performed prior to the pressurization of containment. Each subvolume was surveyed in at least one

) location with a maximum of three taken per subvolume.

SUBVOLUME OBSERVED NUMBFR TEMPERATURE 1

2 67.8 68.2 67.3

) 3 69.7 68.3 68.3 4 68.2 68.8 68.4 5 68.5 68.2 68.2 6 67.5 67.6 67.3 7 68.5 68.4 68.4 8 65.6 67.1 66.8 9 65.8 65.7 65.7

)

The following sections present computer data for the three main sections of the ILRT.

D.1 TEMPERATURE STABILIZATION DATA

)

The temperature stabilization phase demonstrated proper temperature stability prior to the beginning of the test. The thermal parameters are graphically shown in Figures D.1.1, D.1.2 and D.1.3 with respect to pressure and mass in containment. A summary of the computer data can be found in Appendix C.

) D.2 STATISTICAL LEAK RATE TEST DATA I Graphic results of the measured leak rate test are found in Figures D.2.1 through D.2.6. A summary of the computed data using the MASS PIar METHOD can be found in Appendix D.

D.3 INDUCED LEAK RATE TEST DATA

)

The calculated leak rate and target value leak rates associated with the induced leakage test are shown in Figure D.3.1. Containment conditions during this phase of the test are shown in Figures D.3.2 through D.3.6. A summary of the Induced Leak Rate data of the IIRT can be found in Appendix E.

)

c:\depts\rd79g\1.wpf pg 12

)

i. ..

).

UNIT 2 IIRT FINAL REPORT

)

) ,3. , 4 .. 1. ,. o,. *- .

\

72.5 - - 60.84

)

72.0 - , - 60.78 I

) 71.5 -

- 60.71 9

a p 71.0 - - 60.65 y e

)

70.5 - - 60.59 s

70.0 - - 60.53

)

s 69.5 - - 60.46

)

69.0 , , , , , , , , 60.40 0 1 2 3 4 5 6 7 8 Time - Hours l

)

) Figure D.1.1 Tenperature Stabilization Parameters for Ternperature Sensors with respect to Oantainment Pressure.

o:\depts\ad79s\1.upf P9 13

) 1

O.

INIT 2 ILRT FINAL REPORT S

8 Avwege Dow PoiM  !

64.7 Aww Pressure i

\

64.6 -

- 60.84

\

\

64.4 -

- 60.78 r

) ,

64.3 -

, - 60.71 i

P i F 04 2 - *

) - 60.65 64.0 - 'N - 60.59

)

's 63.9 -

N

  • 60.53 I

\ N ' ,

63.7 -

- 60.46

)  %

63.6 ,

60.40

, , , i . . .

0 1 2 3 4 5 6 7 s Time - Hours

]

Figure D.1.2 T rature Stabilization Parameters for RH Sensors D wi respect to Containment Pressure, o:\cepts\ad79s\1.upf P9 14 l D

LNIT 2 IIRT FINAL REPORT D

a *** 60.M 848625

)

848420 - \ - 60.84 848215 - - 60.78 848010 - -

~ "*7 I

) 'N I

\ P \

l '

s b 847805 _

- 60.65 g m a

's

.59

) 847599 - '.

g N N s s 847394 - - 60.53 x

~

847189- 'N '

N N

846984 , , , , , , , 60.40

} 0 1 2 3 4 5 6 7 8 Time . Hours J

Figure D.1.3 Temperature Stabilization Parameter for (bntairrtent

) Mass with respect to Containment Pressure.

o:\depts\rd79g\1. gf pg 15 D

l O.

UNIT 2 ILRT FINAL REPORT D

r O.50 0.30 "***

-0.44 0.26 -

h  !

l -0.38 0.23 - '

f i i

-0.31 0.19 - .

% I i ,

-0.25 d d 0.15 - I -e a '

Y l

-0.19 0.11 -

i I

h---------------------------------------------------------------------------------- -0.13 i

p 0.08 --

p\ _ _ -

. ~~~. _ - - .. _..__ _ g, n,_

D

, , , 0.00 0.00 , , , , , , , , ,

8 12 14 16 18 20 22 24 0 2 4 6 to Time Hours J

Figure D.2.1 Statistical leak Rate Mass Point Ieak and Mass Point Icak at UCL.

o:\depts\rd79sst.ipf pg 16 D

I J.

UNIT 2 ILRT FINAL REIORT

)

)

846800 846700 -

)

846600 -

I b

b 846500 -

)

846400 -

)

l 846300 , , , , , , , , , , , ,

0 2 4 6 8 10 12 14 16 18 20 22 24 l Time . Hours

)

l Figure D.2.2 ContairuTent Mass during the Statistical Leak Rate.

c:\depts\ad79g\1.wpf pg 17

)

1 1

O, 1 UNIT 2 ILRT FINAL REPORT b

60.380

]

60.370 -

60.360 -

P s

i e

)

(

60.350 - N 3 60.340 -

) 60.330 -- , , , , . > > > > >

20 22

=

24 6 8 to 12 14 16 18 0 2 4 Twne . Hours J

Figure D.2.3 Cantairnent Average Pressure during the Statistical Leak Rate.

)

c \depts\rd79g\1.wpf pg 18

)

-_-_-__-_--_-______-______________n

).

[ NIT 2 IIRT FINAL REPORT

)

) 69.48 - .-

/ ,

69.47 -

) 69.46 -

l 69.45 -

69.44 -

p 69.43 -

sw 69.42 -

I \

"c- y l lh 69.40 -

k 1 69.39 -

D 69.38 , , , , , , , , , , ,

22 24 8 10 12 14 16 18 20 0 2 4 6 Tome . Hours J

Mgue D.2.4 " "

  • 7 S s bI k$t 7 o: W pts \rd79e\1. $ pg 19 D

2 UhIT 2 ILRT FINAL REPORT

)

)

64.080

\

64.070 -

J ,a l V f 64.050 -

64.040 - p f

r / \

64.030 -

64.020 - j

(

64.010 -

64.000 - q l '

)

63.990 , , , , i i i

10 12 14 16 18 20 22 24 O 2 4 6 8 Time - Hours

) Figure D.2.5 Cantainment Statistical Leak Averabete.Dew Point during the I j

o:\deptr\rd79g\1.upf pg 20

)

I

___ j

LNIT 2 IIRT FINAL REPORT D-0.2958 h

0.2957 -

0.2956 -

0.2955 - h b l

(

O.2954 -

0.2953 - ff p h /

0.2952 -

.G 0.2951 -

n f( ,

l 0.2950 -

0.2949 -

D 4 6 8 1O 12 14 16 18 20 22 24 0 2 Twne . Hours D

Figure D.2.5 t r Vapor Pressure during the o:\depts\rd79g\1.npf pg 21 J

L) .

[ NIT 2 ILRT FINAL REPORT q_,

) 0.20

.....___. __..........____.. g........_....._ -......_............--..--....._____......-..____...

9

/ /

/

.A /

.)

