Appendix D Scenario Outline Form ES-D-1 Facility:

Davis-Besse Scenario No.:

3 Op Test No.:

DB NRC 2020 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 100% Power Turnover: SFAS Ch 2 RCS Pressure LO and LOLO Bistables have been tripped due to an instrument failure last shift.

Planned:

Stop #1 HDP for maintenance I&C to repair failed instrument and restore to service Critical tasks:

1. Isolate overcooling SG (CT-17)
2. Restore Seal Return or Shutdown the Reactor Coolant Pumps (CT-B)

Event No.

Malf.

No.

Event Type*

Event Description 1

N-BOP/SRO Stop #1 Heater Drain Pump for maintenance 2

C-ATC/SRO Makeup Filter High diff press 3

TS-SRO Containment Spray Pump Oil Leak (TS) 4 R-ATC/SRO C-BOP TS-SRO RCP 1-1 high vibrations - reduce power - trip RCP (TS) 5 C-BOP/SRO FW auto re-ratio fails when trip RCP 6

C-ATC/SRO Inadvertent SFAS Levels 1 through 3 - Trip reactor 7

Major OVCLG - Leaking Main Steam Safety Valve 8

C-BOP/SRO SFRCS fails to auto initiate on Low Steam Pressure (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 Facility:

Davis-Besse Scenario No.:

4 Op Test No.:

DB NRC 2020 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 100% Power Turnover: Maintain 100% Power Planned: Place cooling tower makeup (CTMU) pump 2 in service and stop CTMU pump 1.

Critical tasks:

1. Shutdown the Reactor - ATWS (CT-24)
2. Control HPI (CT-5)

Event No.

Malf.

No.

Event Type*

Event Description 1

N-BOP/SRO Swap Cooling Tower Makeup Pumps 2

TS-SRO RC TE3A6 Hot Leg temp to SCM meter (TS) 3 C-ATC/SRO MU32 fails closed (use alt inj line) 4 C-BOP/SRO TS-SRO Startup Transformer 02 Lockout (TS) 5 C-BOP/SRO MFP low oil pressure - trip MFP - runback works 6

R-ATC/SRO C-BOP SG Tube Rupture 7

Major ATWS - Key Switch Works 8

C-ATC/SRO PZR Spray valve fails closed (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 Facility:

Davis-Besse Scenario No.:

5 Op Test No.:

DB NRC 2020 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 100% Power Turnover: Maintain 100% Power Planned: Routine activities Critical tasks:

1. Isolate Overcooling SG (CT-17)
2. FW Flow Control (CT-16)
3. Control RCS Inventory (CT-30)

Event No.

Malf.

No.

Event Type*

Event Description 1

R-ATC/SRO TS-SRO D2 Lockout - Power reduction (TS) 2 C-BOP/SRO SAC 2 trip (SAC 1 and EIAC Auto start fail) 3 I-ATC/SRO Power range (NI5) high failure 4

I-BOP/SRO TS-SRO Place RPS Channel 2 in Manual Bypass (TS) 5 C-ATC/SRO Turbine Vibration - trip Rx 6

Major/ALL OVCLG - MSR 2ND STG FAIL 7

C-BOP/SRO AFP Target rock fails open - SG overfeed 8

C-ATC/SRO MUP Trip - Loss of Both MUPs (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor