ML20077N392
| ML20077N392 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 08/31/1983 |
| From: | Dise D NIAGARA MOHAWK POWER CORP. |
| To: | Starostecki R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, 7293, NUDOCS 8309130067 | |
| Download: ML20077N392 (2) | |
Text
B^
M Y NIAGARA R UMOHAWK NBAGARA BA0 HAWK POWER CORPORATION /300 ERIE BOULEVARD WEST SYRACUSE, N.Y.13202/ TELEPHONE (315) 4741511 August 31, 1983 (7293)
Mr. R. W. Starostecki, Director U.S. Nuclear Regulatory Commission Region I Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point Unit 2 Docket No. 50-410
Dear Mr. Starostecki:
Enclosed is a 30-day interim report in accordance with 10CFR50.55(e) for the problem concerning Agastat Relay Base. This condition was reported via telecon to Mr. C. Holden of our staff on August 11, 1983.
Very truly yours, D. P. Dise Vice President Quality Assurance DPD/TL:ja Enclosure xc: Director of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555 Mr. R. Gramm, Resident Inspector 8309130067 830831 f
PDR ADOCK 05000410
) I S
/
i
NIAGARA M0 HAWK POWER CORPORATION i
NINE MILE POINT UNIT 2 DOCKET NO. 50-410 30-Day Interim Report for a Problem Concerning Agastat Relay Bases The problem pertains to Agastat relay bases installed in the panels of the Power Generation Control Complex (PGCC) by the General Electric Company.
During a Niagara Mohawk Quality Assurance surveillance (No. SRNMP2-101583), it was discovered that several safety related Agastat relay bases were not tightened to the metal channels in the panels to the torque specified in General Electric shop instructions.
In addition, fiber washers which were supposed to be included in the installation of the Agastat relay to the metal channel in accordance with shop instructions were also omitted in several General Electric installed connections.
During the surveillance, one base was discovered to be cracked.
This problem is under investigation by Niagara Mohawk and General Electric. A final report will be submitted by November 7, 1983.