/

I d 0.10 -

C Y

1 3

J 1

l b 4 01 , , , , , , , , , , , , , , ,

0.0 0.3 0.5 0.8 1.0 1.3 1.5 1.8 2.0 2.3 2.5 2.8 3.0 3.3 3.5 3.8 Time - Hours Figure D.3.1 Verification test Mass Point Leak (Irxhiced Test) .

o:\depts\ad79 3\1. gf pg 22 3

4 l

l

- ________ _ ______ ___________________________a

4

).

LNIT 2 ILRT FINAL REPORT

)

)

)

846300 f

)

I 846200 - /

) /

I '

b m

)

846100 -

)

)

846000 , , , , , , , , , , , , , , ,

0.0 0.3 0.5 0.8 1.0 1.3 1.5 1.8 2.0 2.3 2.5 2.8 3.0 3.3 3.5 3.8 Time - Hours

)

) Figure D.3.2 Contaiment Mass during the Induced Imak Rate.

o:\depts\ad79g\1.wpf pg 23

)

1

).

LNIT 2 IIRT FINAL REPORT

?

) _ _ _ _

60.340

)

N

) N P m,

'N s 's w 60.330 -

I

) 0 l

)

. . , , i 60.320 , , , , , ,

2.5 2.8 3.0 3.3 3.5 3.8 0.8 1.0 1.3 1.5 1.8 2.0 2.3 O.0 0.3 0.5 Time Hours

)

Figure D.3.3 Containment Average Pressure during the

?

Induced Icak Rate, c:\depts\td79g\1,upf pg 24

)

).

UNIT 2 ILRT FINAL REPORT

) 69.440

)

69.430 -

i

)

p 69.420 -

)

69.410 -

)

)

69.400 i , , , , , , , , i , , , , ,

0.0 0.3 0.5 0.8 1.0 1.3 1.5 1.8 2.0 2.3 2.5 2.8 3.0 3.3 3.5 3.8 Time - Hours

)

i l

Figure D.3.4 Containment Average Temperature during

) the Induced Leak Rate.

o:\depts\rd79g\1. ef pg 25

)

l s

O. ,

I LNIT 2 ILRT FINAL REPORT f

r) i i

) j 64.110 1 J .

64.100 - '

i

) \. >

64.090 -

F .

)

64.080 -

l ,

S 64.070 -

t D

I 3 8 I I I u v I i 1 y u  !

0.0 0.'3 0.5 0.8 1.0 1.3 1.5 1.8 2.0 2.3 2.5 2.8 3.0 3.3 3.5 3.8 Time Hours i i

S I Figure D.3.5 Cantainment Average Dew Point during 5 the Indaced leak Rate.

c:\depts\ad79g\1. ,f pg 26

l

),

UNIT 2 ILRT FINAL REPORT

)

) 0.29610 0.29600 -

\

) 0.29590 -

P s

i 0

) 0.29580 -

)

0.29570 -

I

)

0.29560 , , , , , , , , , , , . . , ,

0.0 0.3 0.5 0.8 1.0 1.3 1.5 1.8 2.0 2.3 2.5 2.8 3.0 3.3 3.5 3.8 Trne - Hours

)

l Figure D.3.6 Contairunent Average Vapr Pressure

) during the Induced Icax Rate.

o \depts\td799\1.wpf pg 27

)

1

)

UNIT 2 ILRT FINAL REPORT

)

E. TEST CAICUIATIONS Calculations for the test were based on Braidwood Station procedure 2BWS 6.1. 2.a-1. A reproduction of the compilations is found in Appendix B.

) Braidwood performed the Mass Plot Method test Using Mass Point calculations, l

)

)

1 1

\

l o:\depts\rd799\1.wpf pg 23

Q UNIT 2 ILRT FINAL REPORT f

a l

F. TEST RESULTS AND INTERPRETATIONS F.1 STATISTICAL LEAK RATE TEST RESULTS

)

l The "AS FOUND" statistical average leak rate (95% UCL) before any corrections was 0.04944 wt%/ day. The "AS LEFT" statistical average leak rate (95% UCL) after corrections was 0.05317 wt%/ day.

l Containment dry air temperature and relative humidity trended downward throughout the test. This is indicative of a stable containment with no major heat sources as the reactor coolant was kept reasonably constant throughout the test. Measured tank and containment sump levels were not significantly changed from the beginning to end of test.

l There was two instrument failures. One was temperature sensor which was blocked and replaced with one near by (T26 was replaced with T27). The other failure was signal converter box (black Box) had a erroneous malfunction which resulted in restarting the statistical test.

)

l Durir ressurization a number of leakage The l magnitudeok$eakagefromthesepathscouldnotbthswereidentified. quantified by visual observation, although they appeared to be small. It was decided to continue  !

with the pressurization and measure the total containment leakage rate once l containment pressure was reached and stable. After the containment reached f

test pressure the total containment leak rate exceeded 0.75L,. Looking for penetrations that were potential leakers we came across some slight leaks, the following were found: P-1, P-11, P-28, P-70 and the equipment hatch inner / outer door were swapped. Penetration P-70 has 4 lines that go through that penetration 1 of the 4 was isolated due to the leakage being excessive.

Penetration P-28 was the major source of leakage.

The penetrations were isolated one at a time and the effects on the

) total containment leakage rate was observed. With the isciation of the penetration P-70, P-11, P-1 and the swapping of the equipment hatch doors the leakage rate was still above the .75I S. It was only after the isolation of penetration P-28 did the leakage rate fall below .75L .

The test was then successfully continued until completion. The isolated pathways were left isolated during the entire test. A Minimum Pathway As Left penalty was later assessed for each of these pathways and for the pathways

) that were not lined up for the ILRT (P-21, P-24 and P-25) . Other penalties were added to the ILRT for the penetrations that were repaired during the refuel outage.

{ It is CtmEds policy to Type A test containments in as close to the Post f

LOCA condition as possible. The pathways were left isolated in this case for the fr2 lowing reasons:

D For all cases, there were no direction dependency concerns. The leakage measured by the T, C tests performed after the Type A test can in all cases clearly be s.own to yield results conservative relative to what would have been the;r actual contribur.icns had they remained open during the Type A test.

) h cumulative effect of suddenly opening all the pathways may have had the effect of destabilizing the containment atmosphere. This would have both e.: tended the test duration and reduced the quality of the results.

o:\depts\rd79g\1.wpf pg 29

UNIT 2 IIRT FIIAL REPORT

)

It is always desirable to minimize the number of valve manipulations during ILRTs. This reduces the potential for line up errors and other unforeseen problems.

) F.2 DECED LEAK RATE TEST The Induced test was performed following the Statistical test which was performed in a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mass plot leak rate test. After a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period for stabilization of the known induced leak the induced test was started. The Induced test was completed in approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> with successful results.

The statistically averaged composite leak rate was verified to be stable ard

) within f. 0.254 of the sum of the statistically averaged measured leak rate and the average flowmeter induced leak rate. No abnormal containment response or significant events occurred during this test.

The results are as followed:

The initial imposed leak (4) rate as indicated on the flowmeter 7.8 sefm.

) The revised leak rate (4) as calculated was 7.8 scfm.

1/2 Pc T.

