Forwards Application for Amend to License NPF-69,revising SR 4.8.1.1.2.e.8 to Add Footnote Re 24 H Functional Test of Diesel Generators
ML20078B972
Person / Time
Site: Nine Mile Point 
Issue date: 10/21/1994
From: Sylvia B
NIAGARA MOHAWK POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20078B974 List:
References
NMP2L-1503, NUDOCS 9410270314
Download: ML20078B972 (2)


Text

,

RJ Y NIAGARA R UMOHAWK NIAGARA MOHAWK POWER CORPORATION / NICE MILE POINI PO. BOX 63. LYCOMING NY 13093/ TELEPHONE (315) 349-2682 B Ra!ph Sylvia Executive Vice President Nuclear October 21,1994 NMP2L 1503 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 RE: Nine Mile Point Unit 2 Docket No. 50-410 NPF-69 Gentlemen:

Niagara Mohawk Power Corporation hereby transmits an Application for Amendment to the Nine Mile Point Unit 2 Operating License NPF-69. Also enclosed as Attachment A is the proposed change to the Technical Specification as set forth in Appendix A to the above mentioned license. Supporting information and an analysis demonstrating that the proposed change involves no significant hazards consideration pursuant to 10CFR50.92 are included as Attachment B.

The proposed Technical Specification change contained herein represents a revision to Surveillance Requirement 4.8.1.1.2.e.8 to add a footnote regarding the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> functional test of the diesel generators. The proposed change would permit functional testing of the dicscis to be performed during power operation. Niagara Mohawk requests approval of this amendment by March 1,1995 to support the upcoming refueling outage.

Niagara Mohawk is submitting this Application for Amendment as a cost beneficial licensing action (CBLA). A direct cost avoidance of approximately $720,000 will occur by performing each 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> functional test of the three diesel generators during power operation. This change will result in a total cost savings of $10,800,000 over the life of the plant by reducing outage lengths by approximately three days.

Pursuant to 10CFR50.91(b)(1), Niagara Mohawk has provided a copy of this license amendment request and the associated analysis regarding no significant hazards consideration to the appropriate state representative.

Sincerely, h

~'-

B. Ralph Sylvia Executive Vice President - Nuclear BRS/KBT/ksj Enclosures 9410270314 941021 fDR ADOCK 0500 o

{

Q Page 2 xc:

Regional Administrator, Region I Mr. B. S. Norris, Senior Resident Inspector Mr. L. B. Marsh, Director, Project Directorate I-1, NRR Mr. D. S. Brinkman, Senior Project Manager, NRR Ms. Donna Ross Division of Policy Analysis and Planning New York State Energy Office Agency Building 2 Empire State Plaza Albany, NY 12223 Records Management 1