4=4 -

P. Te

?

where Pc = calibrated pressure, psia (from flowmeter) 14.7 psia P, = fluid pressure used during test, psia (flowmeter discharge pressure)

) Te = calibrated temperature, "R ( F + 459.7) (from flowmeter)

T, = fluid temperature used during test, R ( F + 459.7) (flowmeter discharge temp) 4= flow recorded from instrument, scfm 4= corrected flow N 4 or 7.72 scfm

)

To correct for differences in actual versus calibrated fluid temperature and pressure the following is used:

Tc tra P.

4=4 -

  • Pc T.

Corrected imposed leak rate (4) = 7.8 scfm

)

0:\depts\rd79 9 \1.wpf pg 30

)

).

UNIT 2 ILRT FINAL REPORT

)

To convert the Is from SCFM to wt%/ days the following equation is used:

Is scfm * .1%/ day 7.72

) The target induced leak rate I+ was .1010 %/

The measured induced leak rate 1% was .07997 % day The measured composite least square statistical leakage rate (I , 0.04853 S

% day) including the imposed target leak rate (Is .1010 %/ day) = I+ 0.14953

% day.

3 The measured composite least sguare statistical leakage rate (I+, .04853

) including the measured imposed leak rate (I+ .07997 %/ day) = I+ .1285 The measured leak rate value is within the combined statistical leak rate and the target leak rate value. The leakage is between the acceptable limits of the required tolerances of i .25 1 .

)

(le + Is, - . 25

  • I ) s Ig s (le + I+, + . 25
  • I S)

.12453 s .14953 s .17453

) where le = measured composite least square statistical leakage rate including the i p sed leak rate. .

I+ = imposed leak rate 15 = maximum allowable leak rate of the containment at 45.4 psig (.1

%/ day).

) IS , = the final statistical leak rate measured.

F.3 COMPARISON 'ID PREVIOUS TEST RESULTS This was the third ILRT performed at Braidwood Unit 2. The previous test

) was perfonned September 12 to November 16, 1991 which was the first refuel outage for Braidwood Unit 2.

The statistical average containment leakage rate during the 1991 test was 0.0527 wt%< day after a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Mass Plot test. The 95% upper confidence limit of the extainment leakage rate was 0.05359 wt%/ day.

) The induced leak rate during the 1991 test was .1471%/ day after 1.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. This was within the 0.25 La of the sum of the statistical average leakrate and the induced leak rate.

)

c:\depts\rd79g\1.wpf pg 31

)

. ~. . .. .. ._- _ . - _ _

.0, IRJIT 2 IIRT FINAL REPORT l

O I I

F.4 TYPE B AND C TEST RESULTS FOR A2R04 Local leak rates performed during A2R04 can be reviewed in Appendix G.

F.5 TYPE B AND C TEST RESULTS FOR A2R03 O

Local leak rates perfonned during A2R03 can be reviewed in Appendix G.

r O

i b

'O l

i I

i O

i f

f O  !

I f

t O i O  !

O i

-i i

i i

o:\depts\rd79g\1.wpf pg 32  ;

O

l UNIT 2 ILRT FINAL REPORT

) I APPENDIX A - INSTRUMENT SPECIFICATION  ;

L The computer used is a 486/25ms lap top with a mathico processor and nodem.  !

) Instruments used :

31 Graftel model 9202 temperature sensors range 32-150 F accuracy i .5 degree F .

9 Graftel model 9203 relative humidity sensors range 30-90%  !

) accuracy i 5%

2 Paroscientific precision pressure monitors nodel 760-100-A range 0-100 psia accuracy 1 .020% of span 1 Fisher Porter flowmeter model 10A3555-S range 0-10.2 scfm accuracy 1 1% max flow ,

)

)  :

f

)  !

i i

1

)

)

r o:\depts\rd79g\1.wpf pg 33

)

O, UNIT 2 IIRT FINAL REPORT O

APPENDIX B STATISTICAL LEAK RATE TEST ANALYSIS METHODS Mass Point Calculations b

l This method calculates the rate of change with respect to time of dry air mass using the Mass Point Method.

I 2400 M=1 (ti - tr) (1 - M 1/M,)

l m Then the least squares fit 95% UCL of the Mass Point Leakrates are calculated H as shown below.

k -Ab, B= ,

C (NkM - kh) 3 A=

N2 (t ) 2 i (Lt i)2 D

l l N= Number of data sets to be Least Squares Fit.

L = B + At t O 1.6559 (N-1) + 3.5283 + 0.85602/(N-2)

(N-1) + 1.2209 - 1.5162/ (N-2)

NOTE N is the number of data sets minus one.

] UCL = L + 'IU o:\depts\rd79 9\1.wpf pg 34 D

).

UNIT 2 ILRT FINAL REPORT 1

)

APPENDIX C TEMPERATURE STABILIZATION DATA I

The following tables present the data for the temperature stabilization

) phase of the IIRT. The temperature stabilization phase is defined as data collected from data sets 197 to 250. The following data is included:

1. Containment Pressure in psia
2. Containment Temperature in deg F
3. Containment Dew point in deg
4. Containment Mass

)

I l

(

i

)

i

)

) l l

l

)

1

)

c:\depts\rd79g\1.wpf pg 35

)

Tomparatura Stabilization " " " "

BRAIDWOOD UNIT 2 RDG TIME Comp 1 Comp Comp

) Press 1 1 197 Nov 0419:54:12 6D.'87 72.71 67.B7 198 Nov 04 20:04:12 60.83 7f.*46 6f77 199 Nov 04 20:14:13 60.80 72.25 63.89 200 Nov 04 20:24:13 60.78 72.07 63.96 201 Nov 04 20:34:13 60.75 71.91 64.06

) 202 Nov 04 20:44:14 60.73 71.76 64.08 203 Nov 04 20:54:14 60.71 71.63 64.11 204 Nov 04 21:04:14 60.70 71.51 64.23 205 Nov 04 21:14:15 60.68 71.40 64.23 206 Nov 04 21:24:15 60.66 71.28 64.26 207 Nov 04 21:34:15 60.65 71.21 64.35

) 208 Nov 04 21:44:16 60.64 71.15 64.38 209 Nov 04 21:54:16 60.63 71.08 64.43 210 Nov 04 22:04:17 60.62 71.03 64.50 211 Nov 04 22:14:17 60.61 70.96 64.54 212 Nov 04 22:24:17 60.60 70.90 64.57

) 213 Nov 04 22:34:17 60.59 70.85 64.62 214 Nov 04 22:44:18 60.59 70.79 64.57 215 Nov 04 22:54:18 60.58 70.75 64.57 216 Nov 04 23:04:18 60.57 70.70 64.59 217 Nov 04 23:14:19 60.57 70.64 64.59 218 Nov 04 23:24:19 60.56 70.60 64.59

) 219 Nov 04 23:34:19 60.55 70.56 64.56 220 Nov 04 23:44:20 60.55 70.52 64.55 221 Nov 04 23:54:20 60.54 70.49 64.50 222 Nov 05 00:04:31 60.54 70.45 64.48 223 Nov 05 00:14:32 60.53 70.41 64.48 224 Nov 05 00:24:32 60.53 70.38 64.45

)

225 Nov 05 00:34:32 60.52 70.35 64.42 226 Nov 05 00:44:33 60.52 70.32 64.43 227 Nov 05 00:54:33 60.52 70.28 64.44 228 Nov 05 01:04:33 60.51 70.25 64.42 229 Nov 05 01:14:34 60.51 70.23 64.40 p 230 Nov 05 01:24:34 60.50 70.21 64.40 231 Nov 05 01:34:34 60.50 70.18 64.40 232 Nov 05 01:44:35 60.50 70.14 64.38 233 Nov 05 01:54:35 60.49 70.12 64.38 234 Nov 05 02:04:35 60.47 70.06 64.36 235 Nov 05 02:14:36 60.47 70.06 64.40

) 236 Nov 05 02:24:36 60.46 70.04 64.35 237 Nov 05 02:34:36 60.46 70.02 64.35 238 Nov 05 02:44:37 60.46 70.01 64.35 239 Nov 05 02:54:37 60.46 69.99 64.35 240 Nov 05 03:04:37 60.46 69.97 64.35

j. 241 Nov 05 03:14:38 60.45 69.96 64.32 242 Nov 05 03:24:38 60.45 69.94 64.30 243 Nov 05 03:34:39 60.45 69.92 64.31 244 Nov 05 03:44:39 60.45 69.91 64.32 245 Nov 05 03:54:40 60.44 69.90 64.32

)

a Tomparatura Stabilization ' * ' " '

BRAIDWOOD UNIT 2 RDG TIME Comp 1 Comp Comp O P,re,ss _1 _1, ,

246 Nov 05 04:04:40 60.44 69.89 64.31 l 247 Nov 05 04:14:41 60.44 69.87 64.29 '

248 Nov 05 04:24:41 60.44 69.85 64.28 249 Nov 05 04:34:42 60.43 69.83 64.25 ,

250 Nov 05 04:44:42 60.43 69.83 64.26 o i i

O i

O ,

i 3

p 1

3- Mcss Plot during Tamparaturo Stabilizatiorf"'"

BRAIDWOOD UNIT 2 RDG TIME Mass

) 197 Nov 0419:54:12 Ibm 848533.33 198 Nov 04 20:04:12 848436.98 199 Nov 04 20:14:13 848345.56 200 Nov 04 20:24:13 848259.47 201 Nov 04 20:34:13 848179.17

) 202 Nov 04 20:44:14 848109.64 203 Nov 04 20:54:14 848046.80 204 Nov 04 21:04:14 847985.22 205 Nov 04 21:14:15 847920.16 206 Nov 04 21:24:15 847897.73 207 Nov 04 21:34:15 847817.96 7 208 Nov 04 21:44:16 847756.53 209 Nov 04 21:54:16 847710.28 210 Nov 04 22:04:17 847656.64 211 Nov 04 22:14:17 847627.15 212 Nov 04 22:24:17 847594.93 213 Nov 04 22:34:17 847552.15 214 Nov 04 22:44:18 847546.17 215 Nov 04 22:54:18 847510.44 216 Nov 04 23:04:18 847490.44 217 Nov 04 23:14:19 847493.24 q 218 Nov 04 23:24:19 847473.87

> 219 Nov 04 23:34:19 847460.61 220 Nov 04 23:44:20 847450.90 221 Nov 04 23:54:20 847441.56 222 Nov 05 00:04:31 847426.77 223 Nov 05 00:14:32 847418.93 224 Nov 05 00:24:32 847404.64

) 225 Nov 05 00:34:32 847400.21 226 Nov 05 00:44:33 847394.23 227 Nov 05 00:54:33 847401.71 f 228 Nov 05 01:04:33 847386.95 l

229 Nov 05 01:14:34 847372.29 230 Nov 05 01:24:34 847353.83 231 Nov 05 01:34:34 847350.31 232 Nov 05 01:44:35 847354.80 233 Nov 05 01:54:35 847296.55 234 Nov 05 02:04:35 847093.57 235 Nov 05 02:14:36 847064.80 236 Nov 05 02:24:36 847066.12 237 Nov 05 02:34:36 847070.44 238 Nov 05 02:44:37 847047.61 239 Nov 05 02:54:37 847051.93 240 Nov 05 03:04:37 847044.98 241 Nov 05 03:14:38 847027.54

)

242 Nov 05 03:24:38 847027.30 243 Nov 05 03:34:39 847021.61 244 Nov 05 03:44:39 846999.83 245 Nov 05 03:54:40 846997.22

)

3- Mess Plot during Tomparaturo Stabilizatiorf"'

BRAIDWOOD .

UNIT 2 l RDG TIME Mass

) 246 Nov 05 04:04:40 Ibm 846980.47 247 Nov 05 04:14:41 846976.95 248 Nov 05 04:24:41 846986.40 ,

249 Nov 05 04:34:42 846986.31 250 Nov 05 04:44:42 846962.80  !

)

)

)

)

) I

)

UNIT 2 ILRT FINAL REPORT

)

APPENDIX D STATISTICAL LEAK RATE TFST DATA The following tables present the data for the leak test phases of the ILRT using the Mass Plot Method. The measured leak test is defined as the

) interval between data sets 291 to 437 inclusive. This corresponds to a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and 21 minute test duration. The following data is included:

1. Containment Mass Point Leak Rate
2. Containment Average Pressure in psia
3. Containment Average Temperature in deg F

) 4. Containment Average Dew Point in deg F

)

)

)

o:\depts\rd79g\1.wpf pg 36

)

~)-

Mass Point Laak Roto Anclysis " " " ' '

BRAIDWOOD UNIT 2 RDG TIME (MINUTES) NORM. MASS MEASURED LEAK (WT UCL LEAK (WT O  %/ DAY)  %/ DAY) 291 0.00 1.000000 - -

292 10.70 0.999984 0.211422 -

293 20.70 0.999964 0.250717 0.453674 294 30.72 0.999990 0.073800 0.382692 9 295 40.72 0.999973 0.070098 0.213897 296 50.72 0.999992 0.020197 0.125878 297 60.73 0.999960 0.049601 0.128328 298 70.73 0.999957 0.060700 0.118747 299 80.73 0.999969 0.050941 0.096123

_ 300 90.75 0.999975 0.038109 0.076115 J

301 100.75 0.999957 0.041337 0.072138 302 110.75 0.999929 0.056993 0.087197 303 120.77 0.999936 0.061374 0.087084 304 130.77 0.999931 0.064452 0.086537 305 140.77 0.999944 0.060115 0.079636 306 150.78 0.999939 0.057551 0.074731 307 160.78 0.999941 0.053917 0.069444 308 170.78 0.999921 0.055547 0.069386 309 180.80 0.999914 0.057389 0.069863 310 190.80 0.999912 0.058378 0.069609 9 311 200.80 0.999887 0.062997 0.074131 312 210.82 0.999902 0.063227 0.073324 313 220.82 0.999891 0.064341 0.073604 314 230.82 0.999892 0.064454 0.072927 315 240.83 0.999878 0.065826 0.073723 316 250.83 0.999877 0.066459 0.073762 I

] 317 260.83 0.999897 0.064144 0.071271 318 270.85 0.999874 0.064289 0.070898 319 280.85 0.999877 0.063635 0.069813 320 290.85 0.999867 0.063635 0.069394 321 300.87 0.999863 0.063545 0.068926 .

, 322 310.87 0.999847 0.064462 0.069581 l 323 320.87 0.999838 0.065587 0.070515 1 324 330.88 0.999855 0.064963 0.069637 325 340.88 0.999831 0.065740 0.070208 326 350.88 0.999834 0.065887 0.070105 327 360.90 0.999833 0.065803 0.069790 g 328 370.90 0.999828 0.065780 0.069555 329 380.90 0.999833 0.065225 0.068845 330 390.92 0.999818 0.065317 0.068754 331 400.92 0.999800 0.066059 0.069405 i 332 410.92 0.999829 0.065084 0.068406 l 333 420.93 0.999797 0.065509 0.068702 i O

9

3- Mass Point Loak Rato Analysis BRAIDWOOD UNIT 2 RDG TIME (MINUTES) NORM. MASS MEASURED LEAK (WT UCL LEAK (WT

)  %/ DAY)  %/ DAY) 334 430.93 0.999778 0.066494 0.069687 335 440.93 0.999839 0.064622 0.068172 336 450.95 0.999773 0.065429 0.068912 337 460.95 0.999778 0.065776 0.069126

) 338 470.95 0.999802 0.065033 0.068322 339 480.97 0.999778 0.065074 0.068227 340 490.97 0.999776 0.065023 0.068049 341 500.97 0.999772 0.064956 0.067863 342 510.98 0.999764 0.065000 0.067794 343 520.98 0.999781 0.064408 0.067156 344 530.98 0.999767 0.064141 0.066799 345 541.00 0.999755 0.064112 0.066673 346 551.00 0.999749 0.064118 0.066587 347 561.00 0.999750 0.064001 0.066385 348 571.02 0.999748 0.063828 0.066135 349 581.02 0.999741 0.063732 0.065962 350 591.02 0.999739 0.063600 0.065759 351 601.03 0.999743 0.063274 0.065385 352 611.03 0.999730 0.063168 0.065213 353 621.03 0.999750 0.062560 0.064625

) 354 631.05 0.999742 0.062080 0.064132 355 641.05 0.999714 0.062119 0.064108  ;

356 651.05 0.999730 0.061765 0.063723 1 357 661.07 0.999714 0.061663 0.063565 358 671.22 0.999718 0.061416 0.063277 359 681.22 0.999696 0.061491 0.063299  ;

) 360 691.23 0.999709 0.061273 0.063042 361 701.23 0.999727 0.060689 0.062497 362 711.23 0.999702 0.060492 0.062259 363 721.25 0.999708 0.060157 0.061906 364 731.25 0.999698 0.059935 0.061650 365 741.27 0.999700 0.059631 0.061325

) 366 751.27 0.999681 0.059579 0.061229 367 761.27 0.999697 0.059242 0.060881 368 771.27 0.999677 0.059154 0.060753 1

369 781.28 0.999685 0.058904 0.060480 370 791.28 0.999671 0.058799 0.060339

) 371 801.28 0.999684 0.058476 0.060010 ,

372 811.30 0.999655 0.058504 0.060000 '

373 821.30 0.999657 0.058455 0.059915 374 831.30 0.999684 0.058033 0.059515 375 841.32 0.999666 0.057806 0.059270 376 851.32 0.999667 0.057534 0.058987

)

3- Mass Point Loak Rato Analysis BRAIDWOOD UNIT 2 RDG TIME (MINUTES) NORM. MASS MEASURED LEAK (WT UCL LEAK (WT

])  %/ DAY)  %/ DAY) 377 861.32 0.999657 0.057350 0.058780 378 871.33 0.999654 0.057164 0.058573 379 881.33 0.999644 0.057058 0.058438 i

380 891.33 0.999645 0.056898 0.058257

) 381 901.35 0.999639 0.056777 0.058110 ,

382 911.35 0.999662 0.056388 0.057745 383 921.50 0.999666 0.055949 0.057342 384 930.37 0.999639 0.055764 0.057139 385 940.37 0.999632 0.055620 0.056973 386 950.37 0.999634 0.055426 0.056763 387 960.38 0.999620 0.055339 0.056652 388 970.38 0.999628 0.055149 0.056448 l 389 980.38 0.999631 0.054913 0.056206  !

390 990.40 0.999620 0.054756 0.056032 391 1000.40 0.999602 0.054725 0.055976 392 1010.40 0.999636 0.054388 0.055656 393 1020.42 0.999619 0.054170 0.055431.

394 1030.42 0.999607 0.054030 0.055274 395 1040.42 0.999619 0.053777 0.055021 396 1050.43 0.999600 0.053657 0.054883

) 397 398 1060.43 1070.43 0.999583 0.999600 0.053644 0.053477 0.054847 0.054668 l 399 1080.45 0.999599 0.053302 0.054484 400 1090.45 0.999576 0.053272 0.054432 401 1100.45 0.999581 0.053184 0.054326

]

402 1110.47 0.999586 0.053036 0.054167

) 403 1120.47 0.999586 0.052876 0.053997 404 1130.47 0.999590 0.052670 0.053789 <

405 1140.48 0.999569 0.052588 0.053691 i 406 1150.48 0.999569 0.052488 0.053576 l 407 1160.48 0.999593 0.052217 0.053317 408 1170.50 0.999568 0.052094 0.053182

) 409 1180.50 0.999557 0.052020 0.053092 .

410 1190.50 0.999559 0.051920 0.052978 l 411 1200.52 0.999550 0.051855 0.052897 l

412 1210.52 0.999549 0.051779 0.052807 l 413 1220.52 0.999571 0.051561 0.052593

) 414 415 1230.53 1240.53 0.999566 0.999563 0.051359 0.051161 0.052393 0.052196 416 1250.53 0.999558 0.050986 0.052018 417 1260.55 0.999552 0.050829 0.051856

'418 1270.55 0.999533 0.050761 0.051774 i 419 1280.57 0.999554 0.050568 0.051582 I

) 1 1

1 I

l

)

l Mess Point Loak Rate Analysis 3-BRAIDWOOD UNR 2 RDG TIME (MINUTES) NORM. MASS MEASURED LEAK (WT UCL LEAK (WT

) ,  %/ DAY)  %/ DAY) 420 1290.57 0.999546 0.050408 0.051418 421 1300.57 0.999524 0.050348 0.051345 422 1310.58 0.999534 0.050222 0.051211

, 423 1320.58 0.999512 0.050194 0.051168

) 424 1330.58 0.999564 0.049899 0.050899 425 1340.60 0.999522 0.049799 0.050789 426 1350.60 0.999530 0.049651 0.050636 427 1360.60 0.999512 0.049578 0.050551 428 1370.62 0.999513 0.049487 0.050450 429 1380.62 0.999513 0.049384 0.050339

)

430 1390.62 0.999507 0.049298 0.050242 431 1400.63 0.999517 0.049158 0.050098 432 1410.63 0.999483 0.049153 0.050080 433 1420.63 0.999516 0.048996 0.049922 434 1430.65 0.999509 0.048859 0.049782 435 1440.65 0.999481 0.048828 0.049738 436 1450.65 0.999501 0.048704 0.049610 437 1460.67 0.999510 0.048537 0.049444

)

)

)

)

?

)

3 '"*""

Statistical Lcck Rota Tost Data BRAIDWOOD UNIT 2 RDG TIME Comp 1 Comp Comp D Press 1 1 291 Nov 0512:51:35 6D.'37 69.47 64.D4 292 Nov 0513:02:17 60.37 66.~48 6s.04 293 Nov 0513:12:17 60.37 69.48 64.05 294 Nov 0513:22:18 60.37 69.46 64.06 295 Nov 0513:32:18 60.37 69.47 64.06 3 296 Nov 0513:42:18 60.37 69.45 64.06 297 Nov 0513:52:19 60.37 69.46 64.06 298 Nov 0514:02:19 60.37 69.46 64.05 299 Nov 0514:12:19 60.37 69.45 64.03 300 Nov 0514:22:20 60.37 69.44 64.02 a

301 Nov 0514:32:20 60.37 69.44 64.01 302 Nov 0514:42:20 60.37 69.45 64.02 303 Nov 0514:52:21 60.37 69.45 64.01 304 Nov 0515:02:21 60.37 69.44 64.02 305 Nov 0515:12:21 60.37 69.43 64.03 306 Nov 0515:22:22 60.37 69.43 64.04 3 307 Nov 0515:32:22 60.36 69.42 64.03 308 Nov 0515:42:22 60.36 69.43 64.02 ,

309 Nov 0515:52:23 60.36 69.43 64.02 l 310 Nov 0516:02:23 60.36 69.43 64.01  !

311 Nov 0516:12:23 60.36 69.44 64.04

, 312 Nov 0516:22 24 60.36 69.42 64.04 '

i J 313 Nov 0516:32:24 60.36 69.43 64.04 314 Nov 0516:42:24 60.36 69.42 64.03 315 Nov 0516:52:25 60.36 69.43 64.02 316 Nov 0517:02:25 60.36 69.42 64.01 317 Nov 0517:12:25 60.36 69.41 64.00 g 318 Nov 0517:22:26 60.36 69.41 64.02 l 319 Nov 0517:32:26 60.36 69.41 64.01 <

320 Nov 0517:42:26 60.36 69.41 64.02 l l

321 Nov 0517:52:27 60.36 69.41 64.01 l 322 Nov 0518:02:27 60.36 69.41 64.01 323 Nov 0518:12:27 60.36 69.41 64.02 D 324 Nov 0518:22:28 60.36 69.40 64.01 l 325 Nov 0518:32:28 60.36 69.41 64.02 1 326 Nov 0518:42:28 60.36 69.41 64.02 327 Nov 0518:52:29 60.30 69.41 64.01 328 Nov 0519:02:29 60.36 69.40 64.02 329 Nov 0519:12:29 60.36 69.40 63.99 3 330 Nov 0519:22:30 60.36 69.41 64.00 l 331 Nov 0519:32:30 60.35 69.41 64.02 332 Nov 0519:42:30 60.35 69.39 64.01 333 Nov 0519:52:31 60.35 69.41 64.01 I 334 Nov 05 20:02:31 60.35 69.42 64.03 335 Nov 05 20:12:31 60.35 69.38 64.00 336 Nov 05 20:22:32 60.35 69.41 64.03 337 Nov 05 20:32:32 60.35 69.41 64.02 338 Nov 05 20:42:32 60.35 69.39 64.01 339 Nov 05 20:52:33 60.35 69.40 64.03 D

Statistical Loak Rato Tost Data BRAIDWOOD UNIT 2 RDG TIME Comp 1 Comp Comp O P,ress _1 _1, 340 Nov 05 21:02:33 60.35 69.40 64.03 341 Nov 05 21:12:33 60.35 69.40 64.01 342 Nov 05 21:22:34 60.35 69.40 64.03 343 Nov 05 21:32:34 60.35 69.39 64.01 344 Nov 05 21:42:34 60.35 69.40 64.02 q

'" 345 Nov 05 21:52:35 60.35 69.40 64.02 346 Nov 05 22:02:35 60.35 69.40 64.02 347 Nov 05 22:12:35 60.35 69.40 64.03 348 Nov 05 22:22:36 60.35 69.40 64.03 349 Nov 05 22:32:36 60.35 69.39 64.04 O 350 Nov 05 22:42:36 60.35 69.39 64.05 351 Nov 05 22:52:37 60.35 69.39 64.04 352 Nov 05 23:02:37 60.35 69.40 64.03 353 Nov 05 23:12:37 60.35 69.39 64.03 354 Nov 05 23:22:38 60.35 69.39 64.02 355 Nov 05 23:32:38 60.35 69.40 64.04 U 356 Nov 05 23:42:38 60.35 69.39 64.05 357 Nov 05 23:52:39 60,35 69.40 64.05 358 Nov 06 00:02:48 60.35 69.40 64.04 359 Nov 06 00:12:48 60.35 69.41 64.03 360 Nov 06 00:22:49 60.35 69.40 64.04 q 361 Nov 06 00:32:49 60.35 69.39 64.03 s 362 Nov 06 00:42:49 60.35 69.40 64.03 363 Nov 06 00:52:50 60.35 69.39 64.03 364 Nov 06 01:02:50 60.35 69.40 64.04 365 Nov 06 01:12:51 60.35 69.39 64.03 366 Nov 06 01:22:51 60.35 69.40 64.03 o

367 Nov 06 01:32:51 60.35 69.39 64.03 368 Nov 06 01:42:51 60.35 69.40 64.03 369 Nov 06 01:52:52 60.35 69.40 64.03 l 370 Nov 06 02:02:52 60.35 69.40 64.04 371 Nov 06 02:12:52 60.35 69.39 64.02 l' 372 Nov 06 02:22:53 60.35 69.41 64.03 S 373 Nov 06 02:32:53 60.35 69.40 64.03 374 Nov 06 02:42:53 60.35 69.39 64.04 ,

1 37S Nov 06 02:52:54 60.35 69.40 64.03 I 376 Nov 06 03:02:54 60.35 69.40 64.03 377 Nov 06 03:12:54 60.35 69.40 64.03 378 Nov 06 03:22:55 60.34 69.40 64.03 0 379 Nov 06 03:32:55 60.34 69.40 64.05 380 Nov 06 03:42:55 60.34 69.40 64.04 381 Nov 06 03:52:56 60.34 69.41 64.03 382 Nov 06 04:02:56 60.34 69.39 64.03 383 Nov 06 04:13:05 60.34 69.39 64.02 g 384 Nov 06 04:21:57 60.34 69.40 64.03 385 Nov 06 04:31:57 60.34 69.41 64.05 386 Nov 06 04:41:57 60.34 69.40 64 05 387 Nov 06 04:51:58 60.34 69.41 64.06 388 Nov 06 05:01:58 60.34 69.40 64.06 O

M "*"

Statistical Loak Reto Test Data BRAIDWOOD UNIT 2 RDG TIME Comp 1 Comp Comp

) Qe,ss ,1 _1, 389 Nov 06 05:11:58 60.34 69.40 64.05 390 Nov 06 05:21:59 60.34 69.40 64.05 391 Nov 06 05:31:59 60.34 69.41 64.06 392 Nov 06 05:41:59 60.34 69.39 64.03 393 Nov 06 05:52:00 60.34 69.40 64.04 394 Nov 06 06:02:00 60.34 69.41 64.05 395 Nov 06 06:12:00 60.34 69.40 64.05 396 Nov 06 06:22:01 60.34 69.41 64.05 397 Nov 06 06:32:01 60.34 69.42 64.05 398 Nov 06 06:42:01 60.34 69.41 64.05

) 399 Nov 06 06:52:02 60.34 69.40 64.06 400 Nov 06 07:02:02 60.34 69.42 64.05 401 Nov 06 07:12:02 60.34 69.41 64.04 402 Nov 06 07:22:03 60.34 69.41 64.04 403 Nov 06 07:32:03 60.34 69.41 64.06 404 Nov 06 07:42:03 60.34 69.41 64.06

). 405 Nov 06 07:52:04 60.34 69.42 64.06 406 Nov 06 08:02:04 60.34 69.41 64.06 407 Nov 06 08:12:04 60.34 69.40 64.05 408 Nov 06 08:22:05 60.34 69.41 64.05 409 Nov 06 08:32:05 60.34 69.42 64.05 410 Nov 06 08:42:05 60.34 69.41 64.05 411 Nov 06 08:52:06 60.34 69.42 64.06 412 Nov 06 09:02:06 60.34 69.42 64.05 413 Nov 06 09:12:06 60.34 69.40 64.06 414 Nov 06 09:22:07 60.34 69.40 64.07 415 Nov 06 09:32:07 60.34 69.41 64.05

) 416 Nov 06 09:42:07 60.34 69.41 64.05 417 Nov 06 09:52:08 60.34 69.41 64.05 418 Nov 06 10:02:08 60.34 69.42 64.06 419 Nov 06 10:12:09 60.34 69.41 64.07 420 Nov 06 10:22:09 60.34 69.41 64.05 421 Nov 06 10:32:09 60.34 69.42 64.06

) 422 Nov 06 10:42:10 60.34 69.41 64.06 423 Nov 06 10:52:10 60.34 69.42 64.07 424 Nov 06 11:02:10 60.34 69.39 64.06 425 Nov 06 11:12:11 60.34 69.42 64.06 426 Nov 06 11:22:11 60.34 69.41 64.07

)

427 No 'r 06 11:32:11 60.34 69.42 64.05 428 Nov 06 11:42:12 60.34 69.42 64.06 429 Nov 06 11:52:12 60.34 69.41 64.06 430 Nov 06 12:02:12 60.34 69.41 64.06 431 Nov 06 12:12:13 60.34 69.41 64.07 432 Nov 06 12:22:13 60.34 69.43 64.08

, 433 Nov 06 12:32:13 60.34 69.41 64.06 434 Nov 06 12:42:14 60.34 69.41 64.06 435 Nov 06 12:52:14 60.34 69.43 64.06 436 Nov 06 13:02:14 60.34 69.41 64.07 437 Nov 06 13:12:15 60.34 69.41 64.07

)

O.

UNIT 2 ILRT FINAL REPORT q.)

APPENDIX E INDUCED LEAK PATE DATA The following tables present the data for the induced leakage phase of the ILRT. The induced leakage test is defined as the interval between data O sets 444 to 467 inclusive. This corresponds to a 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> and 50 minute test duration. The following data is included:

1. Containment Mass Plot Leak Rate
2. Containment Average Pressure in psia
3. Containment Average Temperature in deg F O 4. Containment Average Dew point in deg F  ;

.., 1 J

l i

l 1

l

\

~ ) l s,

J 9

9 o:\depts\rd79g\1.wpf pg 37 9

A Mcss Point Lock Rsto Analysis ' * " "

BRAIDWOOD UNIT 2 RDG TIME (MINUTES) NORM. MASS MEASURED LEAK (WT UCL LEAK (WT

)-  %/ DAY)  %/ DAY) 444 0.00 1.000000 - -

445 10.00 1.000000 0.003838 -

446 20.02 1.000002 -0.017195 0.086605 447 30.02 0.999971 0.121180 0.356844 r

) 448 40.02 0.999963 0.146492 0.260704 449 50.03 0.999955 0.150585 0.218460 450 60.03 0.999945 0.150769 0.196136 l 451 70.03 0.999914 0.176233 0.219592 452 80.05 0.999935 0.156100 0.195560 453 90.05 0.999932 0.139420 0.175132 454 100.05 0.999899 0.145528 0.174991 455 110.07 0.999890 0.148657 0.173115 456 120.07 0.999887 0.146811 0.167382 ,

457 130.07 0.999880 0.144353 0.162018  :

458 140.08 0.999875 0.141171 0.156716 459 150.08 0.999881 0.133737 0.149227 460 160.08 0.999862 0.131572 0.145344 461 170.10 0.999871 0.125410 0.139088 462 180.10 0.999841 0.125819 0.138016 463 190.10 0.999813 0.130101 0.141850 I

) 464 200.12 0.999839 0.126738 0.137855 465 210.12 0.999819 0.126062 0.136162 466 220.25 0.999810 0.125563 0.134774 467 230.13 0.999779 0.128488 0.137398

)

i l

j

A Induced Lock Reto Test Data " * " "

BRAIDWOOD l

UNIT 2  !

RDG TIME Comp 1 Comp Comp l

) 444 Nov 0614:22:17 Press 6D.'33 1

69.42 1

65.D7 l

445 Nov 0614:32:17 60.33 6ff41 6s.08  !

446 Nov 0614:42:18 60.33 69.41 64.06 i 447 Nov 0614:52:18 60.33 69.42 64.09 j 448 Nov 0615:02:18 60.33 69.42 64.09 i

)- 449 Nov 0615:12:19 60.33 69.42 64.07 '

450 Nov 0615:22:19 60.33 69.42 64.07 451 Nov 0615:32:19 60.33 69.43 64.08 452 Nov 0615:42:20 60.33 69.42 64.07 453 Nov 0615:52:20 60.33 69.41 64.08

) 454 455 Nov 0616:02:20 Nov 0616:12:21 60.33 60.33 69.43 69.43 64.09 64.11 l 456 Nov 0616:22:21 60.33 69.42 64.10 457 Nov 0616:32:21 60.33 69.42 64.10 458 Nov 0616:42:22 60.33 69.42 64.11 i 459 Nov 0616:52:22 60.33 69.41 64.09 I

) 460 461 Nov 0617:02:22 Nov 0617:12:23 60.33 60.33 69.42 69.41 64.08 64.08 i

462 Nov 0617:22:23 60.32 69.42 64.08 [

463 Nov 0617:32:23 60.32 69.43 64.08 i 464 Nov 0617:42:24 60.32 69.41 64.09 i 465 Nov 0617:52:24 60.32 69.42 64.08

) 466 Nov 0618:02:32 60.32 69.42 64.08 i

467 Nov 0618:12:25 60.32 69.43 64.09 I

i l

2 1

i i

) I J

l 1

) l 1

)

1 I

).

INIT 2 ILRT FIIAL REPORT

) APPENDIX F TYPE A TEST CDRRECTIONS The following table presents the Type A Test corrections for leakage pathways ISOLATED during the IIRT.

) Pen No. Description Local Leak Rate Test No. Minpath Ieakrate 1 Containment Spray 2BWS 6.1.2.d-1.14 0.9 scfh 11 RCDT pump Discharge 2BWs 6.1.2.d-1.10 0.4 scfh Isolation

) 21 Component Cooling 2BwVS 6.1.2.d-1.12 0.5 scfh 24 Component Cooling 2BwVS 6.1.2.d-1.12 0.4 scfh 25 Component Cooling 2BwVS 6.1.2.d-1.12 0.4 scfh 28 Chemical Volume 2BwVS 6.1.2.d-1.9 0.4 scfh Seal Water Return 70 Primary Sampling 2BwVS 6.1.2.d-1.8 0.4 scfh

) Total 3.4 scfh The following table presents the Type A Test corrections for penetrations that were repaired during the refuel outage and before the ILRT. This was also added to the Statistical Test 95% UCL penalty.

)

Pen No. Description Local Leak Rate Test No. Minpath Leakrate 5 Containment Chilled 2BwVS 6.1.2.d-1.21 1.4 scfh Water System 6 Containment Chilled 2BwVS 6.1.2.d-1.21 0.0 scfh

) Water System 8 Containment Chilled 2BwVS 6.1.2.d-1.21 1.2 scfh Water System 10 Containment Chilled 2BwVS 6.1.2.d-1.21 1.3 scfh Water System

) 27 PRT to Auto Gas 2BWS 6.1.2.d-1.11 0.0 scfh Analyzer 36 Primary Sampling 2BwVS 6.1.2.d-1.8 8.6 scfh 45 Primary Sampling 2BWS 6.1. 2. d-1. 8 0.0 scfh

) 52 Process Radiation 2BwVS 6.1.2.d-1.20 1.2 scfh Cnmt Air Sample o:\depts\rd79g\1.wpf pg 38

)

1 i

).

i UNIT 2 IIRT FINAL REPORT

)

Pen No. Description Ixx:al Leak Rate Test No. Minpath leakrate 55 N2 supply to SI 2BWS 6.1.2.d-1.22 0.0 scfh Accumulators

) 56 Service Air 2BwVS 6.1.2.d-1.16 0.0 scfh 63 Spare Penetration 2BWS 6.1.2.d-1.26 0.0 scfh 64 Spare Penetration 2BWS 6.1.2.d-1.26 0.0 scfh P-4 Cnmt Pressurization 2BwvS 6.1.2.d-1.24 0.0 scfh

) Penetration I-3 ILRT Test Taps 2BWS 6.1. 2. d-1. 7 0.0 scfh Refuel Transfer Tube and 2BWS 6.1.2.d-1.5 0.2 scfh ,

Sleeve Bellows ,

Total 13.9 scfh I

) I

)

b .

I

) j I

I l

o:\depts\rd79g\1.wpf pg 39 h

O, LNIT 2 ILRT FIIRL REPORT

.O APPENDIX G TYPE B AND C IDCAL LEAK RATE DATA local leak rate testing has been performed once (A2R03) since the last ILRT perfonned in 1991 (A2R02), and were performed before and after the ILRT performed in October of 1994 (A2R04). Results indicated for A2R03 and A2R04 O are "AS LEFT" LLRT values perfonned durincy the outages. Several Containment penetrations, including the containment airlocks and purge valves, are tested at more frequent intervals, as specified by the stations Technical Specifications. The results below represent the periodic Type B and C LLRTs performed at 18 month intervals as specified in 10CFR50 Appendix J.

PENETRATIONS SYSTEM IJRT RFEULTS A2R03 4/93 A2R04 11/94 seem sefh ZONE 1 ELEC 175.6 0.4 ZONE 2 ELEC 74.8 0.4 ZONE 3 ELEC 314.0 0.8 ZONE 4 ELEC 81.9 0.4 WEL X-FER WBE 31.2 0.4 O FUEL X-FER BELIDWS 47.3 0.4 EQUIPMENT HATCH 46.2 0.4 I-3 VQ 2.5 0.4 I-3 VQ 2.0 0.4 P-70 PS 84.5 0.7 P-70 PS 570.0 0.4 P-70 PS 45.2 0.5 O p_70 pS 64.3 0.5 P-45 PS 60.6 0.4 P-45 PS 240.0 0.4 P-36 PS 23.1 0.4 P-36 PS 102.4 9.0 P-41 CV 30.8 13.0 P-28 CV 773.0 1.2 O P-11 RE 52.7 0.4 P-65 RE 38.8 0.4 P-65 PE 108.1 13.0 P-27 RY 1475.0 0.6 P-27 RY 146.1 0.4 P-44 RY 595.0 0.4 I-5 RY 1510.0 0.7 O P-21 CC 1054.0 0.4 P-24 CC 48.3 0.4 P-25 CC 1364.0 11.5 P-32 FC 33.7 0.4 P-57 FC 56.2 0.4 P-1 CS 805.0 2.8 P- 16 CS 137.0 1.7 O P 39 IA 376.0 4.0 P-56 SA 655.0 2.7 P-30 WM 537.0 0.5 P-47 RF 921.0 0.4 P-13 OG 166.0 0.4 P-13 OG 133.0 0.4 P-69 OG 210.0 0.4 P-23 OG 232.0 0.4 O. p_52 PR 370.0 2.8 o:\depts\rd79 9\1.wpf pg 40 I O

l

  • 1 Oo l

UNIT 2 ILRT FINAL REPORT O \

APPENDIX G TYPE B AND C IOCAL LEAK RATE TEST DATA cont. I l

PDEI'P.ATIONS SYSTEM LLRT RESULTS (SC W) g A2R03 4/93 A2R04 11/94 P-52 PR 34.5 5.0 EQUIP. HATCH PR 94.2 0.4 PR 630.0 1.5 EMERG. HA'ICH PR 48.1 1.5 PR 490.0 0.8 P-5 WO 118.4 1.5 g P-8 WO 863.0 1.6 P-6 WO 420.0 2.7 P-10 WO 680.0 0.4 P-55 SI 117.8 3.0 P-55 SI 34.5 0.4 P-4 CPP 31.5 0.5 P-63 SPARE 85.5 0.4 3' P-64 SPARE 96.7 0.4 P-74 SPARE 16.8 0.4 EQUIP HATCH AIRIDCK 4810.0 20.5 FLANGE 2.6 0.4 D4 ERG HATCH AIRIOCK 618.0 3.8 FLANGE #1 77.5 0.4 FLANGE #2 75.2 0.4 P-97 VQ 1683.0 6.0

.) P-95 VQ 2140.0 18.0 P-96 VQ 353.0 0.9 P-94 VQ 418.0 1.0

)

l 1

l D

l t

o:\depts\rd79gi1.wpf pg 41 D

_ _ _ _ - - . _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - - _ - _